| Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of Pacific 
              Gas and Electric's (PG&E's) proposed Windsor Substation Project. 
              An application for this project was submitted to the CPUC on April 21, 
              2010 (A.10-04-024) This site provides access to public documents 
              and information relevant to the CEQA review process. 
             Background The originally proposed Windsor Substation Project site was located 
              on Mitchell Lane in the southern part of the Town of Windsor, Sonoma 
              County, California. Subsequent to its original Application, PG&E 
              amended its Application and submitted a Supplemental PEA for substation 
              sited at a different location. The new site is in the northern part 
              of the Town, on Old Redwood Highway at Herb Road, between Highway 
              101 and the Northwestern Pacific Railroad (NWPRR) right of way. Electrical power would enter the substation by tapping the existing 
              Fulton No. 1 60 kV power line that parallels the west 
              side of the NWPRR right of way. Electrical power would leave the 
              substation as 12 kV via distribution feeder lines, which would 
              interconnect with the distribution network. Construction involves 
              the installation of the following components: 
              Construction of a 3-bank 115/12 kilovolt substation on 2.6 acres 
                of a 4.11-acre parcel on Old Redwood Highway at Herb Road in the 
                Town of Windsor, California. The substation would consist of the 
                following at full buildout: 
 
 
                  Three 115 kV bus structures
 
Six 115 kV circuit breakers
 
Three 115/12 kV power transformers
 
Eighteen 115 kV disconnecting switches
 
Three 12 kV metal-clad switchgear enclosures
 
Twelve 12 kV distribution circuits
 
Three 30 MVA power transformers
 
Connection of the new substation to on the Fulton No. 1 
                    60 kV power line by way of a new tubular steel pole [TSP] 
                    replacing an existing wood pole
 
Two 42-foot-high dead-end structures within the substation 
                    supporting the 60 kV power line entering and exiting 
                    the substation
 
Pole replacement and line work along Old Redwood Highway, Starr 
                Road, Gumview Road, Wilcox Road, Starr Circle, Railroad Avenue 
                and Joni Court.
 
Underground distribution lines connecting the substation to 
                existing and future infrastructure.
 
Rebuilding approximately 1.5 miles of the existing Fulton No. 
                1 60 kV power line, requiring replacement 39 wooden poles (with 
                38 wood poles and 1 steel pole) and installation of 2 new wood 
                riser poles.
 
Reconductoring approximately 1.8 miles of existing distribution 
                line with 12 kV double-circuit conductor along Old Redwood Highway, 
                requiring replacement of 44 wooden poles with taller wood poles 
                and installation of 3 additional wood riser poles. Proponent's Environmental Assessment 
              (PEA) PG&E filed a PEA with the Application 
              in April 2010. A Supplemental PEA 
              was submitted in May 2011. The PEA provides a starting point for 
              the independent environmental review process conducted by the CPUC. 
              In addition, PG&E's Notice of an Application for a Permit to 
              Construct can be found here. Environmental Review Process PG&E's Application and PEA were deemed complete for review 
              by the CPUC on May 20, 2010. However, the PEA was replaced 
              by the Supplemental PEA, submitted in 2011. The CPUC evaluated the 
              substation site and related project elements identified in the Supplemental 
              PEA. The CPUC determined that an Initial Study/Mitigated Negative Declaration 
              (IS/MND) appeared to be the appropriate CEQA document to prepare 
              for this project. After it was prepared, the Draft IS/MND was published 
              and the public and agencies had an opportunity to comment on the 
              document. Based on the Draft IS/MND, CPUC determined that an EIR 
              was not required. Draft Initial Study/Mitigated 
              Negative Declaration On July 15, 2013, the CPUC released a Notice of Intent to Adopt 
              a Mitigated Negative Declaration for the Windsor Substation Project 
              showing that the Proposed Project, as mitigated, would not have 
              any significant effects on the environment. The Draft Mitigated 
              Negative Declaration and Supporting Initial Study (IS/MND) can be 
              viewed here. The Draft IS/MND underwent a public review period from July 15, 
              2013 through August 14, 2013. Final Initial Study/Mitigated 
              Negative Declaration After the close of the comment period, CPUC prepared a Final Mitigated 
              Negative Declaration for the Windsor Substation Project. The Final 
              IS/MND can be viewed here. The study 
              showed that the Proposed Project, as mitigated, would not have any 
              significant effects on the environment. The Final MND provides details 
              on the Proposed Project, evaluates and describes its potential environmental 
              impacts, identifies those impacts that could be significant, and 
              presents mitigation measures to avoid or minimize these impacts. It is anticipated that the IS/MND would we adopted by the CPUC. Public Information Meeting The CPUC Energy Division held a public information meeting on August 16, 
              2010, to describe the then-proposed project, describe the CEQA process, 
              and receive public comments on the proposal. Written comments were 
              submitted at this meeting. Subsequent to the meeting, PG&E identified 
              its alternate site and submitted a supplemental PEA. For Additional Information To request additional information, ask a question, or be added 
              to the project mailing list, please contact: 
               
                | Voicemail or Fax:
 
 | (707) 657-0316 |   
                | U.S. Mail or Courier:
 | Eric Chiang California Public Utilities Commission
 c/o Aspen Environmental Group
 235 Montgomery Street, Suite 935
 San Francisco, CA 94104-3002
 |   
                | Email: | windsorsubstation@aspeneg.com |  |