|  
               
              Welcome to the California Public Utilities Commission (CPUC) website 
              for the permitting and construction of the Southern California Edison 
              (SCE) Antelope-Pardee 500 kV Transmission Line Project. This project 
              included a 25.6-mile 500-kV single-circuit transmission line which 
              replaced an existing 66-kV line between the Antelope Substation 
              in Lancaster and the Pardee Substation in Santa Clarita, in northern 
              Los Angeles County, including approximately 13 miles within the 
              Angeles National Forest (ANF). The project also included electrical 
              interconnections at the existing Antelope and Pardee Substations, 
              as well as an expansion of the Antelope Substation and relocation 
              of several existing 66-kV subtransmission lines in the vicinity 
              of the Antelope Substation. SCE submitted an application for a Certificate 
              of Public Convenience and Necessity (CPCN) for this project to the 
              CPUC on December 9, 2004. SCE also submitted an application for 
              a Special Use Easement to the USDA Forest Service. The Project was 
              reviewed under both the California Environmental Quality Act (CEQA) 
              and National Environmental Policy Act (NEPA). 
            
 This site provides access to public documents and information relevant 
              to the permitting, CEQA and NEPA review processes, and construction 
              of the Project. 
             PROJECT STATUS
            The Final Environmental Impact Report/Environmental Impact Statement 
              (Final EIR/EIS) was certified and a Certification of Public Convenience 
              and Necessity (CPCN) was granted by CPUC (Docket #A.04-12-007, SCH 
              #2005061161) on March 1, 2007. The USDA Forest Service issued 
              a Record of Decision (ROD) on August 23, 2007. Project construction 
              occurred between March 2008 and September 2009. 
             Pre-Construction Compliance
            Notices to Proceed (NTPs) were issued by CPUC by subsection of 
              the project as requested by SCE. A summary of NTPs issued for 
              the Antelope-Pardee Project is provided in Table 1 below, as well 
              as any NTP modifications/addendums and Forest Service approvals. 
              Issuance of NTPs was contingent upon SCE's compliance with pre-construction 
              requirements as specified by the approved mitigation measures and 
              responsible agency permitting requirements. 
            
               
                |  
                   TABLE 1: NOTICES TO PROCEED 
                 | 
               
               
                |  
                   NTP # 
                    Permit  
                 | 
                 
                   Date Requested 
                 | 
                 
                   Date 
                    Issued  
                 | 
                 
                   Segment 
                 | 
                 
                   Description 
                 | 
               
               
                |  
                   #1 
                 | 
                 
                   10/10/07 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Use of the Mojave Marshalling Yard to store construction 
                  equipment and materials. | 
               
               
                |  
                   #2 
                 | 
                 
                   11/16/07 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Antelope Substation construction and expansion, 
                  and use of two adjacent contractor laydown yards. | 
               
               
                |  
                   #2 Mod 
                 | 
                 
                   12/21/07 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Grading at Antelope Substation site and yards. 
                  Replacement of an existing 80 foot microwave tower with a new 
                  120 foot tower within the fenced area of the Antelope Substation. | 
               
               
                |  
                   #3 
                 | 
                 
                   1/10/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Use of five contractor laydown yards: Pumpkin 
                  Yard, Pottery Yard, Pardee Substation Yard, Mechanics Yard and 
                  Avenue I Yard. | 
               
               
                |  
                   #4 
                 | 
                 
                   1/29/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Use of the Racetrack Marshalling Yard. | 
               
               
                |  
                   #5 
                 | 
                 
                   2/19/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Shoofly Construction, Section 1. | 
               
               
                |  
                   #5 Mod #1 
                 | 
                 
                   3/11/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Use of a new soil disposal site for the Shoofly 
                  construction, Section 1. | 
               
               
                |  
                   #5 Mod #2 
                 | 
                 
                   3/24/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Removal of the 66 kV conductors on the Del Sur-Saugus 
                  line during the outage scheduled for March 27, 2008.s | 
               
               
                |  
                   #6 
                 | 
                 
                   3/19/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Use of three additional construction yards, Rodeo, 
                  Blue Cloud, and Pumpkin expansion. Rodeo yard approved under 
                  NTP #9.  | 
               
               
                |  
                   #7 
                 | 
                 
                   4/03/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Section 1 Construction. | 
               
               
                |  
                   #8 
                 | 
                 
                   5/01/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                10 acre marshalling yard near Antelope Substation. | 
               
               
                |  
                   #9 
                 | 
                 
                   3/18/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Rodeo Yard | 
               
               
                |  
                   #10 
                 | 
                 
                   6/02/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                12 kV line (Hughes Lake Distribution Line). | 
               
               
                |  
                   #11 
                 | 
                 
                   6/03/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Section 3 construction. | 
               
               
                |  
                   #12 
                 | 
                 
                   6/27/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Hydrant Yard | 
               
               
                |  
                   #13 
                 | 
                 
                   7/17/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Removal of the 66 kV conductors within the ANF, 
                  Phase 1, from tower 7-3 (near southern Forest boundary) to 16-3 
                  (near Bouquet Reservoir). | 
               
               
                |  
                   #15 
                 | 
                 
                   9-24-08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Removal of the 66 kV conductors within the ANF, 
                  Phase 2. | 
               
               
                |  
                   #16 
                 | 
                 
                   10/01/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Section 3, Reitano Marshalling yard. | 
               
               
                |  
                   #18 
                 | 
                 
                   10/24/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Section 2 Construction (Angeles National Forest) | 
               
               
                |  
                   #CPUC Addendum #1 
                 | 
                 
                   8/04/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Reclassify several roads as permanent and leave 
                  several existing foundations in place. | 
               
               
                |  
                   #24 
                 | 
                 
                   10/07/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Relocation of 66kV lines for Antelope Substation 
                  expansion. | 
               
               
                |  
                   #CPUC Addendum #2 
                 | 
                 
                   11/06/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Reclassify several roads for Antelope 66kV relocation 
                  and Reitano property as permanent. | 
               
               
                |  
                   #26 
                 | 
                 
                   12/18/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Expansion of Antelope Substation | 
               
               
                |  
                   #CPUC Addendum #3 
                 | 
                 
                   12/21/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Permanent refueling basin at Hydrant Yard | 
               
               
                |  
                   #29 
                 | 
                 
                   2/10/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Relocation of the Sagebrush Transmission Line 
                  at the Antelope Substation expansion area | 
               
               
                |  
                   #CPUC Addendum #4 
                 | 
                 
                   4/16/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Installation of fiber optics surrounding the Antelope 
                  Expansion | 
               
               
                |  
                   #CPUC Addendum #5 
                 | 
                 
                   5/25/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Permanent overland travel routes for Operation 
                  and Maintenance inspections | 
               
               
                |  
                   USDA Forest Service Permtting & Modifications 
                    (ANF lands only) 
                 | 
               
               
                |  
                     
                 | 
                 
                   11/29/07 
                 | 
                 
                   12/14/07 
                 | 
                 
                   1 
                 | 
                Radio Repeater - installation of a temporary radio 
                  repeater site on Sierra Pelona Ridge to provide communication 
                  during construction activities tied to the project. Improvement 
                  installation began Jan. 11  | 
               
               
                |  
                     
                 | 
                 
                   9/27/07 
                 | 
                 
                   12/14/07 
                 | 
                 
                   1 
                 | 
                Geotechnical testing - 23 geotechnical borings 
                  are authorized on National Forest lands to provide additional 
                  information that will be used in the design of the transmission 
                  towers. Notice to proceed was signed Jan 31 to begin work the 
                  week of Feb. 3 | 
               
               
                |  
                     
                 | 
                 
                  
                 | 
                 
                   7/14/08 
                 | 
                 
                   1 
                 | 
                Removal of the 66 kV conductor within the ANF, 
                  from tower 7-3 (near southern Forest boundary) to 16-3 (near 
                  Bouquet Reservoir) Phase I. | 
               
               
                |  
                     
                 | 
                 
                     
                 | 
                 
                   9/23/08 
                 | 
                 
                   1 
                 | 
                Removal of the 66 kV conductor within the ANF, 
                  Phase II | 
               
               
                |  
                     
                 | 
                 
                     
                 | 
                 
                   10/23/08 
                 | 
                 
                   1 
                 | 
                Construction of the 500 kV transmission line and 
                  wreck out of the 66 kV towers in the ANF, Section 2. | 
               
             
            Other responsible agency permits required for construction, and 
              their amendments, are listed here. Major 
              compliance plans requiring CPUC and/or permit agency review and 
              approval included the following.  
            
              - Sensitive Biological Habitat Survey Reports 
 
              -  Bird Nesting Survey Reports 
 
              -  Restoration Plans
 
              -  Storm Water Pollution Prevention Plans (SWPPPs)
 
              -  Spill Prevention Control and Countermeasure Plans (SPCCs)
 
              -  Fugitive Dust Control Plans 
 
              -  Paleontological Resources Discovery and Management Plans 
 
              -  Cultural Resources Treatment Plans 
 
              -  Phase I and II Site Investigation Reports
 
              -  Waste Characterization and Management Plans
 
              -  Worker Environmental Awareness Program Plans
 
              -  Health and Safety Plans 
 
              -  Construction Safety and Emergency Response Plans 
 
              -  Fire Prevention Plans
 
              -  Construction Transportation/Traffic Plans 
 
             
             Construction Monitoring & Variance Review
            CPUC Environmental Monitors monitored construction activities to 
              ensure that construction was conducted in accordance with the approved 
              mitigation measures and permit conditions. Weekly reports documenting 
              construction and monitoring activities are posted here. 
            As final engineering was completed and as construction necessitated, 
              Variance Requests were submitted for the Project. A summary of the 
              Variance Requests is provided in Table 2 below. Each of these requests 
              was reviewed by CPUC to ensure that no new impacts or increase in 
              impact severity would result from the requested change. 
            
               
                |  
                   TABLE 2: VARIANCE REQUESTS 
                 | 
               
               
                |  
                   Variance 
                    Request 
                 | 
                 
                   Date Requested 
                 | 
                 
                   Date 
                    Issued  
                 | 
                 
                   Segment 
                 | 
                 
                   Description 
                 | 
               
               
                |  
                   VR #1 
                 | 
                 
                   4/01/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Temporary road along Shoofly portion. | 
               
               
                |  
                   VR #2 
                 | 
                 
                   4/18/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Several expanded stringing sites, new staging 
                  areas, and guard structure installation sites for the removal 
                  of the 220 kV line. | 
               
               
                |  
                   VR #3 
                 | 
                 
                   4/24/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Weekend work along the Shoofly portion of Section 
                  1, within the City of Santa Clarita and Los Angeles County, 
                  and at the Antelope Substation, Avenue J, in the City of Lancaster. 
                 | 
               
               
                |  
                   VR #4 
                 | 
                 
                   5/08/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Weekend work along the 66 kV line in Section 1 
                 | 
               
               
                |  
                   VR #5 
                 | 
                 
                   7/15/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Wreck-out Tower and Guard Poles | 
               
               
                |  
                   VR #6 
                 | 
                 
                   7/30/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Modification to the notice and review requirements 
                  under Mitigation Measures L-5 and L-6. | 
               
               
                |  
                   VR #7 
                 | 
                 
                   8/12/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Wire Stringing site in Section 1 between NC 11 
                  and 12. | 
               
               
                |  
                   VR #8 
                 | 
                 
                   8/20/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Guard structures at Haskell Canyon outside of 
                  approved disturbance areas. | 
               
               
                |  
                   VR #9 
                 | 
                 
                   8/19/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Valuzet Movie Ranch Helicopter Landing Zone, Section 
                  1. | 
               
               
                |  
                   VR #10 
                 | 
                 
                   8/21/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Permission to leave one tower foundation in place 
                  at wreck out tower 24/2 in Section 1, due to likelihood of slope 
                  failure. | 
               
               
                |  
                   VR #11 
                 | 
                 
                   9/12/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                New temporary road construction to NC 97 in Section 
                  3. | 
               
               
                |  
                   VR #13 
                 | 
                 
                   9/16/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Turn around for equipment at NC 28 in Section 
                  1 | 
               
               
                |  
                   VR #15 
                 | 
                 
                   9/20/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Access road changes, Section 3 | 
               
               
                |  
                   VR #17 
                 | 
                 
                   10/14/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Extended weekend work hours between NC 22 & 23 
                  Haskell Canyon utility crossings | 
               
               
                |  
                   VR #18 
                 | 
                 
                   10/15/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Wreck-out Tower 25/5 disturbance area and access 
                  road and footing removal. Segment 1, Section 3. | 
               
               
                |  
                   VR #19 
                 | 
                 
                   11/05/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Use of existing disturbance areas as helicopter 
                  landing zones, Section 1 | 
               
               
                |  
                   VR #20 
                 | 
                 
                   11/05/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Use of existing disturbance areas as helicopter 
                  landing zones, Section 3 | 
               
               
                |  
                   VR #21 
                 | 
                 
                   11/24/08 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Approved to leave two foundations in place at 
                  wreck-out tower 25/1 | 
               
               
                |  
                   VR #23 
                 | 
                 
                   1/07/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Additional disturbance area near Tower 25 and 
                  Wire Stringing Site 14 on Section 1 | 
               
               
                |  
                   VR #24 
                 | 
                 
                   1/08/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Underground fiber optic line for Tower 13 on Section 
                  1 | 
               
               
                |  
                   MOD  
                    VR #24 
                 | 
                 
                   2/20/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Modify fiber optic line alignment to Tower 13 | 
               
               
                |  
                   VR #25 
                 | 
                 
                   1/13/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Work on Sunday, January 18, during LADWP outage 
                  over Haskell Canyon | 
               
               
                |  
                   VR #26 
                 | 
                 
                   1/20/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Permanent lift Tower M88-T1A southwest side Antelope 
                  Substation | 
               
               
                |  
                   VR #27 
                 | 
                 
                   1/29/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Extension of approved construction work hours 
                  Towers 22 and 23 (Haskell Canyon Crossing) | 
               
               
                |  
                   VR #28 
                 | 
                 
                   2/02/09 
                 | 
                 
                   2/04/09 
                 | 
                 
                   1 
                 | 
                Second wire stringing site for Tower 16 | 
               
               
                |  
                   VR #32 
                 | 
                 
                   3/03/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Nighttime wire removal across Newhall Ranch Road, 
                  City of Santa Clarita | 
               
               
                |  
                   VR #33 
                 | 
                 
                   3/04/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Hydrant Yard nighttime emergency helicopter repairs 
                  Monday through Saturday | 
               
               
                |  
                   VR #34 
                 | 
                 
                   3/12/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Sunday work on March 15th - permanent transfer 
                  of temporary shoo-fly transmission towers to the new permanent 
                  A-P 500kV double-circuit T/L (Section 1) | 
               
               
                |  
                   VR #36 
                 | 
                 
                   3/09/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Heavy-lift helicopter (sky crane) Section 2 - 
                  Upper Pumpkin Yard, Hydrant and Reitano Yard use. | 
               
               
                |  
                   VR #37 
                 | 
                 
                   3/30/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Installation of an underground conduit near Tower 
                  11 (Section 1) | 
               
               
                |  
                   VR #42 
                 | 
                 
                   4/28/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Expansion of Wire Stringing Site 13 (Section 1) | 
               
               
                |  
                   VR #45 
                 | 
                 
                   4/28/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Use of alternate access near Bouquet Reservoir 
                  to access Wire Stringing Site 23 | 
               
               
                |  
                   VR #53 
                 | 
                 
                   7/29/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Modification to existing Tower M24-T1 (Section 
                  1) | 
               
               
                |  
                   VR #60 
                 | 
                 
                   10/15/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Modification to MM PH-6, notification timing for 
                  energization | 
               
               
                |  
                   VR #65 
                 | 
                 
                   12/18/09 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                66 kV relocation shoo-fly | 
               
               
                |  
                   VR #66 
                 | 
                 
                   1/11/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Modify the requirements of MM B-1a to fulfill 
                  a request from the property owner | 
               
               
                |  
                   VR #68 
                 | 
                 
                   4/09/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Release restoration requirements on road to wreck-out 
                  Tower 20-4 (Section 3) | 
               
               
                |  
                   VR #69 
                 | 
                 
                   5/04/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Contractor Yards surrounding Antelope Substation | 
               
               
                |  
                   MOD  
                    VR #69 
                 | 
                 
                   7/29/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Additional space for storage at Antelope Substation 
                  for material being delivered for Antelope, Vincent and Whirlwind 
                  Substations | 
               
               
                |  
                   VR #70 
                 | 
                 
                   6/02/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Additional disturbance areas adjacent to tower 
                  erections for 220 kV Sagebrush relocation work around Antelope 
                  Substation | 
               
               
                |  
                   VR #71 
                 | 
                 
                   6/22/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Change in construction work hours for work on 
                  the Sagebrush 220 kV T/L | 
               
               
                |  
                   MOD #1 
                    VR #71 
                 | 
                 
                   6/24/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Expansion of construction hours for Sagebrush 
                  220 kV T/L and foundation installation work at Antelope Substation | 
               
               
                |  
                   MOD #2 
                    VR #71 
                 | 
                 
                   7/08/10 
                 | 
                
                  
                 | 
                 
                   1 
                 | 
                Further expansion of construction hours for Antelope 
                  Substation construction | 
               
               
                |  
                   MOD #3 
                    VR #71 
                 | 
                 
                   11/18/10 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Further expansion of construction hours for Antelope 
                  Substation construction | 
               
               
                |  
                   VR #72 
                 | 
                 
                   2/07/12 Revised 6/06/12 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Exemption of restoration requirements in areas 
                  where livestock grazing has occurred | 
               
               
                |  
                   VR #74 
                 | 
                 
                   7/30/14 
                 | 
                 
                  
                 | 
                 
                   1 
                 | 
                Exemption of restoration requirements for selected 
                  locations | 
               
             
              
              BACKGROUND
            Final Environmental Impact Report/Environmental Impact Statement 
            
            In accordance with CEQA and NEPA, an Environmental Impact Report/Environmental 
              Impact Statement was prepared for the proposed Project. The Final 
              Environmental Impact Report/Environmental Impact Statement (Final 
              EIR/EIS) was certified and a Certification of Public Convenience 
              and Necessity (CPCN) was granted by CPUC (Docket #A.04-12-007, SCH 
              #2005061161) on March 1, 2007. The CPUC approved a project 
              alignment that included the originally proposed alignment (northern 
              and southern ends) and a combination of Alternatives 2 and 4. Maps 
              of the approved alignment are provided below, in the link provided 
              to the Final EIR/EIS. 
            The Final EIR/EIS was prepared in December 2006 and issued in early 
              January 2007. The Final EIR/EIS consists of two volumes. Volume 
              I is a re-printed version of the Draft EIR/EIS. Changes made to 
              the Draft EIR/EIS in Volume I are identified as follows: inserted 
              text is underlined and deleted text is shown in strikeout. Volume 
              II consists of all comments received on the Draft EIR/EIS and responses 
              to those comments, as well as the mitigation monitoring plan. 
            The CPUC released the Draft EIR/EIS for the proposed Project on 
              July 21, 2006. The public comment period for this document 
              ended on October 3, 2006. All comments received on the Draft EIR/EIS 
              were responded to in the Final EIR/EIS, Volume II, as discussed 
              above. 
              CEQA requires that the CPUC provide written responses to public 
              agency comments at least 10 days prior to certifying an EIR (Public 
              Resource Code 21092.5(a)). This was accomplished by sending the 
              Final EIR to all agencies that commented. 
            NEPA Process and USDA Forest Service Record of Decision
            The U.S. EPA's Office of Federal Activities published a Notice 
              of Availability of the Final EIS in the Federal Register on January 19, 
              2007. The USDA Forest Service issued a Record of Decision (ROD) 
              on August 23, 2007, which states the decision, identifies all 
              alternatives considered, and describes applicable mitigation. The 
              Forest Service also approved an alignment comprised of a combination 
              of Alternatives 2 and 4. Two Notices of Appeal were filed on the 
              ROD. On November 19, 2007, the USDA Forest Service Appeal Reviewing 
              Officer (ARO) found that the Forest Supervisor's decision was appropriate 
              and complied with existing laws, policies, and regulations. 
            OTHER DOCUMENTS AVAILABLE
             
              Final 
                Decision Granting a CPCN 
               
               USDA Forest Service Record 
                of Decision (August 23, 2007) 
              Notice of Availability of the Final EIR/EIS 
                (December 29, 2006) 
              Notice of Extension of the Draft EIR/EIS 
                review period (September 13, 2006) 
              Notice of Availability of the Draft 
                EIR/EIS (July 21, 2006) 
              Federal Register Notice of Intent to prepare 
                a joint environmental impact statement/report (June 28, 
                2005) 
              Notice of Preparation of an EIR/EIS (June 
                24, 2005) 
              SCE's Proponent's Environmental Assessment 
                (December 9, 2004) 
              More 
                Construction photos 
              Informational 
                Video (26MB) 
             
            For Additional Information 
            
               
                |  
                   To request 
                    additional information, please contact CPUC as follows: 
                 | 
               
               
                |  
                  
                 | 
               
             
           |