             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of Southern 
              California Edison's (SCE's) proposed Banducci Substation Project 
              (Proposed Project). An Application for this project was submitted 
              to the CPUC on November 15, 2012. The CPUC approved the Proposed 
              Project and granted SCE a Permit to Construct (PTC) on June 11, 
              2015. This website provides access to public documents and information 
              relevant to the CEQA review process and construction monitoring 
              for the Proposed Project. 
              
               
                Application A.12-11-011 
                  Decision D.15-06-009 
               
             
            PROJECT STATUS 
            The Final MND was adopted by the CPUC on June 11, 2015 in Decision 
              D.15-06-009. In accordance with CEQA, a Mitigation Monitoring, Compliance, 
              and Reporting Plan (MMCRP) was prepared to ensure compliance with 
              the mitigation measures approved in the MND. The MMCRP is available 
              here. SCE started construction of the Banducci 
              Substation Project on July 26, 2017, and the majority of construction 
              activities were completed by June 2018; testing and driveway paving 
              remain. The Final Report documenting construction and compliance 
              activities is available here 
              (17MB). 
            Pre-construction Compliance and 
              Notices to Proceed 
            Notices to Proceed (NTPs) were issued by CPUC by subsection of 
              the project as requested by SCE. Issuance of NTPs was contingent 
              upon SCE's compliance with pre-construction requirements as specified 
              by the approved mitigation measures and responsible agency permitting 
              requirements. Table 1 summarizes the Banducci Substation Projects 
              NTPs issued.  
            
               
                 
                    
                    Table 1. Notices to Proceed (NTPs) 
                       
                 | 
               
               
                |  
                   NTP No. 
                 | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date Issued 
                 | 
                Phase | 
                Description | 
               
               
                |  
                   NTP #1 
                 | 
                 
                   11/22/16 
                 | 
                 
                  
                 | 
                Banducci Substation and Subtransmission | 
                Construction of the Banducci Substation 
                  and the associated 69 kV subtransmission features located on 
                  Pelliser Road near the town of Tehachapi. | 
               
               
                |  
                   NTP #2 
                 | 
                 
                   07/31/17 
                 | 
                 
                  
                 | 
                Telecommunications | 
                Telecommunications related components 
                  of the Banducci Substation (see MPC #1, Table 2). | 
               
               
                |  
                   NTP #3 
                 | 
                 
                   02/07/17 
                 | 
                 
                  
                 | 
                12 kV Distribution Getaways and a Portion 
                  of the Telecommunication Route #1 | 
                Construction of the distribution getaways 
                  and a portion of Telecommunication Route #1 along Pelliser 
                  and Highline Roads. | 
               
             
            Other responsible agency permits required for construction, and 
              their amendments, are listed in the MMCRP (see above). Major compliance 
              plans requiring CPUC and/or permit agency review and approval included 
              the following: 
            
              - Preconstruction Survey Reports
 
               
              - Salvage and Relocation Plan, if special-status plants can not 
                be avoided.
 
              - Habitat Restoration Plan for Tehachapi Slender Salamander, if 
                occupied habitat is directly impacted
 
              - Nesting Bird Management Plan
 
              - Ecological Restoration Plan / Compensation Plan, if avoidance 
                is not feasible
 
              - Jurisdictional Delineation Reports
 
              - Cultural Resources Treatment Plan
 
              - Paleontological Resources Management Plan
 
              - Geotechnical Report
 
              - Fire Management Plan
 
              - Restoration Plans as necessary
 
              - Storm Water Pollution Prevention Plans (SWPPPs)
 
              - Worker Environmental Awareness Program Plans
 
             
            Construction Monitoring and Minor 
              Project Change Review 
            CPUC Environmental Monitors monitored construction activities to 
              ensure that construction was conducted in accordance with the approved 
              mitigation measures and permit conditions. Monitoring reports documenting 
              construction and monitoring activities are available here. 
            As final engineering was completed or as construction necessitated, 
              Minor Project Changes (MPCs) were submitted by SCE for the Project. 
              Each of these requests was reviewed by CPUC to ensure that no new 
              impacts or increase in impact severity would result from the requested 
              change. Table 2 provides a summary of the MPCs submitted for 
              the Banducci Substation Project. 
            
               
                 
                    
                    Table 2. Minor Project Changes (MPCs) 
                       
                 | 
               
               
                | MPC No. | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date Issued 
                 | 
                Phase | 
                Description | 
               
               
                |  
                   MPC #1 
                 | 
                 
                   07/31/17 
                 | 
                 
                  
                 | 
                Telecom | 
                Changes to Telecommunication Routes #1 
                  and #2 (see NTP #2, Table 1). | 
               
               
                |  
                   MPC #2 
                 | 
                 
                   08/09/17 
                 | 
                 
                  
                 | 
                12 kV | 
                Relocation of 12 kV distribution 
                  infrastructure to avoid an existing, unmarked utility. | 
               
               
                |  
                   MPC #3 
                 | 
                 
                   08/21/17 
                 | 
                 
                  
                 | 
                Substation | 
                Extend use of water source for duration 
                  of project (originally approved under a TEWS). | 
               
               
                |  
                   MPC #4 
                 | 
                 
                   11/06/17 
                 | 
                 
                  
                 | 
                Telecom | 
                Change to Telecommunication Route #2. | 
               
               
                |  
                   MPC #5 
                 | 
                 
                   03/06/18 
                 | 
                 
                  
                 | 
                Substation | 
                Adjustments to Substation level of 
                  disturbance and GIS changes to reflect final build. | 
               
             
             
              BACKGROUND 
            Project Description 
            The proposed Banducci Substation Project includes the following 
              components: 
            
              - Construction of a new Banducci 66/12 kilovolt (kV) Substation. 
                Banducci Substation would be an unstaffed, automated, 56.0 megavolt-ampere 
                (MVA), low-profile substation with a potential capacity of 112 
                MVA at final buildout. The proposed 66/12 kV distribution substation 
                would be located on an approximately 6.3 acre parcel in the unincorporated 
                Cummings Valley area of Kern County.
 
                 
               
              - Construction of two new 66 kV subtransmission line segments 
                that would loop the existing Correction-Cummings‒Kern River 
                1 66 kV Subtransmission Line: one that would enter and one that 
                would exit the proposed Banducci Substation creating the new Banducci‒Kern 
                River 1 66 kV Subtransmission Line and the new Banducci-Correction-Cummings 
                66 kV Subtransmission Line.
 
                 
               
              - Construction of three new underground 12 kV distribution getaways.
 
                 
               
              - Installation of telecommunications facilities to connect the 
                proposed Banducci Substation to SCE's existing telecommunications 
                system.
 
               
             
            The Banducci Substation site is located at the southeast corner of 
            Pelliser Road and unimproved Dale Road in unincorporated Cummings 
            Valley, Kern County. The subtransmission line upgrades would occur 
            on new and replacement poles along Pelisse Road in close proximity 
            to the substation. Telecommunications upgrades would include installation 
            of fiber optic cable within existing SCE rights-of-way, overhead on 
            existing and replacement poles and underground in new conduit. A total 
            of approximately 32 miles of fiber optic cable would be installed 
            between the proposed Banducci Substation and the existing Cummings 
            and Monolith Substations, both near the City of Tehachapi, Kern County. 
            Construction would last approximately 12 months. SCE states that the 
            Proposed Project is needed to serve increased electrical demand and 
            to address reliability and operational flexibility issues in the Electrical 
            Needs Area. In accordance with the CPUC's General Order 131 D, approval 
            of this project must comply with CEQA. 
            Environmental 
              Review Process 
            SCE filed its original Proponent's Environmental Assessment (PEA) 
              with the Application on November 15, 2012. The PEA provided a starting 
              point for the environmental review process that is to be conducted 
              by the CPUC. After reviewing the 2012 PEA, CPUC directed SCE to 
              supplement and submit additional information. A number of requests 
              and responses ensued, culminating in SCE submitting an amended PEA 
              dated June 6, 2014. 
             
               
                Original Proponent's Environmental Assessment 
                  2012 (superseded) 
                  Amended Proponent's Environmental Assessment 
                  2014 
               
             
            Original (2012) 
              PEA Review 
            SCE's Application and original PEA were reviewed by the CPUC. The 
              Energy Division sent a letter to SCE on December 17, 2012, 
              indicating that the submitted PEA for the Banducci Substation required 
              supplementation and resubmission. 
             
               
                PEA Completeness Letter 
                  #1 
               
             
            SCE subsequently submitted supplemental information to the CPUC 
              on February 5, 2013. 
             
               
                Supplemental PEA Information 
                  #1 
               
             
            The Energy Division sent a letter to SCE on February 25, 2013, 
              indicating that the PEA for the Banducci Substation requires further 
              supplementation and resubmission. 
             
               
                PEA Completeness Letter 
                  #2 
               
             
            In response, SCE submitted additional supplemental information 
              to the CPUC on April 19, 2013. 
             
               
                Supplemental PEA Information 
                  #2 
               
             
            After reviewing the supplemental information, the Energy Division 
              sent a letter to SCE on May 8, 2013, indicating that the PEA 
              for the Banducci Substation again requires further supplementation 
              and resubmission. 
             
               
                PEA Completeness Letter 
                  #3 
               
             
            In response, SCE submitted additional supplemental information 
              to the CPUC on June 3, 2013: 
             
               
                Response to Question #1, 
                  Right-of-Way Description and Land Rights Definitions 
                  Response 
                  to Question #2, Soil Types GIS Data (.zip file; right-click 
                  to download)  
                  Response 
                  to Question #3, Vegetation GIS Data (.zip file; right-click 
                  to download) 
                  Response to Question 
                  #4, Cultural Resources Survey Description (PDF) 
                  Revised 
                  Mapping Suite of Data Package (.mpk file; right-click to 
                  download) 
               
             
            After reviewing all supplemental information, the Energy Division 
              sent a letter to SCE on July 2, 2013, indicating that SCE has 
              submitted all necessary information at this time. However, in order 
              to deem the PEA complete, the CPUC requested that SCE re-file the 
              PEA in its entirety in the format consistent with the CPUC's PEA 
              Checklist for Transmission Line Projects (2008). 
             
               
                PEA Completeness Letter 
                  #4 
               
             
            Amended (2014) 
              PEA Review 
            The requested Amended PEA was submitted in June 2014. 
             
               
                Amended PEA 2014 
               
             
            After a completeness review of the amended PEA, the CPUC deemed 
              SCE's Application and PEA complete on July 15, 2014. 
             
               
                PEA Completeness Letter 
                  #5 
               
             
            Mitigated Negative 
              Declaration Preparation 
            On November 14, 2014, the CPUC released a Notice of Intent to Adopt 
              a Mitigated Negative Declaration (MND) for the Banducci Substation 
              Project, showing that the Proposed Project, as mitigated, would 
              not have any significant effects on the environment. 
             
               
                Draft Initial Study/Mitigated Negative 
                  Declaration (IS/MND)  
               
             
            The Proposed IS/MND was made available for public review and comment 
              from November 14, 2014, through December 15, 2014. 
            In order to help affected communities understand the Proposed Project 
              and the Proposed IS/MND and to explain how the public can participate 
              in the CPUC's decision-making process, the CPUC held an informational 
              meeting on December 11, 2014, at the Tehachapi Police Department, 
              Community Room. 
            On March 10, 2015, the CPUC released a Final Mitigated Negative 
              Declaration, showing that the Banducci Substation Project, as mitigated, 
              would not have any significant effects on the environment. The Final 
              IS/MND details the Proposed Project, evaluates and describes its 
              potential environmental impacts, identifies those impacts that could 
              be potentially significant, and presents mitigation measures to 
              avoid or minimize these impacts. 
             
               
                Final Initial Study/Mitigated Negative 
                  Declaration (IS/MND)  
               
             
            For Additional 
              Information 
            To request additional information, please contact the CPUC, as 
              follows: 
            Mary Jo Borak, CPUC Project Manager 
              c/o Aspen Environmental Group  
              235 Montgomery Street, Suite 935  
              San Francisco CA 94104 
              Email:  maryjo.borak@cpuc.ca.gov 
           |