|  
             Welcome to the California Public Utilities Commission (CPUC) web 
              site for the California Environmental Quality Act (CEQA) review 
              of Pacific Gas and Electric's (PG&E's) proposed Cressey-Gallo 
              115 kV Power Line Project. An application for this project was submitted 
              to the CPUC on November 30, 2011 (A.11-11-020). This site provides 
              access to public documents and information relevant to the CEQA 
              review process.
             Background 
            In its 2011 application, Pacific Gas and Electric Company (PG&E) 
              proposed to construct the Cressey-Gallo 115 Kilovolt (kV) Power 
              Line Project, a new, approximately 14.4-mile-long, single-circuit 
              power line needed to improve transmission system reliability for 
              customers in north-central Merced County, California. 
            The project consisted of constructing a new 115 kV power line between 
              Cressey and Gallo Substations to form a power line loop with two 
              other area substations (Livingston and Atwater). The new transmission 
              loop allows power to flow from another direction when there is an 
              outage on a line feeding the loop, avoiding customer service interruptions 
              from single-line outages in this area. As proposed by PG&E, 
              the project included: 
            
              - Constructing a new, approximately 14.4-mile, single-circuit 
                115 kV power line interconnecting Cressey Substation and Gallo 
                Substation.
 
                 
               
              - Upgrading the bus configurations at Cressey Substation and replacing 
                the existing radial power line transition into the substation 
                within the existing substation property.
 
                 
               
              - Expanding Gallo Substation to add switchgear and upgrade the 
                bus configurations.
 
             
            The project is located in the San Joaquin Valley in Merced County 
              near the City of Livingston, California. The project route is oriented 
              primarily east to-west between Cressey Substation and Gallo Substation, 
              intersecting with State Route 99 south of the City of Livingston. 
              The project connects Cressey Substation (located at the southeast 
              corner of West Lane and Meadow Drive, approximately 2 miles east 
              of the community of Cressey) to an expanded Gallo Substation (located 
              on the property of the Gallo Winery facility at 18000 River Road, 
              approximately 4 miles west of the City of Livingston). 
            CPUC Application Review and Approval 
            The PG&E Cressey-Gallo 115 kV Power Line Project was 
              evaluated in accordance with the California Environmental Quality 
              Act (CEQA). A Mitigated Negative Declaration (MND) was prepared 
              to inform the CPUC and public of the potential project impacts and 
              available mitigation (information on the MND preparation is provided 
              below). The CPUC voted on January 16, 2014 to approve the PG&E 
              Cressey-Gallo 115 kV Transmission Project and Final MND (Decision 
              D.14-01-003) and a Notice of Determination was submitted to the 
              State Clearinghouse (SCH #2013021061). The mitigation measures and 
              applicant-proposed measures (APMs) described in the Final MND were 
              adopted by the CPUC as conditions of project approvals. 
            Construction and Mitigation 
              Monitoring 
            Mitigation Monitoring, Compliance, and Reporting 
              Plan 
            Following CPUC approval, a Mitigation Monitoring, Compliance, and 
              Reporting Plan (MMCRP) was prepared to ensure compliance with APMs 
              and mitigation measures approved in the Final MND. The MMCRP provided 
              guidelines and standardized procedures for environmental compliance 
              during project implementation. The procedures were developed in 
              coordination with PG&E and CPUC and described the reporting 
              relationships, the roles and responsibilities of the project's environmental 
              compliance team members, compliance reporting procedures, and the 
              communication protocol. 
            The MMCRP can be viewed here (5.2MB). 
            Notices to Proceed with Construction 
            As defined by the MMCRP, it was necessary for CPUC to issue a Notice-to-Proceed 
              (NTP) before construction could start. On the Cressey-Gallo Project 
              there were multiple work packages and work sites, so PG&E elected 
              to request multiple separate NTPs. Each separate NTP request was 
              applicable to a defined segment or aspect of the Project. Over the 
              course of the Cressey-Gallo Project, PG&E submitted 3 separate 
              NTP requests. CPUC reviewed the NTP requests and the applicable 
              pre-construction requirements to ensure that all of the information 
              required to process and approve the NTPs was included. CPUC requested 
              additional information or clarification as needed. Based on information 
              provided in the requests for NTPs and the review findings, CPUC 
              issued each of the 3 NTPs. The complete list of NTPs issued by CPUC 
              for the Cressey-Gallo Project is provided in the table below. 
            
               
                |  
                   Notices to Proceed 
                 | 
                 
                   Date Requested 
                 | 
                 
                   Date Issued 
                 | 
                 
                   Description 
                 | 
               
               
                |  
                   #1 
                 | 
                 
                   09/12/14 
                 | 
                 
                  
                 | 
                Installation and removal of the shoo-fly, expansion 
                  work at the Gallo Substation, construction of the single and 
                  double circuit 115 kV pole lines on the Gallo Property, and 
                  modification work at the Cressey Substation. | 
               
               
                |  
                   #2 
                 | 
                 
                   12/11/14 
                 | 
                 
                  
                 | 
                Installation of remaining TSPs, construction of 
                  the re-route area north of Livingston Canal, construction of 
                  single circuit 115 kV pole lines within 1/2-mile buffers for 
                  Swainson’s hawk nesting areas east of Howard Street, and pulling 
                  of conductor. | 
               
               
                |  
                   #3 
                 | 
                 
                   03/09/15 
                 | 
                 
                  
                 | 
                Installation of the remaining portions of the Project, 
                  including construction of single circuit 115 kV pole lines and 
                  pulling of conductor. | 
               
             
            Construction began in November 2014. The transmission line, and 
              substation structure upgrades were complete and energized on December 19, 
              2015. Remaining substation work (including paving, fencing and clean-up) 
              was completed and crews were demobilized by January 2016. A soil 
              pile and construction trailer located in the Project staging area 
              was removed in February 2016. Weekly reports documenting construction 
              and compliance activities can be viewed here. 
            Minor Project Changes 
            As defined by the MMCRP, at various times throughout project construction, 
              minor changes to the project, such as the need for additional or 
              revised workspace, were anticipated as common practice for construction 
              efforts of this scale. Minor Project Change requests were required 
              for such activities. The CPUC Project Manager, along with the CPUC 
              EMs, implemented the Minor Project Change procedures defined in 
              the MMCRP to evaluate each proposed project change for its potential 
              for creating significant environmental effects to determine whether 
              supplemental CEQA review is required. A complete list of Minor 
              Project Changes processed for the Cressey-Gallo Project is provided 
              in the table below. 
            
               
                |  
                   Minor Project Changes 
                 | 
                 
                   Date Requested 
                 | 
                 
                   Date Issued 
                 | 
                 
                   Description 
                 | 
               
               
                |  
                   #1 
                 | 
                 
                   10/01/14 
                 | 
                 
                  
                 | 
                Use of an existing alternative staging 
                  area 75 feet west of the proposed Staging Area 001 located southeast 
                  of the Gallo Substation | 
               
               
                |  
                   #2 
                 | 
                 
                   01/22/16 
                 | 
                 
                  
                 | 
                (1) Allow for a temporary fence around 
                  the project staging area to remain permanently, per the request 
                  of the Gallo Winery, and (2) allow for 3 existing wooden power 
                  line poles to remain in place, to be used by an orchard as owl 
                  box posts. | 
               
             
            A Final Report documenting Cressey-Gallo permitting, NTPs, construction, 
              compliance, and Minor Project Changes is located here. 
            Environmental Review Process 
            PG&E filed a Proponent's Environmental 
              Assessment (PEA) with the Application in November 2011. The 
              PEA provided a starting point for the independent environmental 
              review process conducted by the CPUC. 
            PG&E's Application and PEA were deemed complete for review 
              by the CPUC on December 21, 2011. 
            Mitigated Negative Declaration Preparation 
            On February 27, 2013, the CPUC released a Notice of Intent 
              to Adopt a Mitigated Negative Declaration for the Cressey-Gallo 
              115 kV power Line Project showing that the Proposed Project, as 
              mitigated, would not have any significant effects on the environment. 
            The Draft IS/MND underwent a public review period from February 27, 
              2013, through March 29, 2013. 
             
            On June 7, 2013, the CPUC released a Final Mitigated Negative Declaration 
              for the Cressey-Gallo 115 kV Power Line Project, showing that the 
              Proposed Project, as mitigated, would not have any significant effects 
              on the environment. The Final MND detailed the Proposed Project, 
              evaluated and described its potential environmental impacts, identified 
              those impacts that could be significant, and presented mitigation 
              measures to avoid or minimize these impacts. The Final MND can be 
              viewed here. 
             |