|  Welcome to the California Public Utilities Commission 
            (CPUC) website for the California Environmental Quality Act (CEQA) 
            review of Pacific Gas and Electric's (PG&E) proposed Delta DPA 
            Capacity Increase Substation Project (Delta Substation). An application 
            for this project was submitted to the CPUC on August 12, 2005 (A.05-08-022) 
            and a Certification of Public Convenience and Necessity (CPCN) was 
            granted by CPUC on March 1, 2007. This site provides access to 
            public documents and information relevant to the CEQA review process. 
             Background 
            PG&E filed an application with the CPUC to build a new three-bank 
              230/21 kV distribution substation on a 5.1-acre site in the City 
              of Antioch in eastern Contra Costa County. In addition, the Proposed 
              Project would include a new transmission tower in an existing transmission 
              right of way and a new paved access road from the intersection of 
              Heidorn Ranch Road and Sand Creek Road to the proposed substation 
              site. The temporary access road would require a temporary bridge 
              over Sand Creek. PG&E's project objective is to improve reliability 
              and meet projected electrical load requirements in the Delta Distribution 
              Planning Area (DPA), which includes the rapidly growing southern 
              and eastern portion of Antioch, the cities of Brentwood and Oakley, 
              and much of the remainder of unincorporated eastern Contra Costa 
              County. 
            
            Proponent's Environmental Assessment 
              (PEA) 
            PG&E filed a PEA with the Application 
              in August 2005. This document provided a starting point for the 
              environmental review process conducted by the CPUC. 
            Environmental Review Process 
            The CPUC on September 22, 2006, released a Notice of Intent to 
              Adopt a Mitigated Negative Declaration 
              (MND) for the Delta Substation Project, showing that the Proposed 
              Project, as mitigated, would not have any significant effects on 
              the environment. Public comments on the MND were accepted for 30 
              days until October 23, 2006. The CPUC on November 28, 
              2006 released a Final MND incorporating responses to the public 
              comments. On March 1, 2007, the CPUC granted a Certification 
              of Public Convenience and Necessity (CPCN) for the project 
            Construction of the project began on September 10, 2007, after 
              a Notice to Proceed with Construction was granted by CPUC on August 
              30, 2007. A CPUC Environmental Monitor is monitoring construction 
              activities to ensure that they are conducted in accordance with 
              the approved mitigation measures and permit conditions. This site 
              holds all weekly reports documenting this 
              monitoring activity. 
            For Additional Information 
            General questions pertaining to CPUC Environmental Information 
              should be addressed to the Environmental Review Team: 
            
           |