|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of Pacific 
              Gas and Electric's (PG&E) proposed replacement of steam generators 
              at Diablo Canyon Power Plant (DCPP). An application for this project 
              was submitted to the CPUC on January 9, 2004. This site provides 
              access to public documents and information relevant to the CEQA 
              review process. 
             Background 
            PG&E has filed an application with the CPUC to replace the 
              steam generators at DCPP Units 1 and 2. The project would enable 
              DCPP to remain in service until the ends of the current terms of 
              the Nuclear Regulatory Commission (NRC) licenses. The current licenses 
              authorize DCPP Unit 1 to operate until 2021 and Unit 2 to operate 
              until 2025. However, the existing steam generators have exhibited 
              degradation and they are currently predicted to reach the end of 
              their operating life within the next several years. The original 
              steam generators will eventually reach a state where, under applicable 
              NRC regulations, either the steam generators must be replaced or 
              the units must be shut down. 
            DCPP Units 1 and 2 went into operation in 1985 and 1986, respectively. 
              DCPP uses eight steam generators, four per unit, which are large 
              heat exchangers that convert heat from the reactor into steam to 
              drive the turbine generators and produce electricity. All eight 
              would be replaced as part of the proposed project. DCPP produces 
              a combined nominal 2,220 net megawatts of electric power, enough 
              to power over 2 million homes. The DCPP facility is located on a 
              remote stretch of coastline in central San Luis Obispo County. 
            Proponent's Environmental Assessment 
              (PEA) 
            PG&E filed a PEA with the Application 
              in January 2004. This document provided a starting point for the 
              environmental review process conducted by the CPUC. 
            Environmental Review Process 
               
            The CPUC on October 1, 2004, issued a Notice 
              of Preparation of an Environmental Impact Report (EIR) for DCPP 
              Steam Generator Replacement Project. Scoping meetings were held 
              in October 2004. The Public Scoping Report 
              was completed in December 2004. 
            The Draft Environmental Impact Report 
              (DEIR) was issued on March 21, 2005. 
            The submittal period for written comments 
              on the Draft EIR ended May 5, 2005. 
            The Final Environmental Impact Report 
              (Final EIR) was issued on August 15, 2005. The Final EIR consists 
              of two volumes: Volume I is the complete EIR showing changes 
              made to the Draft EIR, and Volume II consists of all comments 
              on the Draft EIR and responses to comments. 
            There is no comment period following issuance of the Final EIR. 
              The CPUC will determine the adequacy of the Final EIR, and, if adequate, 
              will certify the document as compliant with CEQA. The CPUC will 
              issue a Decision on the Proposed Project, which will be announced 
              and published concurrent with a scheduled CPUC Meeting. 
            For Additional Information 
             Requests for additional information should be sent to: 
            Andrew Barnsdale, CPUC Project Manager 
              c/o Aspen Environmental Group 
              235 Montgomery Street, Suite 935 
              San Francisco, CA 94104 
             
           |