             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of proposed 
              construction of the DeversPalo Verde No. 2 (DPV2) Transmission 
              Line Project. An application for this project was submitted to the 
              CPUC on April 11, 2005. The application was determined to be 
              complete and in compliance with CPUC requirements on September 30, 
              2005. The CPUC approved the DPV2 Project on January 25, 2007 in 
              Decision 
              D.07-01-040 and certified the EIR as being in compliance with 
              the requirements of CEQA. The CPUC approved construction of the 
              expanded Colorado River Substation on July 14, 2011 in Decision 
              D.11-07-011. 
             On May 14, 2008, SCE filed a Petition for Modification (PFM) of 
              the existing Certificate for Public Convenience and Necessity (CPCN) 
              approved per Decision D.07-01-040. SCE requested that the CPUC authorize 
              SCE to construct DPV2 facilities in only the California portion 
              of DPV2 and the Midpoint Substation near Blythe, California. The 
              CPUC approved SCE’s PFM on November 20, 2009 in Decision 
              D.09-11-007. The BLM issued its Record 
              of Decision approving the project on July 19, 2011. 
             
            This site provides access to public documents and information relevant 
              to the CEQA review process. 
             Construction Progress and Mitigation 
              Monitoring 
             Construction of the Devers-Palo Verde No. 2 Project began 
              in June 2011 with the establishment of some construction and helicopter 
              yards. The majority of construction started in late 2011/early 2012 
              after the CPUC and BLM issued NTPs for the overhead transmission 
              line and substation construction. Notices to Proceed (NTPs) were 
              issued by the CPUC for each construction activity. Issuance of NTPs 
              were contingent upon SCE compliance with pre-construction requirements 
              as specified by the approved mitigation measures and responsible 
              agency permitting requirements. NTPs that have been issued to SCE 
              by the CPUC are noted in the table below. BLM issued NTPs for construction 
              of the Red Bluff and Colorado River Substations and the overhead 
              transmission line on its lands in September 2011. The U.S. Forest 
              Service also issued its NTP for construction on Forest lands. 
             Most construction was completed by September 2013, including final 
              cleanup. Site restoration at some locations was conducted in early 
              2014. A Final Report documenting construction and compliance activities 
              is available here (6.5MB). 
              Site restoration work will con-tinue into 2015 and beyond until 
              such time that restoration success criteria are met. Construction 
              of the access road to Red Bluff Substation started in August 2014 
              and will be completed by May 2015. 
               
             
               
                |  
                   Work Package 
                 | 
                 
                   Description 
                 | 
                 
                   Jurisdiction 
                 | 
                 
                   Type 
                 | 
                 
                   NTP Request Submitted 
                 | 
                 
                   NTP Issued 
                 | 
                 
                   Construction Authorized¹ 
                 | 
               
               
                | Colorado River-Red Bluff | 
                Colorado River Substation (CRD MP0) to Red Bluff 
                  Substation | 
                CPUC 
                  BLM  | 
                500 kV Overhead | 
                NTPR submitted to CPUC on 10/8/11 | 
                NTP #8 for CRS-RB issued 12/2/11; 
                  BLM issued NTP in Sept 2011 | 
                 
                   1/16/12 
                 | 
               
               
                | Red Bluff-Devers | 
                Red Bluff Substation to Devers Substation (CRD MP109.6) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                NTPR submitted to CPUC on 10/8/11 | 
                NTP #9 for RB-Devers issued 12/2/11; 
                  BLM issued NTP in Sept 2011 
                 | 
                 
                   1/16/12 
                 | 
               
               
                | Devers-Valley | 
                Devers Substation (DV MP0) to Valley Substation (DV 
                  MP42) | 
                CPUC 
                  BLM 
                  USFS 
                 | 
                500 kV Overhead | 
                NTPR submitted to CPUC on 10/8/11 | 
                NTP #10 for Devers-Valley issued 12/2/11; 
                  BLM issued NTP in Sept 2011;  
                  USFS issued NTP on 8/2/12 
                 | 
                 
                   1/16/12 
                 | 
               
               
                | Colorado River Substation | 
                Colorado River Substation construction (CRS MP0) | 
                CPUC 
                  BLM 
                 | 
                New 500/230 kV Substation | 
                Not yet submitted. CPUC approved SCE's PTC application 
                  in July 2011 | 
                BLM issued NTP in September 2011 | 
                 
                   September 2011 
                 | 
               
               
                | Devers Substation Improvements | 
                Devers Substation improvements 
                  (CRS MP109.6/DV MP0) 
                 | 
                CPUC 
                  BLM | 
                Substation Upgrades  | 
                NTPR submitted to CPUC 4/12/12 | 
                CPUC NTP #13 for Devers Substation issued 5/9/12 | 
                 
                   6/8/12 
                 | 
               
               
                | Valley Substation Improvements | 
                Valley Substation improvements  
                  (DV MP42) 
                 | 
                CPUC 
                  BLM 
                 | 
                Substation Upgrades | 
                NTPR submitted to CPUC 6/12/12 
                  (3.2MB) | 
                CPUC NTP #14 for Valley Substation issued 6/19/12 | 
                 
                   7/12/12 
                 | 
               
               
                | Construction and Helicopter Yards | 
                Along Colorado River-Devers & Devers-Valley | 
                CPUC | 
                Material storage, marshalling, tower assembly, batch 
                  plants, and helicopter staging | 
                Revised NTPR submitted to CPUC on 5/20/11 
                  (4.9MB)   | 
                CPUC NTP #1 for construction yards issued 6/23/11 
                 | 
                 
                   7/18/11 
                 | 
               
               
                Exclusionary Fencing  
                  (CRS-Devers)  | 
                Exclusionary fencing at 41 work areas | 
                CPUC 
                  BLM  
                 | 
                Fencing | 
                NTPR submitted to CPUC on 8/5/11 
                  (21.0MB)  | 
                CPUC NTP #2 for exclusionary fencing issued 
                  9/9/211 | 
                 
                   9/15/11 
                 | 
               
               
                | Beaumont #2 Yard | 
                New storage/material yard along Devers-Valley | 
                CPUC | 
                Construction yard | 
                NTPR submitted to CPUC on 8/26/11 
                  (3.3MB)  | 
                CPUC NTP #3 for Beaumont #2 Yard issued 9/19/11 | 
                 
                   11/21/11 
                 | 
               
               
                | Indio Yard | 
                New storage/material yard along CRS-Devers | 
                CPUC | 
                Construction yard | 
                NTPR submitted to CPUC on 9/9/11 
                  (4.1MB)  | 
                CPUC NTP #4 for Indio Yard issued 9/20/11 | 
                 
                   10/6/11 
                 | 
               
               
                Red Bluff Distribution Line 
                 | 
                Upgrade existing 12 kV line for substation light 
                  & power  
                 | 
                CPUC | 
                12 kV distribution line | 
                NTPR submitted to CPUC on 9/16/11 | 
                CPUC NTP #5 for Red Bluff Distribution issued 10/11/11 
                 | 
                 
                   11/7/11 
                 | 
               
               
                CRS Distribution Line 
                 | 
                Extend 33 kV distribution line, install telecom line, 
                  access road improvements to serve CRS | 
                CPUC | 
                33 kV distribution line, telecom line, access road | 
                NTPR submitted to CPUC on 9/19/11 | 
                CPUC NTP #6 for CRS Distribution issued 10/17/11 | 
                 
                   10/25/11 
                 | 
               
               
                | CRS-Blythe SE Telecom Line | 
                New Southeast Telecom Line on private property between 
                  the CRS and the Blythe Service Center | 
                CPUC | 
                Optical Ground Wire & All-Dielectric Self-Supporting 
                  fiber optic line | 
                NTPR submitted to CPUC on 7/16/12 | 
                CPUC NTP #15 issued on 11/15/12 | 
                 
                   12/10/12 
                 | 
               
               
                | Mirage Substation Loop-Ins | 
                Installation of new fiber optic cables to Mirage 
                  Substation to provide diverse routing of telecommunications 
                  services | 
                CPUC | 
                Optical Ground Wire & All-Dielectric Self-supporting 
                  fiber optic line | 
                NTPR submitted to CPUC on 11/7/12 | 
                CPUC NTP #16 issued on 12/3/12 | 
                 
                   2/8/13 
                 | 
               
               
                | Devers-Valley #1 Minor Relocation | 
                Relocation of 4 lattice steel towers; construction 
                  of stub roads and foundations; and assembly of steel & interconnecting 
                  wires | 
                CPUC | 
                500 kV Overhead | 
                NTPR submitted to CPUC on 9/8/11 | 
                CPUC NTP #7 issued on 12/1/11 | 
                 
                   1/16/12 
                 | 
               
               
                | Devers #2 and Indio #2 Yards | 
                New storage/material yards along CRS-Devers | 
                CPUC | 
                Construction yards | 
                NTPR submitted to CPUC on 11/8/11 | 
                CPUC NTP #11 issued on 12/10/11 | 
                 
                   12/14/11 
                 | 
               
               
                | Desert Center #3 Yard | 
                New storage/material yard along CRS-Devers | 
                CPUC | 
                Construction yard | 
                NTPR submitted to CPUC on 1/20/12 | 
                CPUC NTP #12 issued on 2/3/12 | 
                 
                   3/5/12 
                 | 
               
             
            1 - Compliance with all remaining pre-construction 
            mitigation measures and NTP conditions satisfied 
            The CPUC, in conjunction with SCE, BLM, USFS, and other Responsible 
              Agencies, drafted a Mitigation Monitoring Compliance and Reporting 
              Program (MMCRP) to ensure compliance with mitigation measures approved 
              in the Final EIR/EIS, as well as with the terms and conditions associated 
              with the BLM right-of-way. The final version of the MMCRP document 
              and attachments, including a map 
              of the approved route, can be found here. 
             
            CPUC Environmental Monitors (EMs) monitored construction activities 
              to ensure that they were conducted in accordance with the approved 
              mitigation measures and permit conditions. Weekly reports documenting 
              construction status and compliance activities are posted here. 
            As defined by the MMCRP, at various times throughout project construction, 
              the need for extra workspace or additional access roads was identified. 
              Similarly, changes to the project requirements (e.g., mitigation 
              measures, specifications, etc.) were needed to facilitate construction 
              (e.g., nighttime construction in response to a planned power outage) 
              or provide more effective protection of resources (e.g., installation 
              of additional erosion control outside of approved disturbance areas). 
              The CPUC Project Manager, along with the CPUC EMs, implemented the 
              variance procedures defined in the MMCRP to evaluate each proposed 
              project change for its potential for creating significant environmental 
              effects to determine whether supplemental CEQA and/or NEPA review 
              is required. Variance Requests processed for the project are provided 
              in the table below. 
               
             
               
                |  
                   Variance 
                    Request 
                 | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date 
                    Issued 
                 | 
                 
                   Segment 
                 | 
                Description | 
               
               
                |  
                   #1 
                 | 
                 
                   5/6/11 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance from Mitigation Measures V-3a 
                  and V-40a to allow for construction of traditional 
                  lattice towers instead of “Tetra” towers at two locations | 
               
               
                |  
                   #2 
                 | 
                 
                   4/21/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Variance from Mitigation Measure B-7d 
                  pertaining to seasonal restrictions in Coachella Valley fringe-toed 
                  lizard and flat-tailed horned lizard habit | 
               
               
                |  
                   #3 
                 | 
                 
                   7/12/11 
                 | 
                 
                  
                 | 
                 
                   DC-1 and DC-2 Yards 
                 | 
                Variance to utilize offsite well location area for 
                  filling water trucks | 
               
               
                |  
                   #4 
                 | 
                 
                   7/6/11 
                 | 
                 
                  
                 | 
                 
                   Menifee Yard 
                 | 
                Variance to add the western portion of the parcel 
                  (approximately 5 acres) to make additional area available for 
                  material storage and other activities | 
               
               
                |  
                   #5 
                 | 
                 
                   4/22/11 
                 | 
                 
                  
                 | 
                 
                   Substations & Series Capacitor 
                 | 
                Variance for modification of APM A-7 regarding carpooling 
                  for construction at substations | 
               
               
                |  
                   #6 
                 | 
                 
                   7/8/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Variance to remove Mitigation Measures B-13a, B-13b 
                  and to modify B-1a, B-1a(rev) and B-7e regarding Western Riverside 
                  County MSHCP compliance | 
               
               
                |  
                   #7 
                 | 
                 
                   8/11/11; revised 8/18/11 
                 | 
                 
                  
                 | 
                 
                   Perris, Beaumont, Blythe & Menifee Yards 
                 | 
                Variance to utilize offsite water sources (existing 
                  fire hydrants) for filling water trucks | 
               
               
                |  
                   #8 
                 | 
                 
                   8/23/11 
                 | 
                 
                  
                 | 
                 
                   Beaumont Yard 
                 | 
                Variance for installation of seeded jute netting 
                  along the property frontage | 
               
               
                |  
                   #9 
                 | 
                 
                   9/1/11 
                 | 
                 
                  
                 | 
                 
                   DC-2 Yard 
                 | 
                Variance for temporary power at the DC-2 Yard | 
               
               
                |  
                   #10 
                 | 
                 
                   8/29/11 
                 | 
                 
                  
                 | 
                 
                   Devers & Summit Yards 
                 | 
                Variance to utilize offsite water sources (existing 
                  fire hydrants) for filling water trucks | 
               
               
                |  
                   #11 
                 | 
                 
                   9/26/11 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Variance to utilize two offsite water sources (existing 
                  fire hydrants) for exclusionary fencing work | 
               
               
                |  
                   #12 
                 | 
                 
                   10/13/11 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Parking/temporary staging vehicles along the existing 
                  disturbed access route for areas within the Coachella Valley 
                  Preserve | 
               
               
                |  
                   #13 
                 | 
                 
                   10/28/11 
                 | 
                 
                  
                 | 
                 
                   Devers Yard 
                 | 
                Variance for temporary power at the Devers Yard | 
               
               
                |  
                   #14 
                 | 
                 
                   11/11/11 
                 | 
                 
                  
                 | 
                 
                   CRS 
                 | 
                Variance for increased groundwater usage | 
               
               
                |  
                   #15 
                 | 
                 
                   12/13/11; modified 4/25/12 
                 | 
                 
                  
                 | 
                 
                   Summit Yard 
                 | 
                Variance for temporary power at the Summit Yard | 
               
               
                |  
                   #16 
                 | 
                 
                   12/8/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Variance for extended construction work hours | 
               
               
                |  
                   #17 
                 | 
                 
                   1/4/12 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance for water sources for transmission line 
                  construction | 
               
               
                |  
                   #18 
                 | 
                 
                   10/26/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                CPUC denied SCE's variance request to formalize changes 
                  to DPV2 MM B-1a, MM B-1a(rev), MM 
                  V-2b, and MM H-1a and Red Bluff MM-BIO-4 
                  and AM-BIO-5 | 
               
               
                |  
                   #19 
                 | 
                 
                   1/6/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for revised helicopter landing zone HLZ 
                  H9-DV | 
               
               
                |  
                   #20 
                 | 
                 
                   1/13/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance to utilize two offsite water sources in 
                  Cabazon | 
               
               
                |  
                   #21 
                 | 
                 
                   1/20/12; modified 3/16/12 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Variances to utilize an offsite water source at Lake 
                  Tamarisk Golf Resort | 
               
               
                |  
                   #21 MOD 
                 | 
                 
                   9/25/12 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Variance for egress widening on Oasis Road at the 
                  Lake Tamarisk water source | 
               
               
                |  
                   #22 
                 | 
                 
                   1/25/12 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Variance for water stand tank locations | 
               
               
                |  
                   #23 
                 | 
                 
                   1/27/12 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance for additional helicopter construction | 
               
               
                |  
                   #24 
                 | 
                 
                   2/8/12 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Variance regarding Colorado River Water Credits | 
               
               
                |  
                   #25 
                 | 
                 
                   2/10/12 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance for additional parking along access roads | 
               
               
                |  
                   #26 
                 | 
                 
                   3/9/12 
                 | 
                 
                  
                 | 
                 
                   Red Bluff 
                 | 
                Variance for new water source for construction of 
                  Red Bluff Substation | 
               
               
                |  
                   #27 
                 | 
                 
                   2/23/12 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance for revised disturbance areas due to engineering 
                  modifications | 
               
               
                |  
                   #28 
                 | 
                 
                   3/22/12 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Variance for use of Gasline Road for construction 
                  access | 
               
               
                |  
                   #29 
                 | 
                 
                   3/22/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for revised pull sites to support the Devers-Valley 
                  #1 minor relocation outage | 
               
               
                |  
                   #30 
                 | 
                 
                   3/23/12 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Variance for modifications to pull sites along CRS-Devers 
                  segment | 
               
               
                |  
                   #31 
                 | 
                 
                   4/24/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for revised helicopter landing zone HLZ 
                  H2-DV | 
               
               
                |  
                   #32 
                 | 
                 
                   3/16/12: additional info submitted 5/3/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for revised helicopter landing zone HLZ 
                  H7-DV  | 
               
               
                |  
                   #33 
                 | 
                 
                   4/26/12 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance for additional offsite water sources | 
               
               
                |  
                   #34 
                 | 
                 
                   4/12/12 
                 | 
                 
                   Retracted by SCE 
                 | 
                 
                   DPV2 
                 | 
                Variance for extension of pre-construction survey 
                  validity from 14 days to 30 days | 
               
               
                |  
                   #35 
                 | 
                 
                   5/11/12 
                 | 
                 
                  
                 | 
                 
                   Devers Substation 
                 | 
                Variance per Mitigation Measure V-1a 
                  to eliminate construction screening of the Devers Substation 
                  expansion area | 
               
               
                |  
                   #36 
                 | 
                 
                   5/17/12 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance for three additional stand tank locations | 
               
               
                |  
                   #37 
                 | 
                 
                   6/20/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for engineering modifications to Tower 1013 | 
               
               
                |  
                   #38 
                 | 
                 
                   7/9/12; modified 8/9/12 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers 
                 | 
                Variance for an additional water source in Thousand 
                  Palms | 
               
               
                |  
                   #39 
                 | 
                 
                   8/14/12; modified 8/16/12 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance for stub roads at Towers 2103, 2112, and 
                  2260 | 
               
               
                |  
                   #40 
                 | 
                 
                   8/22/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Red Bluff 
                 | 
                Variance for stub road at Tower 2242 | 
               
               
                |  
                   #41 
                 | 
                 
                   9/10/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for additional access routes to Towers 1118-1122 
                  and HLZ H9-DV | 
               
               
                |  
                   #42 
                 | 
                 
                   8/14/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for road use for helicopter picking operations 
                  near Tower 1031 | 
               
               
                |  
                   #42 MOD 
                 | 
                 
                   3/1/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for use of existing road surface in addition 
                  to trailers for helicopter picking operations near Tower 1031 | 
               
               
                |  
                   #43 
                 | 
                 
                   9/5/12;  
                    modified 9/18/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Red Bluff 
                 | 
                Variance for pull site revisions along Devers to 
                  Red Bluff transmission line segment. | 
               
               
                |  
                   #44 
                 | 
                 
                   9/24/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for revised stub road at Tower 1147 | 
               
               
                |  
                   #45 
                 | 
                 
                   9/25/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for revised access roads | 
               
               
                |  
                   #46 
                 | 
                 
                   9/20/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for road use for helicopter picking operations 
                  near Towers 1112 and 1108 | 
               
               
                |  
                   #47 
                 | 
                 
                   10/4/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Red Bluff 
                 | 
                Variance for Guard Structures GS53B and GS53C | 
               
               
                |  
                   #48 
                 | 
                 
                   10/2/12 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance for an additional water source on Charlette 
                  Lane in unincorporated Riverside County | 
               
               
                |  
                   #49 
                 | 
                 
                   11/2/12 
                 | 
                 
                  
                 | 
                 
                   Devers- 
                    Red Bluff 
                 | 
                Variance for a temporary work area at Tower 2000X | 
               
               
                |  
                   #50 
                 | 
                 
                   10/19/12; modified  
                    11/2/12 
                 | 
                 
                  
                 | 
                 
                   CRS- 
                    Red Bluff 
                 | 
                Variance for expansion of Splice Site #57 and shift 
                  of Splice Site #64 | 
               
               
                |  
                   #51 
                 | 
                 
                   10/24/12 
                 | 
                 
                  
                 | 
                 
                   Devers- 
                    Red Bluff 
                 | 
                Variance for three temporary helicopter platform 
                  sites (two on private and one on BLM land) | 
               
               
                |  
                   #52 
                 | 
                 
                   11/13/12 
                 | 
                 
                  
                 | 
                 
                   Devers- 
                    Red Bluff 
                 | 
                Variance for revision of DC Fiber Optic Pull Site 
                  #59 | 
               
               
                |  
                   #53 
                 | 
                 
                   10/30/12 
                 | 
                 
                  
                 | 
                 
                   CRS 
                 | 
                Variance for installation of CRS access road slope 
                  protection and improvements | 
               
               
                |  
                   #54 
                 | 
                 
                   11/27/012; 
                    modified 12/3/12 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for pull site revisions along Towers 1061 
                  to 1051 | 
               
               
                |  
                   #55 
                 | 
                 
                   11/6/12; modified 11/28/12 
                 | 
                 
                  
                 | 
                 
                   Devers- 
                    Red Bluff 
                 | 
                Variance for pull site revisions (Part 
                  III-B) at Splice Site 12 & Access Road, Splice Site 14 & 
                  Access Road, Splice Site 15, Secondary Location Wire Site 18 
                  Extension, Pull Site 24 Extension, Splice Site 18 & Associated 
                  Access Road, Splice Site 20, Splice Site 28, Wire Site 40, Splice 
                  Site 29, Pull Site 42, Wire Site 43, Pull Site 41, Splice Site 
                  31, Splice Site 32 & Access Road, Splice Site 34, Wire Site 
                  47, Pull Site 48, Splice Site 35, Splice Site 36 | 
               
               
                |  
                   #56 
                 | 
                 
                   12/18/12 
                 | 
                 
                  
                 | 
                 
                   Devers- 
                    Valley 
                 | 
                Variance for an additional helicopter work area adjacent 
                  to Tower 1051 | 
               
               
                |  
                   #57 
                 | 
                 
                   1/3/13; modified 1/9/13 
                 | 
                 
                  
                 | 
                 
                   Devers- 
                    Red Bluff 
                 | 
                Variance for revisions to temporary disturbance areas | 
               
               
                |  
                   #58 
                 | 
                 
                   1/4/13 
                 | 
                 
                  
                 | 
                 
                   Devers- 
                    Red Bluff 
                 | 
                Variance for 10 pull site revisions (Priority Package 2) | 
               
               
                |  
                   #59 
                 | 
                 
                   1/8/13 
                 | 
                 
                  
                 | 
                 
                   Mirage Substation 
                 | 
                Variance for temporary work areas for Mirage Sub 
                  Telecom Loop-In | 
               
               
                |  
                   #60 
                 | 
                 
                   1/18/13 
                 | 
                 
                  
                 | 
                 
                   CRS Telecom 
                 | 
                Variance for additional disturbance area for anchor 
                  rod installation along the CRS SE Telecom Route | 
               
               
                |  
                   #61 
                 | 
                 
                   1/18/13 
                 | 
                 
                  
                 | 
                 
                   CRS Telecom 
                 | 
                Variance for authorization to use Gravel Pit Road 
                  to access pole installation locations east of Tower M123-T1 | 
               
               
                |  
                   #62 
                 | 
                 
                   1/30/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Pull 102 for Towers 1002-1010  | 
               
               
                |  
                   #63 
                 | 
                 
                   1/30/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Pulls 103 for Towers 1010-1019  | 
               
               
                |  
                   #64 
                 | 
                 
                   1/29/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Pulls 104-105 for Towers 1019-1031  | 
               
               
                |  
                   #65 
                 | 
                 
                   1/31/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Pull 101 for Towers 1000-1002  | 
               
               
                |  
                   #65 MOD 
                 | 
                 
                   3/22/13 
                 | 
                 
                   3/25/13 
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for expansion of Guard Structures DV-GS3 
                  and DV-GS4 | 
               
               
                |  
                   #66 
                 | 
                 
                   2/14/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area expansion at D-V 
                  Tower 1077 | 
               
               
                |  
                   #67 
                 | 
                 
                   2/25/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for adjacent access road watering at Helicopter 
                  Landing Zones H2 & H2A | 
               
               
                |  
                   #68 
                 | 
                 
                   2/13/13; modified 3/5/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Pull 109 for Towers 1083-1090  | 
               
               
                |  
                   #69 
                 | 
                 
                   3/7/13; modified 3/8/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Red Bluff 
                 | 
                Variance for use of D-RB Gasline Access Road to Tower 
                  2249  | 
               
               
                |  
                   #69MOD 
                 | 
                 
                   3/26/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Red Bluff 
                 | 
                Variance for modification of D-RB Gasline Access 
                  Road to Tower 2249 | 
               
               
                |  
                   #70 
                 | 
                 
                   3/5/13 
                 | 
                 
                  
                 | 
                 
                   Devers Substation Telecom  
                 | 
                Variance for additional access road at Devers Substation 
                  for telecom work | 
               
               
                |  
                   #71 
                 | 
                 
                   3/8/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for D-V HLZ H7-DV entrance 
                  turning radius modifications  | 
               
               
                |  
                   #72 
                 | 
                 
                   3/13/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for DV 
                  Pull 115 for Towers 1132-1143  | 
               
               
                |  
                   #73 
                 | 
                 
                   3/13/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Pulls 110-113 for Towers 1090-1122 | 
               
               
                |  
                   #74 
                 | 
                 
                   3/22/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Pull 116-117 for Towers 1143-1157 | 
               
               
                |  
                   #75 
                 | 
                 
                   3/22/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Pulls 107-108 for Towers 1065-1082  | 
               
               
                |  
                   #76 
                 | 
                 
                   3/28/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Wire Site No 42 | 
               
               
                |  
                   #77 
                 | 
                 
                   4/4/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for Guard 
                  Structures D-V GS22A and D-V GS22B | 
               
               
                |  
                   #78 
                 | 
                 
                   4/5/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for D-V 
                  Fiber Optic Optional Setup 34  | 
               
               
                |  
                   #79 
                 | 
                 
                   4/11/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for use of D-V Power Line Road 
                  alternate access route  | 
               
               
                |  
                   #80 
                 | 
                 
                   4/16/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for Guard 
                  Structures D-V GS52A & GS52B | 
               
               
                |  
                   #81 
                 | 
                 
                   4/23/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for disturbance area modifications for Guard 
                  Structures D-V GS89A and D-V GS89B | 
               
               
                |  
                   #82 
                 | 
                 
                   4/23/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for D-V Walking Paths from 
                  Towers 1031 to 1032, 1034 to 1037 and 1048 to 1051  | 
               
               
                |  
                   #83 
                 | 
                 
                   5/2/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for expansion of DV-GS92, DV-GS97 and DV-GS100A | 
               
               
                |  
                   #84 
                 | 
                 
                   5/8/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for expansion of Helicopter Landing Zone 
                  (HLZ) H2A-DV, located northeast of Tower 1051 | 
               
               
                |  
                   #85 
                 | 
                 
                   3/11/13; modified 5/14/13 
                 | 
                 
                  
                 | 
                 
                   DPV2 
                 | 
                Variance to leave improvements permanently in place 
                  at Beaumont 1, Perris, Indio 1, Desert Center 1 and Desert Center 
                  2 Yards | 
               
               
                |  
                   #86 
                 | 
                 
                   5/29/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for Highway 79 southbound turnout  | 
               
               
                |  
                   #87 
                 | 
                 
                   6/6/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for DV-GS54 extension | 
               
               
                |  
                   #88 
                 | 
                 
                   6/11/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for revised expansion of DV-GS54 due to 
                  nesting birds | 
               
               
                |  
                   #89 
                 | 
                 
                   6/14/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for expansion of DV-GS89B  | 
               
               
                |  
                   #90 
                 | 
                 
                   6/14/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for modifications to DV-GS56 and DV-GS57 | 
               
               
                |  
                   #91 
                 | 
                 
                   7/11/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for modifications to DV-GS70, DV-GS76B, 
                  DV-GS77, DV-GS80, and DV-GS84 | 
               
               
                |  
                   #92 
                 | 
                 
                   7/15/13 
                 | 
                 
                  
                 | 
                 
                   Devers-Valley 
                 | 
                Variance for modification of DV Fiber Reel Site 38 
                  to an alternate pull site location (DV Fiber Reel Site 38ALT) | 
               
               
                |  
                   #93 
                 | 
                 
                   2/4/14 
                 | 
                 
                  
                 | 
                 
                   CRS-Devers & Devers-Valley 
                 | 
                Variance for rock entrance "aprons"to remain 
                  in place following construction at 37 locations on unpaved access 
                  roads along CRS-Devers and Devers-Valley | 
               
             
            Project Refinements Report  
            The CPUC has published a Mitigation 
              Consistency Determination Memorandum on SCE's proposed Project 
              Refinements. After careful review of the proposed modifications, 
              as documented in the Mitigation Consistency Determination Memorandum, 
              the CPUC has determined that the changes to the DPV2 Project are 
              within the scope of the Certificate of Public Convenience and Necessity 
              issued by the CPUC.  
            Background: After the California-only project was approved by CPUC 
              in November 2009, SCE began the process of completing final project 
              design and engineering. As is common, some project components were 
              modified as engineering was completed. Modifications result from 
              compliance with adopted mitigation measures requiring resource avoidance 
              to minimize or avoid environmental impacts and final engineering 
              design requirements. In addition, project components may be relocated 
              to accommodate landowner location preferences where possible in 
              compliance with mitigation requirements.  
            Information regarding final project design was provided by SCE 
              to the CPUC and BLM in two Project Refinements Reports, dated August 
              2010 and October 2010. In addition to the refinements outlined in 
              the August 2010 and October 2010 Project Refinements Reports, SCE 
              proposed two additional construction yards in April 2011.  
            The Project Refinements Reports define changes made to the project 
              along the entire route after publication of the Final EIR/EIS, explain 
              the reason for each change, and present the comparative environmental 
              impacts of the project components analyzed in the Final EIR/EIS 
              and those presented in the Project Refinements Reports. SCE's Project 
              Refinements Reports are found here. 
            Addendum/Environmental 
              Assessment  
              October 2012 
            An Addendum to the Focused Final Supplemental EIR was prepared 
              in October 2012 and is available here 
              (8.1MB). The Addendum/EA analyzed 
              the installation of hazard lights on some transmission towers and 
              marker balls on some conductor spans; these had not been considered 
              in the original EIR and were included in a subsequent Petition to 
              Modify the project submitted by SCE. The CPUC approved the PFM on 
              November 29, 2012 in Decision D.12-11-026. 
            Focused Final Supplemental Environmental 
              Impact Report  Released April 29, 2011  
            The Draft Supplemental EIR was released on February 22, 2011 
              and is available here. The comment period 
              on the Draft Supplemental EIR closed on April 8, 2011. Twelve 
              comment letters were received and are available here. 
             The Final Supplemental EIR was released on April 29, 2011 
              and is available here. The Final Supplemental 
              EIR includes all comments and responses to comments that were submitted 
              during the comment period on the Draft Supplemental EIR. 
             The CPUC certified the Final Supplemental EIR and approved SCE’s 
              Permit to Construct application for the Colorado River Substation 
              Expansion on July 14, 2011 in Decision D.11-07-011. 
             Background. After the CPUC's 2009 Decision regarding the 
              PFM, several large solar power projects were proposed in the Blythe 
              area. Two of these projects, the Blythe Solar Power Project and 
              the Genesis Solar Energy Project, have requested interconnection 
              to the electricity grid at the Desert Southwest–Midpoint Substation. 
              As a result, the solar developers and SCE developed a plan to expand 
              the Midpoint Substation, now known as the Colorado River Substation, 
              to allow the required space for generation tie lines to be interconnected 
              with the SCE 500 kV transmission system. SCE filed a Permit to Construct 
              application addressing the substation expansion (A.10-11-005). 
              This expansion was not covered in the original EIR/EIS because the 
              solar power projects had not yet been proposed. 
             
            During 2009 to 2010, the Blythe Solar Power Project and the Genesis 
              Solar Energy Project have been evaluated under CEQA and NEPA by 
              the BLM and the California Energy Commission. The environmental 
              review documents addressed the Colorado River Substation expansion 
              but they did not adequately cover all issues that the CPUC requires 
              to be addressed in accordance with CEQA. Therefore, the CPUC prepared 
              a Focused Supplemental EIR to address only the specific issues not 
              yet covered for its purposes by the previous environmental review. 
             
            A Notice of Preparation (NOP) was sent to interested agencies 
              and members of the public in October 2010 and can be accessed here. 
              The CPUC held a 30-day scoping period soliciting information regarding 
              the topics that should be included in the Focused Supplemental EIR 
              for the Colorado River Substation expansion. Copies of all letters 
              received and a summary of the scoping process and scoping comments 
              are included in a Scoping Report (December 2010), which can be accessed 
              here. 
             All documents filed as part of the CPUC’s proceeding (A.10-11-005) 
              can be accessed here. 
             
            Draft and Final Environmental 
              Impact Report/Environmental Impact Statement 
            The CPUC and BLM released the Draft Environmental 
              Impact Report/Environmental Impact Statement (Draft EIR/EIS) 
              for the proposed project on May 4, 2006. 
            The submittal period for public comments on the Draft EIR/EIS was 
              extended from July 5, 2006 to August 11, 2006. 
            The Final Environmental Impact Report/Environmental 
              Impact Statement (Final EIR/EIS) was issued on October 24, 
              2006. The Final EIR/EIS consists of three volumes. Volumes I and 
              II are completely re-printed from the Draft EIR/EIS. Changes made 
              to the Draft EIR/EIS are marked in Volumes I and II: inserted 
              text is underlined and deleted text is shown in strikeout. 
              Volume III consists of all comments in the Draft EIR/EIS and responses 
              to comments. 
            Over 475 pages of comments on the Draft EIR/EIS were submitted 
              to the BLM and the CPUC, including transcripts from the July 2006 
              Public Participation Hearings. 
            NEPA Process and BLM Record of 
              Decision 
            The BLM published a Notice of Availability of the Final EIR/EIS 
              for DPV2 on March 15, 2007 in the Federal Register (Volume 72, 
              Number 50; page 12185). BLM published a Notice of Availability 
              of the Record of Decision 
              approving the DPV2 project on July 19, 2011 in the Federal Register 
              (Volume 76, Number 138, page 42725). 
            The Department of the Interior (DOI) Control No. for the EIS is 
              FES-06-48. 
            Other Documents Available 
            Notice of Preparation of an Environmental Impact 
              Report (EIR) and Notice of Public Scoping Meetings (October 21, 
              2005) 
              Notice of Intent (December 7, 2005; Federal 
              Register Vol. 70, No. 234) 
              Scoping Report (December 2005) 
              Addendum to the Scoping Report 
              (February 2006) 
              Notice of Availability (October 24, 2006) 
              SCE’s Application and Proponent’s Environmental 
              Assessment (April 11, 2005) 
            For Additional Information 
             
            For additional information please contact the CPUC's Project Manager: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov 
           |