|  
               
              Welcome to the California Public Utilities Commission (CPUC) website 
              for the environmental review of the proposed El Casco System Project 
              (Proposed Project). The Proposed Project includes construction of 
              the El Casco Substation; upgrades to the Zanja and Banning Substations; 
              transmission line upgrades and installation from the new El Casco 
              Substation, located within the Norton Younglove Reserve, east to 
              the Banning Substation in the City of Banning; and telecommunications 
              improvements. 
            
 The objective of Southern California Edison's (SCE's) Proposed 
              Project is to build the electrical facilities necessary to serve 
              forecasted demand in Calimesa, Beaumont, and the surrounding areas 
              of unincorporated northern Riverside County, and to maintain safe 
              and reliable service to customers in the area. 
             The Proposed Project was subject to review under the California 
              Environmental Quality Act (CEQA) and was approved by the CPUC on 
              December 18, 2008. This site provides access to public documents 
              and information relevant to the CEQA environmental review process 
              and project implementation. 
             Recirculated 
              (Revised) Final Environmental Impact Report  
             The CPUC, as Lead agency under the California Environmental Quality 
              Act (CEQA), prepared the Recirculated 
              Final Environmental Impact Report (EIR) for consideration of 
              SCE's Proposed El Casco System Project. The Recirculated Final EIR 
              was prepared in compliance with CEQA, and includes responses to 
              comments received during the Recirculated Draft EIR comment period 
              (July 9, 2008 through August 22, 2008), updates to the 
              original Final EIR resulting from new information presented in the 
              Recirculated Draft EIR, and any text changes resulting from the 
              comments submitted and a feasibility review of mitigation measures. 
             
            The Recirculated Final EIR was released for public review on October 17, 
              2008 and made available for review at several 
              area libraries and on this Project website. The Recirculated 
              Draft EIR, the original Draft EIR, and the original Final EIR were 
              also made available in their entirety on the Project website (see 
              below). Copies of these documents were also made available on CD-ROM 
              and could be requested by phone or fax at (877) 576-8342, or by 
              e-mail at elcasco@aspeneg.com. 
             
            Recirculated 
              (Revised) Draft Environmental Impact Report 
             
            The CPUC, as Lead agency under CEQA, prepared a Recirculated 
              Draft Environmental Impact Report (Draft EIR) for consideration 
              of Southern California Edison Company's (SCE) Proposed El Casco 
              System Project (Proposed Project).  
            The Recirculated Draft EIR for the Proposed Project was prepared 
              to inform the public of changes to the document resulting from new 
              information provided by SCE regarding the ambient noise levels adjacent 
              to the existing single-circuit 115 kV subtransmission line. 
              This information was received subsequent to the CPUC publishing 
              the Final EIR on April 11, 2008.  
            The Recirculated Draft EIR contains an updated noise analysis (Section 
              D.9) reflecting the new information received from SCE; an updated 
              cumulative noise effects analysis (also in Section D.9), an updated 
              Comparison of Alternatives analysis (Section E) the includes 
              a revised discussion of the Environmentally Superior Alternative; 
              and an updated Executive Summary summarizing the changes to the 
              above mentioned sections. Only those sections that have changed 
              from the original Draft EIR published in December 2007 (discussed 
              below) are included in the recirculated EIR, per CEQA Guidelines 
              §15088.5(c).  
            The Recirculated Draft EIR was released for public review for 45 
              days on July 9, 2008. The Recirculated Draft EIR public review 
              period ended on August 22, 2008.  
            Original 
              Environmental Impact Reports 
            The CPUC prepared a Draft Environmental 
              Impact Report (Draft EIR) in December 2007. The Draft EIR details 
              the Proposed Project, evaluates and describes the potential environmental 
              impacts associated with the construction and operation of the Proposed 
              Project, identifies those impacts that could be significant, and 
              presents mitigation measures, which, if adopted by the CPUC or other 
              responsible agencies, could avoid or minimize these impacts. The 
              Draft EIR also evaluated alternatives to the Proposed Project, including 
              the No Project Alternative, as required by CEQA. The Draft EIR was 
              released for public review for 45 days on December 12, 2007. 
              The Draft EIR public review period ended on January 25, 2008. 
             
            The CPUC published the Final Environmental Impact Report (Final 
              EIR) on April 11, 2008. The Final EIR was prepared in compliance 
              with the California Environmental Quality Act (CEQA), and included 
              responses to comments received during the original Draft EIR comment 
              period from December 12, 2007 through January 25, 2008 
              and any text changes resulting from the comments submitted.  
            
            Public Meetings and Hearings 
            The CPUC held one Pre-Hearing Conference and four public meetings 
              to provide information on the Project and to take public comments. 
             
            During the scoping period (July 16, 2007 through August 14, 
              2007), the CPUC held one Pre-Hearing Conference and two public scoping 
              meetings in two locations in northern Riverside County on August 1, 
              2007, as follows: 
            Pre-Hearing Conference 
            
               
                | Location | 
                Banning City Hall Council Chambers 
                 | 
               
               
                | Date | 
                August 1, 2007 | 
               
               
                | Time | 
                1:00 to 2:30pm  | 
               
               
                | Address & Phone | 
                99 East Ramsey Street 
                  Banning, CA 92220 
                  (951) 922-3102  | 
               
             
             
            Public Scoping Meetings 
            
               
                | Location | 
                Banning City Hall Council Chambers 
                 | 
                Beaumont Civic Center Council Chamber | 
               
               
                | Date | 
                August 1, 2007  | 
                August 1, 2007  | 
               
               
                | Time | 
                2:30 to 4:30pm | 
                6:30 to 8:30pm | 
               
               
                | Address | 
                99 East Ramsey Street 
                  Banning, CA 92220 | 
                550 East Sixth Street 
                  Beaumont, CA 92223 | 
               
             
            During the Draft EIR public review period, the CPUC held public 
              workshops and public participation meeting in the City of Banning 
              on January 9, 2008 as follows: 
            
               
                | Location | 
                City of Banning Council 
                  Chambers  | 
               
               
                | Day, Date | 
                Wednesday, January 9, 2008 | 
               
               
                | Time | 
                1:30 to 2:30 PM Workshop  
                  3 to 4 PM Public Participation Meeting  | 
                5:30 to 6:30 PM Workshop 
                  7 to 8 PM Public Participation Meeting  | 
               
               
                Address, 
                  Phone | 
                99 East Ramsey Street 
                  Banning, CA 92220 
                  (951) 922-3102  | 
               
             
            Scoping 
              Report 
            In September 2007, a comprehensive Scoping 
              Report was issued that summarized the issues and concerns received 
              from the public and various agencies during the scoping period (July 
              16, 2007 through August 14, 2007), and presents copies of all 
              written comments received. Approximately 15 letters and emails were 
              received during the NOP scoping period from public agencies and 
              private citizens.  
            The Appendices to the Scoping Report are available here: 
            
            Notice of Preparation 
            In accordance with CEQA, a Notice of Preparation 
              (NOP) of an Environmental Impact Report (EIR) for the El Casco System 
              Project was issued on July 16, 2007 (also see the list of Available 
              Documents below). The NOP summarizes the Proposed Project and 
              advises the public and interested parties of the scoping process 
              for the upcoming environmental impact review. The dates, locations, 
              and times of the CPUC's pre-hearing conference and scoping meetings 
              are identified in the NOP. 
            Repository 
              Sites 
            All project-related documents were made available for review at 
              the following project information repository locations:  
            
               
                |  
                   Repository Sites 
                 | 
               
               
                |  
                   Site 
                 | 
                 
                   Location 
                 | 
                 
                   Phone 
                 | 
                 
                   Hours of Operation 
                 | 
               
               
                Yucaipa 
                  Branch Library | 
                12040 5th St. 
                  Yucaipa CA 92399 | 
                 
                   (909) 790-3146 
                 | 
                Sun Closed. 
                  Mon-Thurs 10am-8pm 
                  Fri 10am-6pm 
                  Sat 9am-5pm | 
               
               
                Banning 
                  Public Library | 
                21 W. Nicolet St. 
                  Banning, CA 92220 | 
                 
                   (951) 849-3192 
                 | 
                Sun Closed. 
                  Mon-Thurs 9am-7pm 
                  Fri 9am-5pm | 
               
               
                Calimesa Branch 
                  Library | 
                974 Calimesa Blvd. 
                  Calimesa, CA 92320 | 
                 
                   (909) 795-9807 
                 | 
                Sun, Mon Closed. 
                  Tues,Thurs, Fri 10am-6pm 
                  Wed 12pm-8pm 
                  Sat 9am-5pm | 
               
               
                Beaumont 
                  Library | 
                125 E 8th Street  
                  Beaumont, CA 92223 | 
                 
                   (951) 845-1357 
                 | 
                Sun Closed. 
                  Mon, Wed, Fri 10am-6pm 
                  Tues,Thurs 10am-8pm 
                  Sat 10am-6pm | 
               
               
                University of  
                  Redlands 
                  Armacost 
                  Library | 
                1200 East Colton Avenue 
                  Redlands, CA 92373-0999 | 
                 
                   (909) 748-8081 
                 | 
                Mon-Thurs 8am-midnight 
                  Fri 8am-9pm  
                  Sat 10am-9pm 
                  (Call to verify hours) | 
               
             
             
            CEQA Process and CPUC General 
              Proceeding 
            CEQA requires the CPUC to take into account the environmental impacts 
              that could result from the Proposed Project, and requires the preparation 
              of an EIR if the Project has the potential to result in significant 
              impacts to the environment. CEQA also requires that the EIR development 
              process include public notice of the Proposed Project and address 
              relevant environmental concerns that the public may have regarding 
              the Proposed Project. 
            The initial public scoping and comment period for the Proposed 
              Project was 30 days per CEQA requirements, from July 16, 2007, 
              until August 14, 2007. During this period, public comments 
              were accepted and two public scoping meetings and a pre-hearing 
              conference were held, prior to selection of alternatives and the 
              preparation of the analysis documented in the EIR. The intent of 
              the scoping process was to obtain input from affected agencies and 
              members of the public on the scope and content of the EIR. 
            The Draft EIR includes an objective analysis of the potential environmental 
              impacts of the Proposed Project. In addition, the Draft EIR provides 
              a detailed discussion of alternatives, including a comparison of 
              each alternative to the Proposed Project. Per CEQA requirements, 
              the Draft EIR was distributed for a 45-day public review period. 
              A notice of completion (NOC) of the Draft EIR was filed with the 
              State Clearinghouse by the CPUC. The CPUC considered all comments 
              on the Draft EIR, prepared responses to comments, and revised the 
              document (as necessary) prior to issuance of the Final EIR on April 11, 
              2008. The Final EIR included responses to comments received on the 
              Draft EIR during the original public review period. 
            The California Public Utilities Commission (CPUC) also prepared 
              a Recirculated Draft EIR for consideration of the Proposed El Casco 
              System Project. The Recirculated Draft EIR was prepared to inform 
              the public of changes to the document resulting from new information 
              provided by SCE regarding the ambient noise levels adjacent to the 
              existing single-circuit 115 kV subtransmission line. SCE provided 
              this information subsequent to the CPUC publishing the Final EIR 
              on April 11, 2008. The Recirculated Draft EIR was released 
              for public review for a 45 days on July 9, 2008. The Recirculated 
              Draft EIR public review period ended August 22, 2007. A NOC 
              was filed with the State Clearinghouse by the CPUC. 
            On October 17, 2008, the CPUC released the Recirculated Final EIR 
              for the Proposed El Casco System Project. The Recirculated Final 
              EIR was prepared in compliance with the California Environmental 
              Quality, and includes responses to comments received during the 
              Recirculated Draft EIR comment period (July 9, 2008 through 
              August 22, 2008), updates to the original Final EIR resulting 
              from new information presented in the Recirculated Draft EIR, and 
              any text changes resulting from comments submitted and a feasibility 
              review of mitigation measures. 
             
            Other Available 
              Documents 
            
              -  Notice of Preparation of an Environmental 
                Impact Report for the El Casco System Project Proposed by Southern 
                California Edison Company prepared by the CPUC (July 16, 
                2007)
 
                 
               
              - Fact Sheet - El Casco System Project 
                prepared by CPUC (June 2007)
 
                 
               
              - Southern California Edison's Proponent's 
                Environmental Assessment (PEA) (March 14, 2007)
 
                  
                Note: The link above provides access to 59 manageably sized files 
                comprising the PEA. The complete PEA is also available for download 
                from the Southern 
                California Edison website as a single very large file (155 MB). 
                This file size means a very long download time, not advisable 
                for anyone with a dialup connection.  
             
            Project Description 
            The El Casco System Project includes the proposed El Casco Substation 
            site, upgrades to the Zanja and Banning Substations and the SCE's 
            Mill Creek Communications Site, upgrades to 
             a total of 15.4 miles of existing 
            115 kV subtransmission line and associated structures, and the installation 
            of fiber optic cables within existing conduits in public streets and 
            on existing SCE structures between the Cities of Redlands and Banning. 
            All portions of the Proposed Project are located within Riverside 
            and San Bernardino Counties, California. The main project components 
            are described below and indicated on the General 
            Location Map. 
            Construction of the El Casco Substation. The new 14-acre 
              El Casco 220/115/12 kV Substation would be located on a 28-acre 
              plot within the Norton Younglove Reserve in Riverside County. This 
              component would include associated 220 kV and 115 kV interconnections 
              and new 12 kV distribution line connections (getaways). The substation 
              would be designed with a low profile (structures no taller than 
              40 feet). Landscaping around the substation would incorporate primarily 
              native vegetation and would be designed to screen views of the substation 
              site. Once constructed, the substation would be an unattended, automated 
              220/115/12 kV substation. 
            Upgrades to the Zanja and Banning Substations. The 115 kV 
              switchracks within the Zanja and Banning Substations, located in 
              the Cities of Yucaipa and Banning, respectively, would be rebuilt 
              to accommodate the new 115 kV subtransmission line, thereby allowing 
              for at least two subtransmission lines to serve each substation 
              at all times. This would reduce the likelihood of temporary power 
              outages, which currently occur due to the fact that each substation 
              is served by only one 115 kV subtransmission line at a time. If 
              there is a problem with the primary (or "preferred") line, 
              a brief delay currently occurs before the secondary (or "emergency") 
              line can be connected. The upgrades to the Zanja and Banning Substations 
              would eliminate this delay by providing a connection for a second 
              115 kV subtransmission line for each substation that would be active 
              at all times. Replacement of the switchracks in both substations 
              would occur within the existing fenced-in areas. 
            Transmission Line Upgrades and Installation. These upgrades 
              would include replacement of existing single-circuit 115 kV subtransmission 
              lines with new, higher capacity lines; tying existing 115 kV and 
              220 kV lines into the new El Casco Substation (looping in); and 
              installation of new 12 kV distribution line getaways at the El Casco 
              Substation. 
            The proposed upgrades of the existing single-circuit subtransmission 
              lines would include the following: 
            
              - Approximately 13 miles of single-circuit 115 kV lines would 
                be replaced with 115 kV double-circuit lines between the new El 
                Casco Substation and the Banning Substation, traversing the Cities 
                of Banning, Beaumont, and unincorporated Riverside County. Single-circuit 
                115 kV structures would be replaced with 115 kV double-circuit 
                structures.
 
                 
               
              - Approximately 1.9 miles of single-circuit 115 kV subtransmission 
                line would be replaced with new, higher capacity single-circuit 
                115 kV subtransmission lines and new support structures within 
                existing SCE rights-of-way (ROWs) in the City of Beaumont and 
                unincorporated Riverside County.
 
                 
               
              - Approximately 0.5 miles of single-circuit 115 kV subtransmission 
                line would be replaced with new, higher capacity single-circuit 
                115 kV subtransmission lines on existing support structures in 
                the City of Beaumont. 
 
             
            The existing San BernardinoMaraschino 115 kV subtransmission 
              line would be looped into the new El Casco Substation 115 kV switchrack 
              on two new approximately 900-foot line segments between the existing 
              ROW and the 115 kV switchrack. The DeversSan Bernardino No. 2 
              220 kV transmission line would be looped into the new 220 kV switchrack 
              at the El Casco Substation on two new approximately 500-foot line 
              segments between the existing ROW and the 220 kV switchrack. Two 
              approximately 400-foot underground duct banks would be constructed 
              for the 12 kV distribution line getaways, traversing beneath San 
              Timoteo Creek and the railroad tracks. These distribution lines 
              would eventually be connected to future distribution lines in the 
              area. 
            Telecommunications Improvements. Proposed improvements to the telecommunications 
              systems as part of the Proposed Project include the construction 
              of a microwave system at the proposed El Casco Substation and SCE's 
              existing Mill Creek Communications Site in the San Bernardino National 
              Forest, as well as installation of fiber optic cables within public 
              streets and on existing SCE structures in the Cities of Banning, 
              Beaumont, Calimesa, Redlands, and Yucaipa, as well as unincorporated 
              parts of Riverside and San Bernardino Counties. 
            The following link provides a general Project map: Map 
              1-General Location  (2.5MB) 
            
            Additional maps and figures for the Proposed Project and alternatives 
              are can be found in the Proponent's Environmental 
              Assessment, which is provided as a link. 
            Commission Decision 
            
              D.08-12-031 
                - Issued December 18, 2008  
              Attachment 
                A - CPUC CEQA Findings of Fact  
             
            Project Activities Subsequent 
              to CPUC Approval 
            On December 18, 2008, CPUC approved the El Casco System Project. 
              Compliance review for pre-construction mitigation measures identified 
              in the Mitigation Monitoring Plan as presented in the Final EIR 
              is being conducted by CPUC. This plan ensures that the approved 
              project will be conducted as defined, and that all adopted mitigation 
              measures and Applicant Proposed Measures will be implemented in 
              order that effects on the environment do not exceed those described 
              in the Final EIR. CPUC Notices to Proceed will be issued for each 
              project component, as requested by SCE, after compliance with pre-construction 
              mitigation requirements is satisfied by SCE. A CPUC Environmental 
              Monitor will monitor construction activities to ensure that they 
              are conducted in accordance with the approved mitigation measures 
              and permit conditions. Reports documenting this monitoring activity 
              are available here. 
            For Additional Information 
            The CPUC, through its Environmental Review Team and per CEQA requirements, 
              is conducting the environmental review process for the Proposed 
              Project. To request additional information or to comment on the 
              Draft EIR, please contact us by project email, fax, or phone, as 
              follows: 
            
             
             The CPUC's Project Manager is: 
               
              Juralynne Mosley, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2210 
              Fax (415) 703-2200 
              Email:  jbm@cpuc.ca.gov 
             
           |