|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the environmental review and monitoring of Southern California 
              Edison's (SCE's) Eldorado-Lugo-Mohave Series Capacitor Project (ELM 
              Project). SCE submitted an application for the proposed Project 
              to the CPUC on May 2, 2018 (Application A.18-05-007). The CPUC 
              is the California Environmental Quality Act (CEQA) lead agency and 
              on August 12, 2019, the CPUC published a Draft Initial Study/Mitigated 
              Negative Declaration (IS/MND) for the Proposed Project. The CPUC 
              approved a Certificate of Public Convenience 
              and Necessity for the Project on August 27, 2020 (Decision 
              D.20-08-032). 
            This website provides access to public documents and information 
              relevant to the CEQA review process and mitigation monitoring. 
            QUICK LINKS 
              Application 
              A.18-05.007 
              Proponent's Environmental Assessment 
              Amended 
              Application 
              Decision 
              D.20-08-032 
             
             Final Initial 
              Study/Mitigated Negative Declaration 
              Draft Initial Study/Mitigated Negative Declaration 
            DESCRIPTION OF PROPOSED 
              PROJECT 
              The ELM Project consists of the following major 
              components: 
            
              - Construct 2 new 500 kV mid-line series capacitors (i.e., the 
                proposed Newberry Springs Series Capacitor and Ludlow Series Capacitor) 
                and associated equipment.
 
                 
               
              - Provide 2 communication paths between the series capacitor sites:
 
                 
                
                  - Install approximately 2 miles of overhead and 500 feet of 
                    underground telecommunications facilities as one path to connect 
                    the proposed series capacitors to SCE's existing communication 
                    system.
 
                     
                   
                  - Install approximately 2 miles of underground telecommunications 
                    facilities as a second communication path to connect the series 
                    capacitors to SCE's existing communication system.
 
                     
                   
                 
               
              - Provide station light and power to the proposed series capacitors 
                by extending and/or rerouting existing lines to create approximately 
                2 miles of overhead and 700 feet of underground 12 kV distribution 
                circuits. (The new distribution poles would support overhead telecommunication 
                facilities as well as the electric distribution lines.)
 
                 
               
              - Construct 3 new fiber optic repeater facilities (Barstow, Kelbaker, 
                and Lanfair) within the Lugo-Mohave ROW.
 
                 
               
              - Install distribution lines for light and power at the 3 proposed 
                fiber optic repeater sites.
 
                 
               
              - Install underground telecommunications facilities from existing 
                transmission structures to the Barstow, Kelbaker, and Lanfair 
                fiber optic repeater sites.
 
                 
               
              - Address 16 potential overhead clearance discrepancies at 14 
                locations by: 
 
                 
                
                  - Relocating, replacing, or modifying existing transmission, 
                    subtransmission, and distribution facilities at approximately 
                    12 locations along the Eldorado-Lugo, Eldorado-Mohave, and 
                    Lugo-Mohave 500 kV Transmission Lines to address 14 of the 
                    overhead clearance discrepancies. Tower modifications would 
                    include raising 9 towers approximately 18.5 feet by inserting 
                    new lattice-steel sections in tower bodies.
 
                     
                   
                  - Performing minor grading at 2 locations along the Lugo-Mohave 
                    500 kV Transmission Line to address 2 of the overhead clearance 
                    discrepancies.
 
                     
                   
                 
               
              - Install approximately 235 miles of optical ground wire (OPGW) 
                (approximately 59 miles on the Eldorado-Mohave Transmission Line 
                and approximately 173 miles on the Lugo-Mohave Transmission Line, 
                including approximately 3 miles of underground telecommunications 
                facilities in the vicinity of the Mohave Substation).
 
                 
               
              - Modify and strengthen the ground wire peak of existing suspension 
                towers where OPGW splices would occur (some of these towers would 
                also require minor modifications to the steel in the tower body).
 
                 
               
              - Install approximately 2,000 feet of underground telecommunications 
                facilities within the existing Lugo, Mohave, and Eldorado Substations.
 
                 
               
              - Within Lugo Substation, perform modifications on the existing 
                series capacitors and install new terminating equipment and remove 
                2 existing tubular steel poles (TSPs) and install 2 new TSPs on 
                the Eldorado-Lugo and Lugo-Mohave 500 kV Transmission Lines.
 
                 
               
              - Within the Eldorado Substation, perform modifications on the 
                existing series capacitors and upgrade the terminal equipment 
                on the Eldorado-Lugo 500 kV Transmission Line.
 
                 
               
              - Within the Mohave Substation, replace existing series capacitors 
                on the Lugo-Mohave 500 kV Transmission Line and install new terminal 
                equipment on the Eldorado-Mohave and Lugo-Mohave 500 kV Transmission 
                Lines.
 
                 
               
              - Within LADWP's McCullough Substation, replace 5 existing 500 
                kV 50 kA circuit breakers with 5 new 500 kV 63 kA circuit breakers.
 
                 
               
              - Install (if necessary) cathodic protection on approximately 
                60 miles of SoCalGas's natural gas pipelines parallel to SCE's 
                Lugo-Mohave 500 kV Transmission Line.
 
               
             
            Construction Status and 
              Mitigation Monitoring  
            The CPUC and SCE have prepared a Mitigation Monitoring, Compliance, 
              and Reporting Plan (MMCRP), which is available here (7MB). 
              The MMCRP ensures compliance with the mitigation measures adopted 
              in the Final IS/MND. The MMCRP provides for Environmental Monitors 
              and defines the reporting relationships, roles and responsibilities, 
              and procedures for environmental compliance on the Project. The 
              MMCRP will be updated to reflect schedule changes and other revisions 
              as needed. 
            Notices to Proceed (NTPs) are reviewed and will be issued by CPUC 
              by subsection of the project as requested by SCE. Issuance of NTPs 
              is contingent upon SCE's compliance with pre-construction requirements 
              as specified by the approved mitigation measures and responsible 
              agency permitting requirements. Table 1 below summarizes the 
              NTPs issued by CPUC. 
            
            Approved plans are available here. Limited 
              construction activities began in January 2021 and completion of series capacitor energization occurred in Quarter 1, 2025. Cathodic protection installation is the remaining task to be completed. 
            CPUC Environmental Monitors were present to monitor construction 
              activities and verify that the proper implementation of project 
              mitigation measures and permit and compliance plan requirements 
              during construction is occurring. Monitoring reports documenting 
              construction and compliance activities are available here. 
            As final engineering was completed or as construction necessitated, 
              Minor Project Refinements (MPRs) were  submitted for the Project. 
              Each of these requests were reviewed by CPUC to ensure that no 
              new impacts or increase in impact severity would result from the 
              requested change. MPRs approved for the project are summarized below. 
            
               
                | Table 2. Minor Project 
                  Refinements | 
               
               
                |  
                   MPR #  
                 | 
                 
                   MPR Request Submittal 
                    Date 
                 | 
                 
                   Description 
                 | 
                 
                   Date Approved 
                 | 
               
               
                |  
                   #1 
                 | 
                 
                  
                 | 
                Additional work areas for five locations to support 
                  construction. | 
                September 8, 
                  2021 | 
               
               
                |  
                   #2 
                 | 
                 
                  
                 | 
                New work areas for OPGW work along Lugo-Mohave 
                  Transmission Line | 
                September 30, 
                  2021 | 
               
               
                |  
                   #3 
                 | 
                 
                  
                 | 
                Continued use of a water source to support construction | 
                October 21, 
                  2021 | 
               
               
                |  
                   #4 
                 | 
                 
                  
                 | 
                Addition of work areas to support distribution 
                  line work along Deep Creek Road | 
                October 21, 
                  2021 | 
               
               
                |  
                   #5 
                 | 
                 
                  
                 | 
                Additional work areas and water source | 
                October 15, 
                  2021 | 
               
               
                |  
                   #6 
                 | 
                 
                  
                 | 
                Work area for grounding activities | 
                January 11, 
                  2022 | 
               
               
                |  
                   #7 
                 | 
                 
                  
                 | 
                Daggett water source | 
                January 26, 
                  2022 | 
               
              
                #8  | 
                
                   
  | 
                  Implementation  of cathodic protection measures related to SoCalGas’s pipeline to occur after the in-service date of the ELM Series Capacitor (ELM) Project, rather than before the ELM Project in-service date, as specified  in Mitigation Measure (MM) UT-1 
                  Revised to clarify operational restrictions in that the MPR applies only to the Lugo-Mohave Transmission Line (L-M T/L) sections of the ELM Project, where SoCalGas has planned AC Mitigation for their pipelines.  | 
                February 22, 
                  2025 
                  Revision August 28, 2025  | 
               
               
            BACKGROUND 
              The CPUC is the California Environmental Quality Act 
              (CEQA) lead agency and the Bureau of Land Management (BLM) is the 
              National Environmental Policy Act (NEPA) lead agency, with the National 
              Park Service (Mojave National Preserve) as a Cooperating Agency 
              under NEPA.  
            Application: SCE submitted an application for a Permit to 
              Construct (PTC) for the Project to the CPUC on May 2, 2018 
              (Application A.18-05-007). 
              The Application was accompanied by a Proponent's 
              Environmental Assessment. On January 9, 2019, the CPUC 
              directed SCE to amend it application and to refile it as an application 
              for a Certificate of Public Convenience and Necessity (CPCN), rather 
              than for a PTC. SCE submitted its amended 
              application for a CPCN (6MB) 
              on April 19, 2019.  
            CEQA Review: The CPUC has reviewed the proposed project 
              under CEQA. On August 12, 2019, the CPUC published a Draft 
              Initial Study/Mitigated Negative Declaration (IS/MND) for the 
              Proposed Project. The 30-day public review and comment period for 
              the IS/MND closed on September 13, 2019. Comment 
              letters were received from 11 parties. The letters, CPUC's responses, 
              and text revisions to the Draft IS/MND are included in the Final 
              IS/MND. 
            The project is located in San Bernardino County, California; Clark 
              County, Nevada; the cities of Hesperia, California, and Boulder 
              City, Nevada; the unincorporated community of Lucerne Valley in 
              California; and the unincorporated communities of Searchlight and 
              Laughlin in Nevada. A map is provided here. 
              An overview of the Proposed Project is provided below. 
            COMMENTS & QUESTIONS? 
              If you have comments or questions regarding the project, 
              please contact us using the CPUC's project email or voicemail, as 
              follows: 
           |