|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of Pacific 
              Gas and Electric's (PG&E) Embarcadero-Potrero 230 kilovolt (kV) 
              Transmission Project. An application for this project was submitted 
              to the CPUC on December 11, 2012 (A.12-12-004), 
              which started the CPUC proceeding to decide whether a Certification 
              of Public Convenience and Necessity (CPCN) should be issued. The 
              CPUC reviewed the application and in a decision on January 16, 
              2014 (D.14-01-07) 
              approved the project and issued a CPCN. This website provides access 
              to public documents and information relevant to the CEQA review 
              process. 
             Background 
             The Embarcadero-Potrero 230 kV Transmission Project includes construction, 
              operation, and maintenance of a 230 kV transmission line entirely 
              within the City and County of San Francisco from Embarcadero Substation 
              near the corner of Fremont and Folsom Streets to Potrero Switchyard 
              on Illinois Street between 22nd and 23rd Streets. 
            The new 230 kV transmission line will be approximately 3.5 miles 
              in length, including approximately 2.5 miles installed offshore 
              in the seafloor of San Francisco Bay, 0.4 mile installed in horizontal 
              directional drills (HDD) from two onshore transition points to the 
              Bay, and approximately 0.6 miles underground in conventional trenching. 
              The new transmission line will be placed in City streets, including 
              Spear Street and Folsom Street in San Francisco's Rincon Hill neighborhood 
              and 23rd Street east of Illinois Street. Construction of a new 230 
              kV switchyard will occur near the existing Potrero Switchyard, but 
              no new substation work will occur at the existing Embarcadero Substation 
              beyond the proposed termination of the new cable into the 230 kV 
              bus. 
            PG&E's project objectives include improving the reliability 
              of the existing transmission system in San Francisco to provide 
              a high likelihood of continued electric service to downtown San 
              Francisco in the event of overlapping outages on both of two existing 
              230 kV transmission lines that presently feed Embarcadero Substation. 
             
            CPUC Application Review 
              and Approval 
            The PG&E Embarcadero-Potrero 230 kV Transmission Project was 
              evaluated in accordance with the California Environmental Quality 
              Act (CEQA). A Mitigated Negative Declaration (MND) was prepared 
              to inform the CPUC and public of the potential project impacts and 
              available mitigation (information on the MND preparation is provided 
              below). The CPUC voted on January 16, 2014 to approve the PG&E 
              Embarcadero-Potrero 230 kV Transmission Project and Final MND (Decision 
              D.14-01-007) and a Notice of Determination was submitted to the 
              State Clearinghouse (SCH#2013082047). The mitigation measures and 
              applicant-proposed measures (APMs) described in the Final MND were 
              adopted by the CPUC as conditions of project approvals. 
             
            Construction and Mitigation Monitoring 
            Mitigation Monitoring, Compliance, and Reporting Plan. Following 
              CPUC approval, a Mitigation Monitoring, Compliance, and Reporting 
              Plan (MMCRP) was prepared to ensure compliance with applicant proposed 
              measures (APMs) and mitigation measures approved in the Final IS/MND. 
              The MMCRP provides guidelines and standardize procedures for environmental 
              compliance during project implementation. The procedures were developed 
              in coordination with PG&E and CPUC and describe the reporting 
              relationships, the roles and responsibilities of the project's environmental 
              compliance team members, compliance reporting procedures, and the 
              communication protocol. 
            The MMCRP can be viewed here. 
            Notices to Proceed with 
              Construction 
            As defined by the MMCRP, CPUC must issue a Notice to Proceed (NTP) 
              before construction can start. On projects where there may be multiple 
              work packages or work sites, PG&E may elect to request separate 
              NTPs. Each separate NTP request will be applicable to a defined 
              segment or aspect of the Project. CPUC will review the NTP request 
              and the applicable pre-construction requirements to ensure that 
              all of the information required to process and approve the NTP is 
              included. CPUC may request additional information or clarification 
              as needed. Based on information provided in the request for an NTP 
              and its review, CPUC will issue the NTP.  
            PG&E submitted several requests for NTPs. NTPs issued by CPUC 
              to date for the PG&E Embarcadero-Potrero Project are provided 
              below. 
            
               
                |  
                   Notices to Proceed 
                 | 
                 
                   Date Requested 
                 | 
                 
                   Date Issued 
                 | 
                 
                   Description 
                 | 
               
               
                |  
                   #1 
                 | 
                 
                   06/23/14 
                 | 
                 
                  
                 | 
                Site preparation and excavation of the proposed 
                  230 kV Potrero Switchyard site. | 
               
               
                |  
                   #2 
                 | 
                 
                   07/31/14 
                 | 
                 
                  
                 | 
                Horizontal Directional Drilling (HDD) component 
                  of the Project on Spear St. and 23rd St. | 
               
               
                |  
                   #3 
                 | 
                 
                   09/18/14 
                 | 
                 
                  
                 | 
                Underground duct bank and vault installation component 
                  of the Project between HDD transition on Spear St. to the Embarcadero 
                  Substation on Folsom St. in the northern section, and between 
                  the HDD transition on 23rd Street to the Potrero Switchyard 
                  in the southern section. | 
               
               
                |  
                   Mod to #3 
                 | 
                 
                   11/13/14 
                 | 
                 
                  
                 | 
                Trenching from the new Potrero Switchyard to the 
                  existing switchyard for the 230 kV/115 kV connections 
                  across the Trans Bay Cable (TBC). | 
               
               
                |  
                   #4 
                 | 
                 
                   11/19/14 
                 | 
                 
                  
                 | 
                Rock removal obstructing the path of the submarine 
                  cable component of the Project along the submarine cable line 
                  and off shore of Pier 50 in the San Francisco Bay. | 
               
               
                |  
                   #5 
                 | 
                 
                   02/19/15 
                 | 
                 
                  
                 | 
                Construction of 230 kV Potrero gas-insulated switchgear 
                  (GIS) building and cable tie-in component at Potrero Switchyard. | 
               
               
                |  
                   #6 
                 | 
                 
                   02/19/15 
                 | 
                 
                  
                 | 
                Site preparation for submarine cable installation, 
                  laying the cable, and pulling the cable to land at either end. | 
               
             
            Construction began in September 2014 and continued through December 
              2016, with minor completion tasks being conducted in Q1 2017. Weekly 
              reports documenting construction and compliance activities can be 
              viewed here. A Final Report documenting 
              Project construction and compliance activities is available here. 
            Compliance plans were developed as required by the mitigation measures 
              and submitted to the CPUC for review and approval prior to construction. 
              A listing of major compliance plans requiring CPUC and/or permit 
              agency review and approval is provided below. 
            
             
              Minor Project Changes 
            As defined by the MMCRP, at various times throughout project construction, 
              minor changes to the project, such as the need for additional or 
              revised workspace, are anticipated and common practice for construction 
              efforts of this scale and a Minor Project Change request would be 
              required for such activities. The CPUC Project Manager, along with 
              the CPUC EMs, will implement the Minor Project Change procedures 
              defined in the MMCRP to evaluate each proposed project change for 
              its potential for creating significant environmental effects to 
              determine whether supplemental CEQA review is required. Minor Project 
              Changes processed to date are provided in the table below. 
            
               
                |  
                   Minor Project Changes 
                 | 
                 
                   Date Requested 
                 | 
                 
                   Date Issued 
                 | 
                 
                   Description 
                 | 
               
               
                |  
                   #1 
                 | 
                 
                   07/16/14 
                 | 
                 
                  
                 | 
                Use of an existing staging and laydown yard adjacent 
                  to Alternate Staging Area #3 on Amador St. identified in MND. | 
               
               
                |  
                   #3 
                 | 
                 
                   12/31/14 
                 | 
                 
                  
                 | 
                Use of an existing staging and laydown yard two 
                  blocks from the Potrero Switchyard at 1215 Michigan Street | 
               
             
            Environmental Review Process 
            PG&E filed a PEA with the Application on December 11, 2012. 
              This document provided a starting point for the environmental review 
              process conducted by the CPUC. PG&E's Application and PEA 
              were deemed complete for review by the CPUC on January 10, 2013. 
              The CPUC Energy Division reviewed PG&E's Application and PEA 
              and prepared an Initial Study/Mitigated Negative Declaration (IS/MND) 
              as the appropriate CEQA document for this project.  
            Mitigated Negative Declaration 
              Preparation 
            The CPUC released a Notice of Intent to Adopt a Mitigated Negative 
              Declaration for the proposed Embarcadero-Potrero 230 kV Transmission 
              Project showing that the Proposed Project, as mitigated, would not 
              have any significant effects on the environment. The Draft Mitigated 
              Negative Declaration and Supporting Initial Study (IS/MND) was made 
              available for public review and comment from August 13, 2013 to 
              September 16, 2013. 
            The Draft IS/MND can be viewed here. 
            On October 29, 2013, the CPUC released a Final Mitigated Negative 
              Declaration showing that the proposed Embarcadero-Potrero 230 kV 
              Transmission Project, as mitigated, would not have any significant 
              effects on the environment. The Final IS/MND details the Proposed 
              Project, evaluates and describes its potential environmental impacts, 
              identifies those impacts that could be significant, and presents 
              mitigation measures to avoid or minimize these impacts. 
            The Final IS/MND can be viewed here. 
             |