             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of Indian 
              Springs Telecom LLC's proposed Indian Springs Telecom Project. As 
              part of the Rural Telecommunications Infrastructure Grant Program 
              (RTIGP), Resolution 
              T-17216, which was approved on October 15, 2009, 
              authorizes the Executive Director of the CPUC to enter into a contract 
              to perform a CEQA review of the Indian Springs Telecom Project. 
              Because the issuance of grants pursuant to the RTIGP are discretionary 
              actions subject to the requirements of CEQA, the CPUC is the lead 
              agency for CEQA review of the Indian Springs Telecom Project.  
               
             
               
                | The Indian Springs Telecom Project was terminated in fall 
                  2010 and is no longer under CEQA review by the CPUC. | 
               
             
             
            Application Process for 
              RTIGP Funding 
             CEQA review for RTIGP grants is conducted consistent with the two-phase 
              application process for RTIGP funding established in D.03-09-071. 
              Phase 1 is the qualifying phase, in which applicants must provide 
              information required in the legislation (information about the community 
              to be served, its residents, financial information, letters of support 
              from the local government and other affected governmental agencies, 
              letters of support from 75 percent of the identified residential 
              community and identity of the fiscal agent). Upon successful completion 
              of Phase 1, an applicant may submit a Phase 2 Application, 
              detailing a feasibility study and a construction cost study. 
             Approval of a Phase 1 Application means that the CPUC has determined 
              that a proposed project would be eligible to receive funds under 
              the RTIGP. Phase 1 determinations do not approve a "project" 
              under CEQA and do not trigger environmental review. 
            Phase 2 Applications seek funds that are necessary for the construction 
              of rural telecommunications infrastructure and are considered to 
              be projects under CEQA. Approvals of Phase 2 Applications are 
              subject to a case-by-case factual analysis of environmental impacts. 
            Indian Springs School District submitted a Phase 1 Application 
              on February 15, 2005. On March 11, 2005, Indian Spring 
              School District was notified of its Phase 1 approval and of 
              its eligibility to submit a Phase 2 Application, which it submitted 
              on April 15, 2005. This site provides access to public documents 
              and information relevant to the Phase 2 CEQA review process. 
            Background 
            Indian Springs Telecom LLC proposes to construct the Indian Springs 
              Telecom Project, which would include construction of cell towers, 
              underground power transmission lines, and access roads at three 
              sites (Bear Mountain, Hatchet Mountain, and Round Mountain) along 
              State Route 299 within Shasta County. The facilities would be owned 
              by Indian Springs Telecom LLC for the duration of the grant period, 
              which ends in July 2010 (at which time ownership would be transferred 
              to the Indian Springs Elementary School). 
            The Indian Springs Telecom Project would provide cellular service 
              to residents and commuters within the coverage area of Hatchet Mountain, 
              Round Mountain and Bear Mountain. The project sites are located 
              on private land and are surrounded by undeveloped areas with low 
              vegetation or timberlands. Most of the proposed project areas have 
              been previously disturbed by the construction of roads and other 
              communications facilities. 
            Project construction would include grading of new access roads 
              and driveways, grading of the tower sites, construction of concrete 
              slabs and/or footings to accommodate the towers, construction of 
              telecommunications towers on the footings, installation of security 
              fencing, and installation of new powerlines. The construction phase 
              of the project is estimated to be completed within four months. 
            Proponent's Environmental 
              Assessment (PEA) 
            Indian Springs LLC filed a PEA on August 31, 
              2009. This document provided a starting point for the environmental 
              review process conducted by the CPUC. 
            Environmental Review Process 
            The PEA was submitted to the CPUC on August 31, 2009. 
            The Draft Initial Study/Mitigated Negative Declaration or Draft 
              Environmental Impact Report will be distributed for public review 
              and published here, when available. A final document will then be 
              published before the CPUC makes a decision on the proposed project. 
            For Additional Information 
            The CPUC's Project Manager is: 
               
             
             Jensen Uchida, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-5484 
              Fax (415) 703-2200 
              Email:  JMU@cpuc.ca.gov 
           |