| On May 24, 
                  2012, The Nevada Hydro Company's (TNHC's) TEVS 500 kV Interconnect 
                  Project Application (A.10-07-001) was dismissed without prejudice 
                  by the California Public Utilities Commission (CPUC). Currently, 
                  there is no application before the Commission for this project. 
                  The historic information provided on the Commission's TEVS Project 
                  website below is with regard to the dismissed project. The Commission 
                  has no additional information about the project other than the 
                  information included here. Interested parties are referred to 
                  TNHC's website: http://www.interconnectproject.com | 
               
             
            Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed construction of The Nevada Hydro Company Inc.'s (TNHC) 
              Talega-Escondido/Valley-Serrano (TE/VS) 500 kV Interconnect Project. 
              This website provides access to public documents and information 
              relevant to the CEQA review process. The official Proceedings are 
              available at http://docs.cpuc.ca.gov/published/proceedings/A1007001.htm. 
              
             Background 
            On July 6, 2010, TNHC filed an application (A.10-07-001) for a 
              Certificate of Public Convenience and Necessity (CPCN) with the 
              CPUC to construct the TE/VS 500 kV Interconnect Project. The CPUC 
              is the CEQA lead agency for the TE/VS transmission line project. 
              The Notice of Preparation (NOP) of an Environmental Impact Report 
              (EIR) was issued on March 14, 2011. 
            TNHC has filed an application for a Certificate of Public Convenience 
              and Necessity (CPCN) with the CPUC to construct the TE/VS 500 kV 
              Interconnect Project. The CPUC is the CEQA lead agency for the TE/VS 
              transmission line project. 
            The TE/VS 500 kV transmission line, as proposed by TNHC, would 
              be a 500 kV alternating current regional interconnection transmission 
              line with a nominal design capacity of 1,000 MW. The transmission 
              line would provide a transmission interconnection from the proposed 
              Lake Elsinore Advanced Pumped Storage (LEAPS) hydroelectric energy 
              storage facility to the transmission systems of Southern California 
              Edison (SCE) and San Diego Gas & Electric (SDG&E), and it 
              would interconnect the SCE and SDG&E systems. 
            The transmission line would be approximately 32 miles long and 
              would extend from the proposed LEAPS facility near the City of Lake 
              Elsinore, southward to SDG&E's existing 230 kV Talega-Escondido 
              transmission line in San Diego County, and northward to SCE's existing 
              500 kV Valley-Serrano transmission line in Riverside County. The 
              interconnection with SDG&E would be between SDG&E's existing 
              Talega and Escondido substations at a new substation adjacent to 
              Camp Pendleton. The interconnection with SCE's network would be 
              at a point between SCE's Valley and Serrano Substations, at a new 
              switchyard in the vicinity of Lee Lake. In addition to the improvements 
              described above, TNHC's TE/VS Interconnect Project would require 
              numerous upgrades to the SDG&E and SCE systems. 
            Application and Proponent's Environmental 
              Assessment (PEA) 
            In October of 2007, an application (A.07-10-005; A.09-02-12) and 
              PEA for the TE/VS project were filed with the CPUC. However, on 
              April 16, 2009, the Administrative Law Judge (ALJ) issued a 
              decision dismissing the application without prejudice as a result 
              of several deficiencies in the PEA: 
             
              Decision 
                of ALJ Karen V. Clopton 
                Attachment 1 (26.4MB) 
                Attachment 2 
                Attachment 3 
                Attachment 4 
                Attachment 5 
             
            Subsequently, a new application and PEA 
              were filed on July 6, 2010. This application and PEA were deemed 
              complete by the CPUC on August 5, 2010. The CPUC acknowledged 
              this with a letter 
              to TNHC. On February 25, 2011, TNHC filed a revised 
              Chapter 3 to replace the Chapter 3 submitted in the 
              July 2010 PEA. This revised chapter and associated figures supersedes 
              the earlier version of Chapter 3. 
            On April 3, 2012, ALJ Minkin issued a Proposed 
              Decision to Dismiss the July 2010 application (A.10-07-001). 
              On May 24, 2012, the Commission voted to dismiss Application 
              10-07-001. The decision to dismiss was without prejudice, meaning 
              that the applicant may submit a new application for the proposed 
              project, subject to meeting a series of conditions laid out in the 
              decision to dismiss.  
             
            Public Scoping Meetings 
            The CPUC held two public meetings, on Tuesday, April 5, 2011 
              in Lake Elsinore, and on Wednesday, April 6, 2011 in Murrieta. 
              These meetings gave the public and interested parties an opportunity 
              to learn more about the proposed TE/VS Project and provided an opportunity 
              for them to comment on the scope of the Environmental Impact Report 
              (EIR) that is being prepared. Copies of the presentation and maps 
              that were shown at the scoping meetings can be downloaded here:
              
              
              Scoping 
                Meeting Presentation 
                Map - Regional 
                Project Location (5.0MB) 
                Map - Northern Part of Proposed 
                Project  
                Map - Southern Part of Proposed 
                Project 
                Map - Lake Elsinore 
                with LEAPS 
                Map - Lake Elsinore 
                115 kV Alignment 
                Mapbook for 500 kV Alignment 
                (6.8MB). Index map 
                Mapbook for 115 kV Alignment 
                (2.8MB). Index map 
             
            Comments made at these meetings or submitted subsequently will 
              be considered by the CPUC in defining the scope of the EIR. The 
              comment period will extend to April 29, 2011.  
            CPUC Data Requests on the TE/VS 
              Project 
            
            For Additional Information 
            To request additional information regarding this project, please 
              contact the following: 
            
            Andrew Barnsdale, CPUC Project Manager 
              c/o Aspen Environmental Group 
              235 Montgomery Street, Suite 935 
              San Francisco, CA 94104 
              Email:  interconnect@aspeneg.com 
           |