      500 kV Transmission Project Web site. 
      Pacific Gas & Electric Company (PG&E) submitted Application
      Number 01-04-012 on April 13, 2001.  The
      application requests authority to do the following: •        Construct
      approximately 84 miles of 500 kV overhead transmission line between the
      Los Banos and Gates Substations.  •        Realign
      the existing Los Banos-Midway No. 2500 kV transmission line into Gates
      Substation. •        Modify
      the Los Banos and Gates Substations to accommodate the new transmission
      line and realignment. •        Upgrade
      portions of the Gates-Arco-Midway 230 kV transmission line. The
      Project would be located in the western portion of the San Joaquin Valley. 
      The Los Banos Substation, the northern terminus, is approximately
      10 miles west of the City of Los Banos, near San Luis Reservoir in western
      Merced County.  The Gates
      Substation, the southern terminus of the new 84-mile transmission line, is
      approximately 5 miles southwest of Huron, in southern Fresno County.
      Upgrades to the existing Gates-Arco-Midway 230 kV transmission line are
      within Kings and Kern Counties. 
 Public
      Involvement                       Environmental
      Review Documents 
 
  | |
| 
       This site contains tables and is best viewed with 
      Netscape or Microsoft Explorer browsers. Please report any problems to the 
      Energy Division web 
      coordinator.  | 
| 
       |