|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Southern California Edison's (SCE) proposed Riverway 
              Substation Project (Riverway Substation). An application for this 
              project was submitted to the CPUC on June 1, 2006 (A.06-06-004). 
              This site provides access to public documents and information relevant 
              to the CEQA review process. 
             Background 
             SCE has filed an application with the CPUC to build a new 1.7-acre 
              66/12 kV low-profile substation with two 28 MVA transformers and 
              six 12 kV distribution lines. The project would include approximately 
              1,200 feet of underground 66 kV subtransmission lines, as well as 
              new fiber optic cable and communication equipment to connect the 
              substation to SCE's existing telecommunication system. The substation 
              site is located north of Riggin Avenue and east of Mooney Boulevard 
              (which is being extended north of Riggin Avenue) in the City of 
              Visalia. 
            SCE has stated that the project is necessary to maintain safe and 
              reliable service and meet projected electrical load requirements 
              in the City of Visalia and northern Tulare County. The substation 
              would be constructed to accommodate future capacity increases beyond 
              2010, as required. 
            Proponent's Environmental Assessment 
              (PEA) 
            SCE filed a PEA with the Application 
              in June 2006. This document provided a starting point for the environmental 
              review process conducted by the CPUC. 
            Environmental Review Process 
            On May 31, 2007, the CPUC released a Notice of Intent to Adopt 
              a Mitigated Negative Declaration (MND) 
              for the Riverway Substation Project, showing that the Proposed Project, 
              as mitigated, would not have any significant effects on the environment. 
            Public comments on the Draft MND were accepted for 30 days until 
              June 30, 2007, and on July 26, 2007, the CPUC released 
              the Final MND incorporating responses to the public comments. 
            On September 6, 2007, the CPUC granted a Permit 
              to Construct for the project. 
            Construction of the project began on October 29, 2007, after a 
              Notice to Proceed with Construction was granted by CPUC on October 
              16, 2007. A CPUC Environmental Monitor is monitoring construction 
              activities to ensure that they are conducted in accordance with 
              the approved mitigation measures and permit conditions. This site 
              holds all weekly reports documenting this 
              monitoring activity 
             
            For Additional Information 
            General questions pertaining to CPUC Environmental Information 
              should be addressed to the Environmental Review Team: 
            
           |