|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of Pacific 
              Gas and Electric's (PG&E) proposed Seventh Standard Substation 
              Project. An application for this project was submitted to the CPUC 
              on March 2, 2009 (A.09-03-004). 
              The CPUC voted on October 29, 2009 to approve the proposed project 
              (see Decision D.09-10-049) and 
              a Notice of Determination 
              was submitted to the State Clearinghouse. Construction of the Project 
              began the week of March 8-12, 2010, and was completed 
              in November 2010. This site provides access to public documents 
              and information relevant to the CEQA review process. 
             Background 
            The proposed Seventh Standard Substation Project is located in 
              northwest Bakersfield, Kern County, California. The proposed 4.9-acre 
              substation is located south of Seventh Standard Road and west of 
              the Calloway Canal, approximately 2.5 miles west of State Route 99. 
              It would be on land that is currently an almond orchard. 
            The new electric substation would be an automated, low-profile 
              facility. Electrical power would enter the substation by tapping 
              the Rio BravoKern Oil 115 kV power line that parallels the 
              south side of Seventh Standard Road. Electrical power would leave 
              the substation as 21 kV via distribution feeder lines, which would 
              interconnect with the distribution network. Construction involves 
              the installation of the following components: 
            
              - A new, three-bank 115/21 kV distribution substation;
 
                 
               
              - A single tubular steel pole (TSP) to be located midway between 
                the substation and Seventh Standard Road, and two other TSPs (drop-down 
                structures) to be located nearer to and east of the substation;
 
                 
               
              - Two dead-end structures on the east side of the substation;
 
                 
               
              - Up to nine distribution circuits (at full build-out) exiting 
                the substation in underground conduit and transitioning to the 
                overhead position or remaining underground; and
 
                 
               
              - A paved access road from Seventh Standard Road to the substation.
 
               
             
            Proponent's Environmental Assessment 
              (PEA) 
            PG&E filed a PEA with the Application 
              in March 2009. This document provided a starting point for the environmental 
              review process conducted by the CPUC. In addition, PG&E's Notice 
              of an Application for a Permit to Construct can be found here. 
            Environmental Review Process 
            PG&E's Application and PEA were deemed complete by the CPUC 
              on April 1, 2009. 
            The CPUC has determined that an Initial Study/Mitigated Negative 
              Declaration (IS/MND) will be the appropriate CEQA document to be 
              prepared for this project. The Draft IS/MND was published on August 11, 
              2009 and the Final IS/MND was published on October 16, 2009. 
            The CPUC voted on October 29, 2009 to approve the proposed project 
              (see Decision D.09-10-049) and 
              a Notice of Determination 
              was submitted to the State Clearinghouse. 
            Construction of the project began the week of March 8, 2010, 
              after a Notice to Proceed with Construction was granted by CPUC. 
              A CPUC Environmental Monitor will be monitoring construction activities 
              to ensure that they are conducted in accordance with the approved 
              mitigation measures and permit conditions. Reports documenting construction 
              and compliance activities are available here. 
              Construction was completed in November 2010. 
            Final Initial Study/Mitigated 
              Negative Declaration 
            On October 16, 2009, the CPUC released a Final Mitigated Negative 
              Declaration for the Seventh Standard Substation Project, showing 
              that the Proposed Project, as mitigated, would not have any significant 
              effects on the environment. The Final MND details the Proposed Project, 
              evaluates and describes its potential environmental impacts, identifies 
              those impacts that could be significant, and presents mitigation 
              measures to avoid or minimize these impacts. The Final IS/MND can 
              be viewed here. 
             Draft Initial Study/Mitigated 
              Negative Declaration 
            On August 11, 2009, the CPUC released a Notice 
              of Intent to Adopt a Mitigated Negative Declaration (MND) for 
              the Seventh Standard Substation Project, showing that the Proposed 
              Project, as mitigated, would not have any significant effects on 
              the environment. The Draft Initial Study/Mitigated Negative Declaration 
              (IS/MND) can be viewed here. 
            The Proposed IS/MND underwent a public review period from August 11, 
              2009, through September 11, 2009. Comments should have been 
              received in writing by 5:00 p.m. on September 11, 2009, at 
              the email, fax, or project mailing address (see "For Additional 
              Information" below). 
            Public Informational Meeting 
            
            
            In order to help affected communities understand the Proposed Project 
              and the Proposed IS/MND and to explain how the public can participate 
              in the CPUC’s decision-making processes, the CPUC held an informational 
              workshop in Bakersfield on August 25, 2009. This informal workshop 
              was an opportunity to ask questions about the content of the Draft 
              IS/MND. While written comments may have been submitted during these 
              workshops, there were no facilities to record oral comments. 
            
            For Additional Information 
            The CPUC, through its Environmental Review Team, conducted an environmental 
              review of the project. To request additional information, please 
              contact the CPUC, as follows: 
            Mary Jo Borak 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-1333 
              Fax (415) 703-2200 
              Email:  BOR@cpuc.ca.gov 
             |