General Order 128
Section I
General Provisions
12.1
Construction and Reconstruction of Lines
These requirements apply to all systems, parts of systems, and
extensions constructed on or after the effective date of the applicable
rule(s). Elements of systems constructed prior to the effective date of
the applicable rule(s) shall be brought into compliance with these rules
when that element of the system is reconstructed or replaced.
An element added to an existing underground system, or element of an
existing system, shall meet all requirements of these rules, but will
not require any change in elements already existing.
Example: Pulling cable into an existing conduit system does not require
upgrading the existing conduit system.
Note: Revised October 9, 1996 by Resolution SU–40.
A. Services
Services may be added to existing plant without necessitating
changes in the system from which they originate.