General Order 165
Opinion
Order
IT IS ORDERED that:
1. The General Order attached to this
decision as Appendix A is adopted.
2. The findings, conclusions, and discussion of
Decision 96-11-021 are incorporated into this decision by reference to the
extent applicable.
3. Respondent utilities shall file implementation
plans for inspections no later than July 1, 1997. Further, no later than
August 1, respondent utilities shall file proposed standards for operation,
reliability, and safety during emergencies and disasters. Parties may file
comments on those proposals no later than September 15, 1997.
4. The State's municipal and publicly-owned electric
utilities, which are respondents to this rulemaking, shall file comments
no later than August 1, 1997, regarding the extent to which they should be
subject to the rules adopted herein. Parties may file responsive comments
no later than September 15, 1997.
This order is effective today.
Dated March 31, 1997, at San Francisco, California.