Change List for this Rule

 

General Order 95

 

Section I

 

General Provisions

 

12.6    Third Party Nonconformance

 

When a third party that is not subject to the requirements of this Order causes a condition on or near a utility facility that does not conform with this Order, the utility shall be allowed reasonable time to address the condition by pursuing appropriate corrective action and/or notification procedures. While addressing this condition, the utility is in conformance with the Order.

 

Note:    For purposes of this Rule, “reasonable time” is intended to account for the safety implications associated with the condition, discussions with the third party, engineering and/or construction manpower availability, and utility practices for addressing these types of conditions.

 

Note:    Added January 13, 2006 by Decision No. 05-01-030