GO 128, Rule 12.5
12.5 New Rule
Strikeout and Underline Version
GO 128, Rule 12.5
12.5 Third Party Nonconformance:
When a third party that is not subject to the requirements of this Order causes a condition on or near a utility facility that does not conform with this Order, the utility shall be allowed reasonable time to address the condition by pursuing appropriate corrective action and/or notification procedures. While addressing this condition, the utility is in conformance with the Order.
Note: For purposes of this Rule, “reasonable time” is intended to account for the safety implications associated with the condition, discussions with the third party, engineering and/or construction manpower availability, and utility practices for addressing these types of conditions.
Final Version
GO 128, Rule 12.5
12.5 Third Party Nonconformance:
When a third party that is not subject to the requirements of this Order causes a condition on or near a utility facility that does not conform with this Order, the utility shall be allowed reasonable time to address the condition by pursuing appropriate corrective action and/or notification procedures. While addressing this condition, the utility is in conformance with the Order.
Note: For purposes of this Rule, “reasonable time” is intended to account for the safety implications associated with the condition, discussions with the third party, engineering and/or construction manpower availability, and utility practices for addressing these types of conditions.