Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3943E
Advice Letter Filed10-NOV-11
Suspension Begin Date06-DEC-11
Suspension End Date03-APR-12
Projected Date of Disposition01-AUG-12
GroundsAdvice letter requires staff review.

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2301E
Advice Letter Filed10-NOV-11
Suspension Begin Date06-DEC-11
Suspension End Date03-APR-12
Projected Date of Disposition01-AUG-12
GroundsAdvice letter requires staff review.

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number2653E
Advice Letter Filed10-NOV-11
Suspension Begin Date06-DEC-11
Suspension End Date03-APR-12
Projected Date of Disposition01-AUG-12
GroundsAdvice letter requires staff review.

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4603G
Advice Letter Filed06-FEB-14
Suspension Begin Date08-MAR-14
Suspension End Date07-JUL-14
Projected Date of Disposition04-NOV-14
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3484G/4443E
Advice Letter Filed13-JUN-14
Suspension Begin Date13-JUL-14
Suspension End Date10-NOV-14
Projected Date of Disposition10-MAR-15
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4690G
Advice Letter Filed19-SEP-14
Suspension Begin Date20-NOV-14
Suspension End Date19-MAR-15
Projected Date of Disposition17-JUL-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3113E
Advice Letter Filed07-OCT-14
Suspension Begin Date06-NOV-14
Suspension End Date05-MAR-15
Projected Date of Disposition03-JUL-15
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2665E
Advice Letter Filed10-NOV-14
Suspension Begin Date10-DEC-14
Suspension End Date08-APR-15
Projected Date of Disposition06-AUG-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3134E
Advice Letter Filed18-NOV-14
Suspension Begin Date18-DEC-14
Suspension End Date16-APR-15
Projected Date of Disposition14-AUG-15
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2674E
Advice Letter Filed21-NOV-14
Suspension Begin Date28-FEB-15
Suspension End Date29-JUN-15
Projected Date of Disposition27-OCT-15
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2676E
Advice Letter Filed26-NOV-14
Suspension Begin Date01-JAN-15
Suspension End Date30-APR-15
Projected Date of Disposition28-AUG-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3142E
Advice Letter Filed01-DEC-14
Suspension Begin Date31-DEC-14
Suspension End Date29-APR-15
Projected Date of Disposition27-AUG-15
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4543E
Advice Letter Filed03-DEC-14
Suspension Begin Date02-JAN-15
Suspension End Date01-MAY-15
Projected Date of Disposition29-AUG-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3147E
Advice Letter Filed12-DEC-14
Suspension Begin Date11-JAN-15
Suspension End Date11-MAY-15
Projected Date of Disposition08-SEP-15
GroundsResolution Needed

Utility NamePacific Pipeline System LLC (U-0018)
Advice Letter Number42O
Advice Letter Filed07-JAN-15
Suspension Begin Date06-FEB-15
Suspension End Date05-JUN-15
Projected Date of Disposition03-OCT-15
GroundsAdditional Time Needed

Utility NamePacific Pipeline System LLC (U-0018)
Advice Letter Number43O
Advice Letter Filed07-JAN-15
Suspension Begin Date06-FEB-15
Suspension End Date05-JUN-15
Projected Date of Disposition03-OCT-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3168E
Advice Letter Filed21-JAN-15
Suspension Begin Date20-FEB-15
Suspension End Date19-JUN-15
Projected Date of Disposition17-OCT-15
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4579E
Advice Letter Filed30-JAN-15
Suspension Begin Date01-MAR-15
Suspension End Date29-JUN-15
Projected Date of Disposition27-OCT-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3171E
Advice Letter Filed30-JAN-15
Suspension Begin Date01-MAR-15
Suspension End Date29-JUN-15
Projected Date of Disposition27-OCT-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3172E
Advice Letter Filed06-FEB-15
Suspension Begin Date08-MAR-15
Suspension End Date06-JUL-15
Projected Date of Disposition03-NOV-15
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4582E
Advice Letter Filed09-FEB-15
Suspension Begin Date11-MAR-15
Suspension End Date08-JUL-15
Projected Date of Disposition05-NOV-15
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2700E
Advice Letter Filed09-FEB-15
Suspension Begin Date11-MAR-15
Suspension End Date08-JUL-15
Projected Date of Disposition05-NOV-15
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2699E
Advice Letter Filed09-FEB-15
Suspension Begin Date11-MAR-15
Suspension End Date08-JUL-15
Projected Date of Disposition05-NOV-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3173E
Advice Letter Filed09-FEB-15
Suspension Begin Date11-MAR-15
Suspension End Date08-JUL-15
Projected Date of Disposition05-NOV-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3174E
Advice Letter Filed09-FEB-15
Suspension Begin Date11-MAR-15
Suspension End Date08-JUL-15
Projected Date of Disposition05-NOV-15
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4756G
Advice Letter Filed10-FEB-15
Suspension Begin Date12-MAR-15
Suspension End Date09-JUL-15
Projected Date of Disposition06-NOV-15
GroundsAdditional Time Needed

Utility NamePacificorp (U-0901)
Advice Letter Number516E
Advice Letter Filed20-FEB-15
Suspension Begin Date25-MAR-15
Suspension End Date22-JUL-15
Projected Date of Disposition19-NOV-15
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3568G/4594E
Advice Letter Filed26-FEB-15
Suspension Begin Date28-MAR-15
Suspension End Date27-JUL-15
Projected Date of Disposition24-NOV-15
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2712E/2369G
Advice Letter Filed06-MAR-15
Suspension Begin Date05-APR-15
Suspension End Date03-AUG-15
Projected Date of Disposition01-DEC-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3191E
Advice Letter Filed17-MAR-15
Suspension Begin Date16-APR-15
Suspension End Date13-AUG-15
Projected Date of Disposition11-DEC-15
GroundsAdditional Time Needed

Utility NameThe California Center For Sustainable Energy(CCSE) (U-0930)
Advice Letter Number58E
Advice Letter Filed26-MAR-15
Suspension Begin Date25-APR-15
Suspension End Date24-AUG-15
Projected Date of Disposition22-DEC-15
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2720E
Advice Letter Filed27-MAR-15
Suspension Begin Date26-APR-15
Suspension End Date24-AUG-15
Projected Date of Disposition22-DEC-15
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number199GI3200E
Advice Letter Filed01-APR-15
Suspension Begin Date01-MAY-15
Suspension End Date28-AUG-15
Projected Date of Disposition26-DEC-15
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4616E
Advice Letter Filed06-APR-15
Suspension Begin Date06-MAY-15
Suspension End Date02-SEP-15
Projected Date of Disposition31-DEC-15
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4618E
Advice Letter Filed20-APR-15
Suspension Begin Date20-MAY-15
Suspension End Date16-SEP-15
Projected Date of Disposition14-JAN-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2727E
Advice Letter Filed20-APR-15
Suspension Begin Date20-MAY-15
Suspension End Date16-SEP-15
Projected Date of Disposition14-JAN-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2729E
Advice Letter Filed20-APR-15
Suspension Begin Date20-MAY-15
Suspension End Date16-SEP-15
Projected Date of Disposition14-JAN-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3207E
Advice Letter Filed20-APR-15
Suspension Begin Date20-MAY-15
Suspension End Date16-SEP-15
Projected Date of Disposition14-JAN-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3208E
Advice Letter Filed20-APR-15
Suspension Begin Date20-MAY-15
Suspension End Date16-SEP-15
Projected Date of Disposition14-JAN-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3209E
Advice Letter Filed23-APR-15
Suspension Begin Date23-MAY-15
Suspension End Date21-SEP-15
Projected Date of Disposition19-JAN-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4626E
Advice Letter Filed30-APR-15
Suspension Begin Date30-MAY-15
Suspension End Date28-SEP-15
Projected Date of Disposition26-JAN-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2736E
Advice Letter Filed30-APR-15
Suspension Begin Date30-MAY-15
Suspension End Date28-SEP-15
Projected Date of Disposition26-JAN-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3211E
Advice Letter Filed30-APR-15
Suspension Begin Date30-MAY-15
Suspension End Date28-SEP-15
Projected Date of Disposition26-JAN-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3214E
Advice Letter Filed01-MAY-15
Suspension Begin Date31-MAY-15
Suspension End Date28-SEP-15
Projected Date of Disposition26-JAN-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4799G
Advice Letter Filed01-MAY-15
Suspension Begin Date01-JUN-15
Suspension End Date28-SEP-15
Projected Date of Disposition26-JAN-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4640E
Advice Letter Filed12-MAY-15
Suspension Begin Date11-JUN-15
Suspension End Date08-OCT-15
Projected Date of Disposition05-FEB-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4638E
Advice Letter Filed13-MAY-15
Suspension Begin Date12-JUN-15
Suspension End Date09-OCT-15
Projected Date of Disposition06-FEB-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4639E
Advice Letter Filed13-MAY-15
Suspension Begin Date12-JUN-15
Suspension End Date09-OCT-15
Projected Date of Disposition06-FEB-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4641E
Advice Letter Filed13-MAY-15
Suspension Begin Date12-JUN-15
Suspension End Date09-OCT-15
Projected Date of Disposition06-FEB-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2745E
Advice Letter Filed13-MAY-15
Suspension Begin Date12-JUN-15
Suspension End Date09-OCT-15
Projected Date of Disposition06-FEB-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2744E
Advice Letter Filed13-MAY-15
Suspension Begin Date12-JUN-15
Suspension End Date09-OCT-15
Projected Date of Disposition06-FEB-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3218-E
Advice Letter Filed13-MAY-15
Suspension Begin Date12-JUN-15
Suspension End Date09-OCT-15
Projected Date of Disposition06-FEB-16
GroundsResolution Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3220E
Advice Letter Filed13-MAY-15
Suspension Begin Date12-JUN-15
Suspension End Date09-OCT-15
Projected Date of Disposition06-FEB-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3219E
Advice Letter Filed13-MAY-15
Suspension Begin Date12-JUN-15
Suspension End Date09-OCT-15
Projected Date of Disposition06-FEB-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4637E
Advice Letter Filed14-MAY-15
Suspension Begin Date13-JUN-15
Suspension End Date12-OCT-15
Projected Date of Disposition09-FEB-16
GroundsResolution Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2743E
Advice Letter Filed14-MAY-15
Suspension Begin Date13-JUN-15
Suspension End Date12-OCT-15
Projected Date of Disposition09-FEB-16
GroundsResolution Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3596G
Advice Letter Filed20-MAY-15
Suspension Begin Date19-JUN-15
Suspension End Date16-OCT-15
Projected Date of Disposition13-FEB-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3597G
Advice Letter Filed21-MAY-15
Suspension Begin Date17-JUL-15
Suspension End Date13-NOV-15
Projected Date of Disposition12-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3225E
Advice Letter Filed28-MAY-15
Suspension Begin Date27-JUN-15
Suspension End Date26-OCT-15
Projected Date of Disposition23-FEB-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2755E
Advice Letter Filed10-JUN-15
Suspension Begin Date10-JUL-15
Suspension End Date06-NOV-15
Projected Date of Disposition05-MAR-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2756E
Advice Letter Filed18-JUN-15
Suspension Begin Date18-JUL-15
Suspension End Date16-NOV-15
Projected Date of Disposition15-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4819G
Advice Letter Filed19-JUN-15
Suspension Begin Date19-JUL-15
Suspension End Date16-NOV-15
Projected Date of Disposition15-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3234E
Advice Letter Filed21-JUN-15
Suspension Begin Date24-JUL-16
Suspension End Date21-NOV-16
Projected Date of Disposition21-MAR-17
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4654E
Advice Letter Filed25-JUN-15
Suspension Begin Date25-JUL-15
Suspension End Date23-NOV-15
Projected Date of Disposition22-MAR-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2758E
Advice Letter Filed25-JUN-15
Suspension Begin Date25-JUL-15
Suspension End Date23-NOV-15
Projected Date of Disposition22-MAR-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2759E/2391G
Advice Letter Filed26-JUN-15
Suspension Begin Date26-JUL-15
Suspension End Date23-NOV-15
Projected Date of Disposition22-MAR-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2392G
Advice Letter Filed29-JUN-15
Suspension Begin Date01-AUG-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4822G
Advice Letter Filed29-JUN-15
Suspension Begin Date01-AUG-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3606G/4659E
Advice Letter Filed30-JUN-15
Suspension Begin Date30-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3605G/4658E
Advice Letter Filed30-JUN-15
Suspension Begin Date30-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2764E/2396G
Advice Letter Filed30-JUN-15
Suspension Begin Date30-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3240E
Advice Letter Filed30-JUN-15
Suspension Begin Date17-DEC-15
Suspension End Date14-APR-16
Projected Date of Disposition12-AUG-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3241E
Advice Letter Filed30-JUN-15
Suspension Begin Date30-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3238E
Advice Letter Filed30-JUN-15
Suspension Begin Date30-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4825G
Advice Letter Filed30-JUN-15
Suspension Begin Date30-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4826G
Advice Letter Filed30-JUN-15
Suspension Begin Date01-JAN-16
Suspension End Date29-APR-16
Projected Date of Disposition27-AUG-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4662E
Advice Letter Filed01-JUL-15
Suspension Begin Date01-JAN-16
Suspension End Date29-APR-16
Projected Date of Disposition27-AUG-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4661E
Advice Letter Filed01-JUL-15
Suspension Begin Date01-JAN-16
Suspension End Date29-APR-16
Projected Date of Disposition27-AUG-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2760E
Advice Letter Filed01-JUL-15
Suspension Begin Date31-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4831G
Advice Letter Filed01-JUL-15
Suspension Begin Date31-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSouthwest Gas Corporation (U-0905)
Advice Letter Number979G
Advice Letter Filed01-JUL-15
Suspension Begin Date31-JUL-15
Suspension End Date30-NOV-15
Projected Date of Disposition29-MAR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3243E
Advice Letter Filed08-JUL-15
Suspension Begin Date07-AUG-15
Suspension End Date04-DEC-15
Projected Date of Disposition02-APR-16
GroundsAdditional Time Needed

Utility NameCalifornia Pacific Electric Company (U-0933)
Advice Letter Number47E
Advice Letter Filed13-JUL-15
Suspension Begin Date12-AUG-15
Suspension End Date09-DEC-15
Projected Date of Disposition07-APR-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4670E
Advice Letter Filed17-JUL-15
Suspension Begin Date16-AUG-15
Suspension End Date14-DEC-15
Projected Date of Disposition12-APR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number203G/3248E
Advice Letter Filed22-JUL-15
Suspension Begin Date21-AUG-15
Suspension End Date18-DEC-15
Projected Date of Disposition16-APR-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3609G/4674E
Advice Letter Filed24-JUL-15
Suspension Begin Date23-AUG-15
Suspension End Date21-DEC-15
Projected Date of Disposition19-APR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3250E
Advice Letter Filed28-JUL-15
Suspension Begin Date27-AUG-15
Suspension End Date24-DEC-15
Projected Date of Disposition22-APR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3254E
Advice Letter Filed30-JUL-15
Suspension Begin Date29-AUG-15
Suspension End Date28-DEC-15
Projected Date of Disposition26-APR-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number4680E
Advice Letter Filed31-JUL-15
Suspension Begin Date30-AUG-15
Suspension End Date28-DEC-15
Projected Date of Disposition26-APR-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3255E
Advice Letter Filed31-JUL-15
Suspension Begin Date30-AUG-15
Suspension End Date28-DEC-15
Projected Date of Disposition26-APR-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2772E/2404G
Advice Letter Filed11-AUG-15
Suspension Begin Date10-SEP-15
Suspension End Date07-JAN-16
Projected Date of Disposition06-MAY-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4845G
Advice Letter Filed11-AUG-15
Suspension Begin Date10-SEP-15
Suspension End Date07-JAN-16
Projected Date of Disposition06-MAY-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3620GI4691E
Advice Letter Filed12-AUG-15
Suspension Begin Date11-SEP-15
Suspension End Date08-JAN-16
Projected Date of Disposition07-MAY-16
GroundsAdditional Time Needed

Utility NamePacific Gas & Electric Company (U-0039)
Advice Letter Number3619G/4690E
Advice Letter Filed12-AUG-15
Suspension Begin Date11-SEP-15
Suspension End Date08-JAN-16
Projected Date of Disposition07-MAY-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2774E/2405G
Advice Letter Filed12-AUG-15
Suspension Begin Date11-SEP-15
Suspension End Date08-JAN-16
Projected Date of Disposition07-MAY-16
GroundsAdditional Time Needed

Utility NameSan Diego Gas & Electric Company (U-0902)
Advice Letter Number2775E/2406G
Advice Letter Filed12-AUG-15
Suspension Begin Date11-SEP-15
Suspension End Date08-JAN-16
Projected Date of Disposition07-MAY-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number3259E
Advice Letter Filed12-AUG-15
Suspension Begin Date11-SEP-15
Suspension End Date08-JAN-16
Projected Date of Disposition07-MAY-16
GroundsAdditional Time Needed

Utility NameSouthern California Edison Company (U-0338)
Advice Letter Number205GI3258E
Advice Letter Filed12-AUG-15
Suspension Begin Date11-SEP-15
Suspension End Date08-JAN-16
Projected Date of Disposition07-MAY-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4846G
Advice Letter Filed12-AUG-15
Suspension Begin Date11-SEP-15
Suspension End Date08-JAN-16
Projected Date of Disposition07-MAY-16
GroundsAdditional Time Needed

Utility NameSouthern California Gas Company (U-0904)
Advice Letter Number4847G
Advice Letter Filed12-AUG-15
Suspension Begin Date11-SEP-15
Suspension End Date08-JAN-16
Projected Date of Disposition07-MAY-16
GroundsAdditional Time Needed