| Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of proposed 
              construction of the DeversPalo Verde No. 2 (DPV2) Transmission 
              Line Project. An application for this project was submitted to the 
              CPUC on April 11, 2005. The application was determined to be 
              complete and in compliance with CPUC requirements on September 30, 
              2005. The CPUC approved the DPV2 Project on January 25, 2007 in 
              Decision 
              D.07-01-040 and certified the EIR as being in compliance with 
              the requirements of CEQA. 
             On May 14, 2008, SCE filed a Petition for Modification (PFM) of 
              the existing Certificate for Public Convenience and Necessity (CPCN) 
              approved per Decision D.07-01-040. SCE requested that the CPUC authorize 
              SCE to construct DPV2 facilities in only the California portion 
              of DPV2 and the Midpoint Substation near Blythe, California. The 
              CPUC approved SCE’s PFM on November 20, 2009 in Decision 
              D.09-11-007. 
             This site provides access to public documents and information relevant 
              to the CEQA review process. 
             Focused Final Supplemental Environmental 
              Impact Report  Released April 29, 2011
             The Draft Supplemental EIR was released on February 22, 2011 
              and is available here. The comment period 
              on the Draft Supplemental EIR closed on April 8, 2011. Twelve 
              comment letters were received and are available here. 
             The Final Supplemental EIR was released on April 29, 2011 
              and is available here. The Final Supplemental 
              EIR includes all comments and responses to comments that were submitted 
              during the comment period on the Draft Supplemental EIR. 
             Background. After the CPUC's 2009 Decision regarding the 
              PFM, several large solar power projects were proposed in the Blythe 
              area. Two of these projects, the Blythe Solar Power Project and 
              the Genesis Solar Energy Project, have requested interconnection 
              to the electricity grid at the Desert Southwest–Midpoint Substation. 
              As a result, the solar developers and SCE developed a plan to expand 
              the Midpoint Substation, now known as the Colorado River Substation, 
              to allow the required space for generation tie lines to be interconnected 
              with the SCE 500 kV transmission system. SCE will file a Permit 
              to Construct application addressing the substation expansion. This 
              expansion was not covered in the original EIR/EIS because the solar 
              power projects had not yet been proposed. 
             During 2009 to 2010, the Blythe Solar Power Project and the Genesis 
              Solar Energy Project have been evaluated under CEQA and NEPA by 
              the BLM and the California Energy Commission. The environmental 
              review documents addressed the Colorado River Substation expansion 
              but they did not adequately cover all issues that the CPUC requires 
              to be addressed in accordance with CEQA. Therefore, the CPUC has 
              concluded that it will prepare a Focused Supplemental EIR to address 
              only the specific issues not yet covered for its purposes by the 
              previous environmental review. 
             A Notice of Preparation (NOP) was sent to interested agencies 
              and members of the public in October 2010 and can be accessed here. 
              The CPUC held a 30-day scoping period soliciting information regarding 
              the topics that should be included in the Focused Supplemental EIR 
              for the Colorado River Substation expansion. Copies of all letters 
              received and a summary of the scoping process and scoping comments 
              are included in a Scoping Report (December 2010), which can be accessed 
              here. 
             Draft and Final Environmental 
              Impact Report/Environmental Impact Statement The CPUC and BLM released the Draft Environmental 
              Impact Report/Environmental Impact Statement (Draft EIR/EIS) 
              for the proposed project on May 4, 2006. The submittal period for public comments on the Draft EIR/EIS was 
              extended from July 5, 2006 to August 11, 2006. The Final Environmental Impact Report/Environmental 
              Impact Statement (Final EIR/EIS) was issued on October 24, 
              2006. The Final EIR/EIS consists of three volumes. Volumes I and 
              II are completely re-printed from the Draft EIR/EIS. Changes made 
              to the Draft EIR/EIS are marked in Volumes I and II: inserted 
              text is underlined and deleted text is shown in strikeout. 
              Volume III consists of all comments in the Draft EIR/EIS and responses 
              to comments. Over 475 pages of comments on the Draft EIR/EIS were submitted 
              to the BLM and the CPUC, including transcripts from the July 2006 
              Public Participation Hearings. NEPA Process and BLM Record of 
              Decision The BLM published a Notice of Availability of the Final EIR/EIS 
              for DPV2 on March 15, 2007 in the Federal Register (Volume 
              72, Number 50; page 12185). After completion of the Final Supplemental 
              EIR, the BLM will prepare a Record of Decision (ROD) to document 
              the selected alternatives and adopted mitigation measures. The Department of the Interior (DOI) Control No. for the EIS is 
              FES-06-48. Other Documents Available Notice of Preparation of an Environmental Impact 
              Report (EIR) and Notice of Public Scoping Meetings (October 21, 
              2005)Notice of Intent (December 7, 2005; Federal 
              Register Vol. 70, No. 234)
 Scoping Report (December 2005)
 Addendum to the Scoping Report 
              (February 2006)
 Notice of Availability (October 24, 2006)
 SCE’s Application and Proponent’s Environmental 
              Assessment (April 11, 2005)
 Construction Progress and Mitigation 
              Monitoring  Construction will begin once the CPUC issues Notices to Proceed 
              for each segment. Issuance of Notices to Proceed will be contingent 
              upon SCE compliance with pre-construction requirements as specified 
              by the approved mitigation measures. 
             The CPUC in conjunction with SCE, BLM, USFS and other Responsible 
              Agencies, are in the process of drafting a Mitigation Monitoring 
              Compliance and Reporting Program (MMCRP) to ensure compliance with 
              mitigation measures approved in the Final EIR/EIS, as well as with 
              the terms and conditions associated with the BLM right-of-way. Once 
              the MMCRP document is finalized, it will be found here. 
             A CPUC Environmental Monitor will be monitoring construction activities 
              to ensure that they are conducted in accordance with the approved 
              mitigation measures and permit conditions. Once construction begins, 
              this site will hold all weekly reports documenting this monitoring 
              activity. Reports on construction status and activities are posted 
              here. 
             For Additional Information
             The environmental team for the DPV2 Project can be reached at: 
              Voice messages or faxes: (800) 491-6153 Email: dpv2@aspeneg.com The CPUC's Project Manager is: Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email: bcb@cpuc.ca.gov |