Welcome to the California Public Utilities Commission (CPUC) website
for the California Environmental Quality Act (CEQA) review of proposed
construction of the DeversPalo Verde No. 2 Transmission
Line Project. An application for this project was submitted to the
CPUC on April 11, 2005. The application was determined to be complete
and in compliance with CPUC requirements on September 30, 2005.
This site provides access to public documents and information relevant
to the CEQA review process.
Background
SCE has filed an application with the CPUC to construct the DeversPalo
Verde No. 2 Transmission Line Project (DPV2). The CPUC is the
CEQA lead agency and the U.S. Bureau of Land Management is the lead
agency under the National Environmental Policy Act (NEPA). This
project was approved by the California Independent System Operator
(CAISO) in February 2005.
The DPV2 Project as proposed by SCE includes a new 230-mile 500
kV line from the Harquahala Substation (in Arizona, near the Palo
Verde nuclear power plant) to SCE's Devers Substation (in North
Palm Springs, California). The 500 kV portion would follow the existing
SCE 500 kV transmission line, DeversPalo Verde No. 1
(DPV1).
The DPV2 Project also includes upgrades to an additional 50 miles
of 230 kV transmission lines west of the Devers Substation. Forty
miles of 230 kV transmission line from Devers Substation to San
Bernardino Junction at the western end of San Timoteo Canyon would
be reconfigured and two separate 230 kV corridors, from San Bernardino
Junction to SCE's Mountain View Substation and from San Bernardino
Junction to SCE's Vista Substation would be reconductored. Map 1-1
shows the project from Devers Substation to
Harquahala Generation Station and Map 1-2 shows
the segment west of Devers Substation.
Draft Environmental Impact Report/Environmental
Impact Statement
The CPUC and BLM have released the Draft
EIR/EIS for the proposed project. The public comment period
for this document has been extended from July 5, 2006 to August 11,
2006.
Public Meetings on the
Draft EIR/EIS
On June 6, 7, and 8, 2006, the CPUC and BLM held a series of public
workshops at which the public asked questions about the document
and the Proposed Project. In addition, the CPUC's Administrative
Law Judge held two Public Participation Hearings at which interested
parties made formal comments on the Draft EIR/EIS or other aspects
of the CPUC's proceeding.
One additional workshop and one Public Participation Hearing have
been scheduled. The schedule for these meetings is below.
July 24, 2006 Public Meetings
|
Location |
City of Beaumont Civic Center
Council Chambers
550 E. 6th Street, Beaumont, CA 92223
|
Time |
4:00 to 7:00 p.m. Workshop
7:00 to 8:30 p.m. Public Participation Hearing
|
Directions |
Exit I-10 at Beaumont Avenue and turn north
for 2 blocks to East 6th Street. Turn right (east) for 2 blocks
to the Civic Center.
|
Other Documents Available
Notice of Preparation of an Environmental Impact
Report (EIR) and Notice of Public Scoping Meetings (October 21,
2005)
Notice of Intent (December 7, 2005; Federal
Register Vol. 70, No. 234)
Scoping Report (December 2005)
Addendum to the Scoping Report
(February 2006)
SCE’s Application and Proponent’s Environmental
Assessment (April 11, 2005)
For Additional Information
The CPUC, through its Environmental Review Team, is conducting
an environmental review of the project. To request additional information
or to be added to the mailing list, please contact us by email,
fax, or phone, as follows:
The CPUC's Project Manager is:
Billie Blanchard, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-2068
Fax (415) 703-2200
Email: bcb@cpuc.ca.gov
|