Welcome to the California Public Utilities Commission (CPUC) website
for the environmental review and monitoring of Southern California
Edison's (SCE's) Eldorado-Lugo-Mohave Series Capacitor Project (ELM
Project). SCE submitted an application for a Permit to Construct (PTC)
for the Project to the CPUC on May 2, 2018 (Application A.18-05-007).
The Application was accompanied by a Proponent's
Environmental Assessment. On January 9, 2019, the CPUC directed
SCE to amend it application and to refile it as an application for
a Certificate of Public Convenience and Necessity (CPCN), rather than
for a PTC. SCE submitted its amended
application for a CPCN (6.4MB)
on April 19, 2019.
The proposed project is being reviewed by the CPUC under the California
Environmental Quality Act (CEQA). On August 12, 2019, the CPUC
published an Initial Study/Mitigated Negative
Declaration (IS/MND) for the Proposed Project. This began a
30-day public review and comment period for the IS/MND. The comment
period closed on September 13, 2019. Comment
letters were received from 11 parties. The letters and the CPUC
responses to them will be included in the Final IS/MND, along with
revisions to the IS/MND, if required. The Final IS/MND will be posted
on this website when available.
The project is located in San Bernardino County, California; Clark
County, Nevada; the cities of Hesperia, California, and Boulder
City, Nevada; the unincorporated community of Lucerne Valley in
California; and the unincorporated communities of Searchlight and
Laughlin in Nevada. A map is provided here.
An overview of the Proposed Project is provided below.
The Proposed Project is being reviewed under both the California
Environmental Quality Act (CEQA) and the National Environmental
Policy Act (NEPA). The CPUC is the CEQA lead agency and the Bureau
of Land Management (BLM) is the NEPA lead agency, with the National
Park Service (Mojave National Preserve) as a Cooperating Agency
under NEPA. This website provides access to public documents and
information relevant to the CEQA review processes and mitigation
monitoring. The BLM project website will be linked here when it
is established.
DESCRIPTION OF PROPOSED
PROJECT
The ELM Project consists of the following major components:
- Construct 2 new 500 kV mid-line series capacitors (i.e., the
proposed Newberry Springs Series Capacitor and Ludlow Series Capacitor)
and associated equipment.
- Provide 2 communication paths between the series capacitor sites:
- Install approximately 2 miles of overhead and 500 feet of
underground telecommunications facilities as one path to connect
the proposed series capacitors to SCE's existing communication
system.
- Install approximately 2 miles of underground telecommunications
facilities as a second communication path to connect the series
capacitors to SCE's existing communication system.
- Provide station light and power to the proposed series capacitors
by extending and/or rerouting existing lines to create approximately
2 miles of overhead and 700 feet of underground 12 kV distribution
circuits. (The new distribution poles would support overhead telecommunication
facilities as well as the electric distribution lines.)
- Construct 3 new fiber optic repeater facilities (Barstow, Kelbaker,
and Lanfair) within the Lugo-Mohave ROW.
- Install distribution lines for light and power at the 3 proposed
fiber optic repeater sites.
- Install underground telecommunications facilities from existing
transmission structures to the Barstow, Kelbaker, and Lanfair
fiber optic repeater sites.
- Address 16 potential overhead clearance discrepancies at 14
locations by:
- Relocating, replacing, or modifying existing transmission,
subtransmission, and distribution facilities at approximately
12 locations along the Eldorado-Lugo, Eldorado-Mohave, and
Lugo-Mohave 500 kV Transmission Lines to address 14 of the
overhead clearance discrepancies. Tower modifications would
include raising 9 towers approximately 18.5 feet by inserting
new lattice-steel sections in tower bodies.
- Performing minor grading at 2 locations along the Lugo-Mohave
500 kV Transmission Line to address 2 of the overhead clearance
discrepancies.
- Install approximately 235 miles of optical ground wire (OPGW)
(approximately 59 miles on the Eldorado-Mohave Transmission Line
and approximately 173 miles on the Lugo-Mohave Transmission Line,
including approximately 3 miles of underground telecommunications
facilities in the vicinity of the Mohave Substation).
- Modify and strengthen the ground wire peak of existing suspension
towers where OPGW splices would occur (some of these towers would
also require minor modifications to the steel in the tower body).
- Install approximately 2,000 feet of underground telecommunications
facilities within the existing Lugo, Mohave, and Eldorado Substations.
- Within Lugo Substation, perform modifications on the existing
series capacitors and install new terminating equipment and remove
2 existing tubular steel poles (TSPs) and install 2 new TSPs on
the Eldorado-Lugo and Lugo-Mohave 500 kV Transmission Lines.
- Within the Eldorado Substation, perform modifications on the
existing series capacitors and upgrade the terminal equipment
on the Eldorado-Lugo 500 kV Transmission Line.
- Within the Mohave Substation, replace existing series capacitors
on the Lugo-Mohave 500 kV Transmission Line and install new terminal
equipment on the Eldorado-Mohave and Lugo-Mohave 500 kV Transmission
Lines.
- Within LADWP's McCullough Substation, replace 5 existing 500
kV 50 kA circuit breakers with 5 new 500 kV 63 kA circuit breakers.
- Install (if necessary) cathodic protection on approximately
60 miles of SoCalGas's natural gas pipelines parallel to SCE's
Lugo-Mohave 500 kV Transmission Line.
Application Completeness
Review
The CPUC determined that SCE's application was not complete as
submitted on May 2, 2018, and identified the deficiencies in
letters to SCE on June 1,
2018 and August 27,
2018. SCE addressed the CPUC's comments and provided
responses to the individual deficiencies from July 2018 to September
2018. SCE's Application and PEA were deemed complete for review
by the CPUC on October 10,
2018.
Below are links to SCE’s responses to CPUC’s completeness review
questions. Each bold link goes to a group of questions/responses.
Some attachments to the responses are provided separately in individual
links beneath the bold link.
Questions 1 through 5
Q.02 B-3 Attachments
(.zip file, right-click to download) (5.2MB)
Q.05B
B-5 Supplemental Attachment 1 of 2 Newberry Capacitor (right-click
to download; requires Microsoft Excel)
Q.05B
B-5 Supplemental Attachment 2 of 2 Ludlow Capacitor (right-click
to download; requires Microsoft Excel)
Questions 6 through 45
Q.12 Attachment (right-click
to download; requires Microsoft Excel)
Q.40
B-18 Attachment 1
Q.42
Q.43 (right-click to download; requires Microsoft Excel)
Q.43
3.75 (right-click to download; requires Microsoft Excel)
Questions 46 through 49
(9.3MB)
Q46
5.3 Air Quality Attachment I AQ and GHG Activity Assumptions and
EFs (right-click to download; requires Microsoft Excel)
Question 50
Q.50A Attachment
1 Ludlow (7.4MB)
Q.50A Attachment
2 Mohave (7.9MB)
Q.50A
Attachment 3 Newberry Springs (6.5MB)
Questions 51 through 55
(5.8MB)
Q.55
Attachment 1 300-ft Mailing List (right-click to download; requires
Microsoft Excel)
Questions 56 through 57
Questions 58 through 59
Questions 60 through 65
Q.60
Bio-Hydro Survey Areas (.zip file, right-click to download)
(5.7MB)
Q.63 Survey
Impact Table (right-click to download; requires Microsoft Excel)
Question 67 (29.3MB)
Questions 68 through 73
COMMENTS & QUESTIONS?
If you have comments or questions regarding the project, please
contact us using the CPUC's project email or voicemail, as follows:
|