|
STATE OF CALIFORNIA
|
![]() |
|
![]() ![]() |
These files are in Portable Document Format (PDF). To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your PC. Note: For best results in displaying the largest files (see sizes shown in parentheses below for files larger than 5 MB), right-click the file's link, click "Save Target As" to download the file to a folder on your hard drive, then browse to that folder and double-click the downloaded file to open it in Acrobat. |
![]() |
|||||||||||||||||||||||
![]() |
This page was last updated: August 2025
Welcome to the California Public Utilities Commission (CPUC) website for the environmental review of Pacific Gas and Electric Company's (PG&E's) Moraga-Oakland X 115 kV Rebuild Project (MOX Project). The Project is located in in the City of Orinda, unincorporated areas of Contra Costa County, and the cities of Oakland and Piedmont within Alameda County, California; a map is provided here. PG&E submitted a Permit to Construct (PTC) application for the Project to the CPUC on November 15, 2024 (Application A.24-11-005). If approved by the CPUC, the Project is anticipated to begin construction in August 2028. The estimated Project completion date is July 2031. The proposed Project will be reviewed under the California Environmental Quality Act (CEQA). The CPUC will prepare a CEQA environmental document as the CEQA lead agency. This website provides access to public documents and information relevant to the CEQA environmental review process. An overview of the proposed Project is provided below: CPUC Review Process Click here for more information about the CPUC’s decision and review process. Click here for CPUC’s Proceeding page. For additional information on the CPUC proceeding, contact the Public Advisor's Office. DESCRIPTION OF THE PROPOSED PROJECT According to PG&E, the purpose of the Project is to replace power line equipment that has reached the end of its useful life for safe operation of the lines. The objectives of the project are:
The Project would involve proposed upgrades to approximately 5-miles of four overhead 115 kV power lines between Moraga and Oakland X substations in the City of Orinda, unincorporated areas of Contra Costa County, and the cities of Oakland and Piedmont within Alameda County. The two existing parallel double-circuit power lines are located within existing PG&E land rights, and the Project would rebuild the four overhead lines into four hybrid lines, with both overhead (~4 miles) and underground (~1 mile) segments. Existing towers, poles and conductors would be replaced either with overhead rebuild or underground components, and minor modifications would occur within the existing substations. Some recently replaced power line structures would be reused or reused with some modification. Single circuit transition structures would support the connection between the overhead and underground portions of each line. Double-circuit transition structures would be used to connect the underground portion to existing overhead line terminals at Oakland X Substation. Additionally, the rebuild would include the installation of optical ground wire on aboveground structures with a communication cable continuing within the underground portion. Detail of PG&E's proposal is provided in Chapter 3 of PG&E’s Proponent’s Environmental Assessment (PEA). PG&E’s Community Wildfire Safety Program A link for more information on PG&E’s Community Wildfire Safety Program, including its Wildfire Mitigation Plan, can be found here. Work under the Program is independent of the proposed Project and includes undergrounding powerlines; system hardening; enhancing powerline safety settings; reducing impacts from Public Safety Power Shutoffs; and managing trees and vegetation near powerlines. ENVIRONMENTAL REVIEW As the CEQA Lead Agency, the CPUC has prepared an EIR to evaluate the environmental effects of the proposed Project. The following table includes estimated milestones and anticipated dates for the CEQA review process. Project Milestones as of April 2025
* Pre-construction mitigation compliance and ministerial permitting to occur between project approval and PG&E’s start of construction. Proponent's Environmental Assessment (PEA) and Application PG&E filed an application and PEA for the MOX Project on November 15, 2024. CPUC Application Review, Data Requests, and Applicant Responses The CPUC has reviewed PG&E's application and PEA, and on December 12, 2024, determined that the application and PEA are complete. The CPUC submitted the following data requests to PG&E regarding their application information. Project Scoping The CPUC has prepared a Notice of Preparation (NOP) of an EIR for the Project to solicit agency and public input on the scope of the EIR. The NOP may be viewed here. During the scoping period, beginning February 25, 2025, and ending March 27, 2025, all interested parties, including responsible and trustee agencies, groups, and the public, are invited to provide input on the scope of the EIR. The CPUC held two virtual public scoping meetings during a 30-day public comment period to obtain input from agencies and the public on the scope and content of the EIR. The scoping presentation may be viewed here. Recordings of the virtual scoping meetings may be viewed here for the afternoon meeting, and here for the evening meeting. The Scoping Report, summarizing the meeting presentations and comments submitted, may be view here. Draft Environmental Impact Report The CPUC published the Draft EIR on August 12, 2025 for a 45-day public review period, which will end on September 26, 2026. Notice of Availability
Draft EIR Public Review A 45-day comment period for the Draft EIR begins Tuesday, August 12, 2025, and ends at 5:00 p.m. Friday, September 26, 2025. Written comments should reference the Moraga-Oakland X Project, A.24-11-005. Include your name, organization (if applicable), mailing address, and email address of the contact person for all future notifications related to this process. Please send your comments by mail to:
Moraga-Oakland X Project MOX@aspeneg.com Draft EIR Public Meetings To provide information about the proposed Project, CEQA process, and provide an opportunity to submit verbal comments on the Draft EIR, the CPUC will hold two virtual scoping meetings on September 3, 2025. Zoom Meeting will be held Thursday, September 3, 2025
COMMENTS & QUESTIONS If you have comments, complaints, or questions regarding the Project, please contact us using the CPUC's MOX Project email or leave a message on the Project voicemail, as follows: Project e-mail: MOX@aspeneg.com
Project voicemail: 877-225-2127 The CPUC's Project Manager is: Tharon Wright, CPUC Project Manager California Public Utilities Commission c/o Aspen Environmental Group 235 Montgomery Street, Suite 967 San Francisco, CA 94104-2920 |
||||||||||||||||||||||
![]() |
This page contains tables and is best viewed with Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator. |
||||||||||||||||||||||
Project Home Page - CPUC
Environmental Information - CPUC Home
|