PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATION
MONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (August 31 through September 6, 1997)

 
TO: Martha Sullivan, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: PPSI: Week 11 Report; August 31 through September 6, 1997
DATE: September 8, 1997

A. INTRODUCTION

Construction continued on Segment 2, Angeles National Forest (MP 33 to 57) and Segment 5B (Milepost (MP) 108 to 118).

 

B. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles Forest Service involves very steep slopes and requires significant time and additional equipment for trenching, stringing, and other pipe laying activities. Segment 2A Environmental Monitor (EM), Stan Harding was on-site. PPSI has 12 craft inspectors, eight environmental inspectors, and eight Native American monitors inspecting the work of approximately 103 contractor employees. Construction progress from September 1 through 6, 1997 included the following:

Segment 2A Activities:

Milepost (all mileposts are approximate)

  • Pot-hole - Complete to Templin Highway
  • Clear & Grade 47.39 to 48.15
  • Trench 45.11 to 48.02
  • Stringing 44.17 to 46.90
  • Bending 43.16 to 45.23
  • Welding 41.42 to 44.23
  • Coating 40.15 to 43.05
  • Lower-In 39.79 to 40.84
  • Tie-In 37.88 to 38.92
  • Backfill 36.93 to 38.75
  • Conduit 36.93 to 38.75

 

Non-Compliance Events for Segment 2A

Mitigation Measure/PC
Non-compliance Level
First Observed
Corrected
Status
B-AQ.1.2 - Environmental monitor present during all earth-moving activities within streams
3 9/4/97 Yes Acceptable
B-AQ.1.4 - Work at wetlands and streams occurs within construction corridor
3
9/4/97
Yes
Acceptable

Segment 2A Comments:

Two non-compliance events occurred at approximately MP 47.62 (Stream Crossing #40).

Segment 2A Schedule for Next Week:

No new crews are scheduled to begin. Construction will continue south of Liebre Gulch.

C. SEGMENT 5B CONSTRUCTION PROGRESS

This segment involves construction in railroad and road right-of-ways through industrial areas. Segment 5B EM, Pete Messick, has been on-site during day construction (7 a.m. until 4 p.m.); EM Brooke Langle has been on-site during night construction (7 p.m. until 5 a.m.). PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 25 contractor employees during day construction; and one craft inspector, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 15 contractor employees during night construction. Crews worked 9 to 10-hour shifts. Construction progress from September 1 through 5, 1997 included the following:

 

Segment 5B/5C Activities:

  Milepost (all mileposts are approximate)
Clear and Grade 113.11 to 114.71 (days)
Trench 113.11 to 113.65 (days)
Completed Anaheim Street crossing , MP 118.8 (nights)

Non-Compliance Events for Segment 5B

Mitigation Measure/PC
Non-compliance Level
First Observed
Corrected
Status
T-PP2 - Fencing used at open trenches at the end of workday

3

9/2/97

Yes

Acceptable
T.12.2 - Railroad representatives shall be on site at all times during construction along rail lines

3

9/5/97

No

Unacceptable

Segment 5B Comments: On 9/2/97, at approximately 4 p.m., an 8-inch water line was broken at Alameda Street near Pacific Coast Highway (approximately MP 117.9) during excavation activities. All necessary contacts were made and the leak was controlled by 6:20 p.m. Union Pacific Railroad has been notified that mitigation measures for the PPSI project require that a flagman be present during construction activities along the railroad right-of-way; however, UPRR has not yet provided a flagman.

Segment 5B Schedule for Next Week:

Night construction scheduled to begin at Del Amo Avenue and pipelaying will begin on Segment 5C.

D. VARIANCES

The following variance was approved September 1 through 5, 1997.

Variance #

Description

Segment(s) Variance Applies

Agency Decision

6, Amended

Alternatively fueled vehicles usage

2

Approved

E. EXTRA WORK SPACE

No extra work spaces were approved September 1 through 5, 1997.

F. GENERAL PLANS FOR NEXT WEEK

Segment 2A and Segment 5C to continue. Segments 1 and 4 expected to begin September 15. Segment 3 to begin in late September; El Segundo portion of Segment 4 (Watts Junction to Chevron El Segundo Refinery) expected to begin in October.

 