WEEKLY REPORT (September 8 through 14, 1997)
TO: Martha Sullivan, CPUC/Rich Borden, ANF | ||||||||||||
FROM: Hamid Rastegar/Kris Thorne | ||||||||||||
RE: PPSI: Week 12 Report; September 8 through 14, 1997 | ||||||||||||
DATE: September 18, 1997 A. INTRODUCTION Construction continued on Segment 2, Angeles National Forest (MP 33 to 57) and Segment 5 (Milepost (MP) 108 to 118).
B. SEGMENT 2A CONSTRUCTION PROGRESS This segment within the Angeles Forest Service involves very steep slopes and requires significant time and additional equipment for trenching, stringing, and other pipe laying activities. Segment 2A Environmental Monitor (EM), Stan Harding was on-site. PPSI has 12 craft inspectors, eight environmental inspectors, and eight Native American monitors inspecting the work of approximately 130 contractor employees. Construction progress from September 8 through 13, 1997 included the following:
Segment 2A Activities: Milepost (all mileposts are approximate)
C. SEGMENT 5B CONSTRUCTION PROGRESS This segment involves construction in railroad and road right-of-ways through industrial areas. Segment 5B EM, Pete Messick, has been on-site during day construction (7 a.m. until 4 p.m.); EM Brooke Langle has been on-site during night construction (7 p.m. until 5 a.m.). PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 25 contractor employees during day construction; and one craft inspector, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 15 contractor employees during night construction. Crews worked 9 to 10-hour shifts. Construction progress from September 8 through 12, 1997 included the following:
D. VARIANCES The following variances were approved September 8 through 12, 1997.
E. EXTRA WORK SPACE No extra work spaces were approved September 8 through 12, 1997. F. GENERAL PLANS FOR NEXT WEEK Segment 2A and Segment 5C to continue. Segments 1 and 4 expected to begin September 17. Segment 3 to begin in late September; El Segundo portion of Segment 4 (Watts Junction to Chevron El Segundo Refinery) expected to begin in October. |