WEEKLY REPORT (September 22 through 28, 1997)
TO: Martha Sullivan, CPUC/Rich Borden, ANF | ||||||||||||||||
FROM: Hamid Rastegar/Kris Thorne | ||||||||||||||||
RE: PPSI: Week 14 Report; September 22 through 28, 1997 | ||||||||||||||||
DATE: September 29, 1997 A. INTRODUCTION Construction continued on Segment 2, Angeles National Forest (Milepost (MP) 33 to 57) and Segment 5 (MP 108 to 118). B. SEGMENT 2A CONSTRUCTION PROGRESS This segment within the Angeles Forest Service involves very steep slopes and requires significant time and additional equipment for trenching, stringing, and other pipe laying activities. Segment 2A Environmental Monitor (EM), Stan Harding was on-site. PPSI has 12 craft inspectors, six environmental inspectors, and six Native American monitors inspecting the work of approximately 160 contractor employees. Construction progress from September 22 through 28, 1997 included the following: Segment 2A Activities: Activity Milepost (approximate)
C. SEGMENT 5 CONSTRUCTION PROGRESS This segment involves construction in railroad and road right-of-ways through industrial areas. Segment 5 EM, Pete Messick, has been on-site during day construction (7 a.m. until 4 p.m.). PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 20 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B except where skips between segments remain. Skips will be tied-in when the county contractors are no longer working in the areas. Construction progress from September 22 through 26, 1997 included the following:
D. VARIANCES The following variance was approved September 22 through 26, 1997.
E. EXTRA WORK SPACE No extra work spaces were approved September 22 through 26, 1997. F. GENERAL PLANS FOR NEXT WEEK Segment 2A and Segment 5C to continue. Segment 3 Wolfskill Bike Path 200-foot segment is projected to begin on Monday, September 29. Segment 4 projected to begin October 1. Segments 1 and 3 are expected to begin in early October; El Segundo portion of Segment 4 (Watts Junction to Chevron El Segundo Refinery) expected to begin in October. |