WEEKLY REPORT (September 29 through October 5, 1997)
TO: Martha Sullivan, CPUC/Rich Borden, ANF | ||||||||||||||||||||||||||||
FROM: Hamid Rastegar/Kris Thorne | ||||||||||||||||||||||||||||
RE: PPSI: Week 15 Report; September 29 through October 5, 1997 | ||||||||||||||||||||||||||||
DATE: October 6, 1997 A. INTRODUCTION Construction continued on Segment 2, Angeles National Forest (Milepost (MP) 33 to 57) and Segment 5 (MP 108 to 118). Construction began on Segment 3 (MP 74 to 99) B. SEGMENT 2A CONSTRUCTION PROGRESS This segment within the Angeles Forest Service involves very steep slopes and requires significant time and additional equipment for trenching, stringing, and other pipe laying activities. Segment 2A Environmental Monitor (EM), Stan Harding was on-site. PPSI has 12 craft inspectors, six environmental inspectors, and six Native American monitors inspecting the work of approximately 160 contractor employees. Construction progress from September 29 through October 4, 1997 included the following:
Non-Compliance Events for Segment 2A
C. SEGMENT 3 CONSTRUCTION PROGRESS This segments onsite environmental monitor is Brooke Langle. Segment 3 runs from Sylmar to Dodger Stadium. PPSI has two craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 15 contractor employees during construction of Segment 3. Construction at the Bike Path extension in the City of San Fernando (Wolfskill and Jessie Streets) began on Tuesday, September 30. Construction progress from September 29 through October 3, 1997 included the following:
D. SEGMENT 5 CONSTRUCTION PROGRESS This segment involves construction in railroad and road right-of-ways through industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during day construction (7 a.m. until 4 p.m.). PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 20 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B except where skips between segments remain. Skips will be tied-in when the county contractors are no longer working in the areas. Construction progress from September 29 through October 3, 1997 included the following: Segment 5C Activities: Milepost (approximate) Clear & Grade complete Pot-hole complete Trench 115.22 Welding complete Lowering-In complete Conduit complete Bore Pits Dominguez Street and Del Amo Blvd complete
E. VARIANCES The following variances were approved September 29 through October 3, 1997.
F. EXTRA WORK SPACE The following construction yard addition was approved September 29 through October 3, 1997.
G. GENERAL PLANS FOR NEXT WEEK Segments 2A, 3, and 5C to continue. Segment 4 projected to begin October 8. Segment 1 is projected to begin in mid-October; El Segundo portion of Segment 4 (Watts Junction to Chevron El Segundo Refinery) projected to begin in October. |