PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATION
MONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (September 29 through October 5, 1997)

TO: Martha Sullivan, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: PPSI: Week 15 Report; September 29 through October 5, 1997
DATE: October 6, 1997

A. INTRODUCTION

Construction continued on Segment 2, Angeles National Forest (Milepost (MP) 33 to 57) and Segment 5 (MP 108 to 118). Construction began on Segment 3 (MP 74 to 99)

B. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles Forest Service involves very steep slopes and requires significant time and additional equipment for trenching, stringing, and other pipe laying activities. Segment 2A Environmental Monitor (EM), Stan Harding was on-site. PPSI has 12 craft inspectors, six environmental inspectors, and six Native American monitors inspecting the work of approximately 160 contractor employees. Construction progress from September 29 through October 4, 1997 included the following:

Segment 2A Activities:

Activity Milepost (approximate)

• Pot-hole Complete to Templin Highway

• Coating Complete to Templin Highway

• Clear & Grade Complete to Templin Highway

• Lower-In 45.09 to 45.10

• Stringing Complete to Templin Highway

• Backfill 42.63 to 44.04

• Welding Complete to Templin Highway

• Clean-up 38.12 to 43.19

• Reveg 33.48 to 35.46

Non-Compliance Events for Segment 2A

Mitigation Measure/PC
Non-compliance Level
First Observed
Corrected
Status
A-2.1 - Keep spoil on ROW

3

10/3/97

Yes

Acceptable

Segment 2A Comments:

One non-compliance event occurred. Mini-crews continue to work on north and south slopes of Liebre Gulch. Revegetation subcontractor continues to reseed ROW and install jute matting on steep slopes. No crews worked on Sunday. The Forest Service is requiring that construction within the forest be completed by November 1, 1997.

Segment 2A Schedule for Next Week:

Lowering-in to resume with tie-ins to follow on Monday.

C. SEGMENT 3 CONSTRUCTION PROGRESS

This segment’s onsite environmental monitor is Brooke Langle. Segment 3 runs from Sylmar to Dodger Stadium. PPSI has two craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 15 contractor employees during construction of Segment 3. Construction at the Bike Path extension in the City of San Fernando (Wolfskill and Jessie Streets) began on Tuesday, September 30. Construction progress from September 29 through October 3, 1997 included the following:

Segment 3 Activities:

Milepost (approximate)

• Cased bore 78.37

• Conduit 78.37

Segment 3 Comments:

No non-compliance events occurred. Crew placed pipe and conduit at site. Oleanders were removed for trenching of the 80-foot section west of rail tracks.

Segment 3 Schedule for Next Week:

Finish work at Wolfskill and Jessie Streets then begin potholing at north end of segment.

D. SEGMENT 5 CONSTRUCTION PROGRESS

This segment involves construction in railroad and road right-of-ways through industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during day construction (7 a.m. until 4 p.m.). PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 20 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B except where skips between segments remain. Skips will be tied-in when the county contractors are no longer working in the areas. Construction progress from September 29 through October 3, 1997 included the following:

Segment 5C Activities:

Milepost (approximate)

• Clear & Grade complete

• Pot-hole complete

• Trench 115.22

• Welding complete

• Lowering-In complete

• Conduit complete

• Bore Pits Dominguez Street and Del Amo Blvd complete

Segment 5 Comments: No non-compliance events occurred.

Segment 5 Schedule for Next Week:

Construction will continue on Segment 5C at Alameda Street between the 405 freeway ramp and the 223rd overpass. No night work is anticipated for the coming week.

E. VARIANCES

The following variances were approved September 29 through October 3, 1997.

Variance #

Description

Segment(s) Variance Applies

Agency Decision

12

Trenching Old Ridge Route at MPs 46.84 & 46.99

2A

Approved

23

Open cut CA Aqueduct access road at Gorman Creek crossing

2A

Approved

F. EXTRA WORK SPACE

The following construction yard addition was approved September 29 through October 3, 1997.

 

Construction Yard/Staging Area

Applicable Segment(s)

Agency Decision

Segment 3 Construction Yard, City of San Fernando, CA

3

Approved

 

G. GENERAL PLANS FOR NEXT WEEK

Segments 2A, 3, and 5C to continue. Segment 4 projected to begin October 8. Segment 1 is projected to begin in mid-October; El Segundo portion of Segment 4 (Watts Junction to Chevron El Segundo Refinery) projected to begin in October.