WEEKLY REPORT (October 13 through 19, 1997)
TO: Martha Sullivan, CPUC/Rich Borden, ANF |
FROM: Hamid Rastegar/Kris Thorne |
RE: PPSI: Week 17 Report; October 13 through 19, 1997 |
DATE: October 20, 1997 A. INTRODUCTION Construction continued on Segment 2, Angeles National Forest (Milepost (MP) 33 to 57) and Segment 5 (MP 108 to 118). B. SEGMENT 2A CONSTRUCTION PROGRESS This segment within the Angeles Forest Service involves very steep slopes and requires significant time and additional equipment for trenching, stringing, and other pipe laying activities. Segment 2A Environmental Monitor (EM), Stan Harding was on-site. PPSI has 12 craft inspectors, six environmental inspectors, and six Native American monitors inspecting the work of approximately 160 contractor employees. Construction progress from October 13 through 18, 1997 included the following:
C. SEGMENT 3 CONSTRUCTION PROGRESS No construction activity occurred on Segment 3 this week.
D. SEGMENT 5 CONSTRUCTION PROGRESS This segment involves construction in railroad and road right-of-ways through industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 20 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B except where skips between segments remain. Skips will be tied-in when the county contractors are no longer working in the areas. Construction progress from October 13 through 17, 1997 included the following:
E. VARIANCES No variances were approved October 14 through 18, 1997. F. EXTRA WORK SPACE No extra work spaces were approved October 14 through 18, 1997. G. GENERAL PLANS FOR NEXT WEEK Segments 2A and 5C to continue. Segment 4 projected to begin on October 20. Segment 3 projected to resume on October 27. Segment 1 is projected to begin in late October; El Segundo portion of Segment 4 (Watts Junction to Chevron El Segundo Refinery) projected to begin in October. |