DATE: November 24, 1997 A. INTRODUCTION
Construction continued on Segment 1
(Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73);
Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108),
Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108
to 118).
B. SEGMENT 1 CONSTRUCTION PROGRESS
This segment extends southward from the
southern end of the San Joaquin Valley (Emidio), through
the Tejon Pass, to the northern perimeter of the Angeles
National Forest. Construction will occur through
agricultural fields, along roads and across very steep
slopes. Segment 1 Environmental Monitor (EM), Lynn
Stafford has been on-site during construction. PPSI has
five craft inspectors, one environmental inspector, and
one Native American monitor inspecting the work of
approximately 25 contractor employees. Construction
progress from November 17 through 21, 1997 included the
following:
Segment 1 Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
29.65 to 27.91 |
Trench |
33.50 |
Valve site |
32.81 (Copco Road) |
|
|
Segment 1 Comments: No
non-compliance events occurred. Excavation at MP
33.50 is slow because unstable sand needs to be
shored and excavation needs to be at least 14 feet
deep to avoid foreign lines.
Segment 1 Schedule for Next
Week:
Continue pot-holing along Peace
Valley Road north from Gorman School Road.
C. SEGMENT 2A CONSTRUCTION PROGRESS
This segment within the Angeles
National Forest involves very steep slopes and required
significant time and additional equipment for trenching,
stringing, and other pipe-laying activities. All
construction activities to Templin Highway, except
revegetation, were completed by November 9. ANF will
inform PPSI of additional work that needs to be done
after final inspection that will occur at a later date.
Segment 2A Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
Complete to
Templin Highway |
Lower-In |
Complete to
Templin Highway |
Clear & Grade |
Complete to Templin
Highway |
Backfill |
Complete to Templin
Highway |
Stringing |
Complete to Templin
Highway |
Conduit |
Complete to Templin
Highway |
Welding |
Complete to Templin
Highway |
Clean-up |
Complete to Templin
Highway |
Coating |
Complete to Templin
Highway |
Reveg |
No progress on skips |
Segment 2A Comments:
No construction or revegetation
activities occurred.
Segment 2A Schedule for Next
Week:
To be determined after meeting with
ANF representative.
D. SEGMENT 2B CONSTRUCTION PROGRESS
This segment is primarily in open lands
and roadway right-of-ways. Segment 2B EM, Stan Harding,
has been on-site during construction. PPSI has two craft
inspectors, one environmental inspector, and one Native
American monitor inspecting the work of approximately 10
contractor employees. Construction progress November 17
through 21, 1997 included the following:
Segment 2B Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
58.3 - no
progress |
Welding |
56.8 to 56.9 |
Trench |
57.1 - no progress |
Coating |
56.8 to 56.9 |
Lower-In |
56.8 to 56.9 |
Backfill |
56.8+100 feet |
Conduit |
56.8+100 feet |
|
|
Segment 2B Comments:
Nine non-compliance events
occurred, but one was rescinded when it was
determined that the non-compliance was prepared
before sweeping activities had finished for the day.
Non-Compliance Events
for Segment 2B
Mitigation
Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
Castaic Yard Extra Work Space approval
conditions (9/28/97) |
Equipment parked in area approved for
personnel vehicle parking only |
11/17/97
|
Yes
|
Acceptable
|
A.8.1 and .2 - Streets swept if visible
soil on roads |
Soil was not removed from roadway at end
of day, Level 2 |
11/17/97
|
Yes
|
Acceptable
|
A.7.1 and .2 - Trucks may not idle for
more than 2 minutes |
Trucks were left idling for more than 2
minutes and signs were not posted, Level 2 |
11/17/97
|
Yes
|
Acceptable
|
Storm Water Pollution Prevention Plan |
More than 1 load of pipe stored on ROW
and spoil stored on street |
11/17/97
|
No* - see below
|
Un-acceptable* -
see below
|
T.5.1 - Transportation Management Plan
developed and followed |
Steel plates not tack-welded together,
cold mix not used along plate edges, warning
signs not in use, and barricades not placed
around excavations, Level 1 |
11/17/97
|
Yes
|
Acceptable
|
V.1.3 - Excavated materials may not be
stored within 50 yards of business |
Excavated materials stored within 50
yards of business, Level 2 |
11/17/97
|
Yes
|
Acceptable
|
A.1.2 - Water spoil piles twice daily |
Spoil piles were not watered, Level 2 |
11/17/97
|
Yes
|
Acceptable
|
Storm Water Pollution Prevention Plan (2nd
notice) |
More than 1 load of pipe stored on ROW |
11/18/97
|
*Yes
|
*Acceptable
11/19/97
|
A.8.1 and .2 - Streets swept if visible
soil on roads |
Soil was not removed from roadway at end
of day, Level 2 |
11/19/97
|
Yes
|
RESCINDED
11/20/97
|
Segment 2B Schedule for Next
Week:
Continue laying pipe along Castaic
Road and begin work on Lake Hughes Road.
E. SEGMENT 3 CONSTRUCTION PROGRESS
This segment is mostly within MTA rail
right-of-way from Sylmar to Alameda Street in Los
Angeles. Segment 3 EM, Brooke Langle, has been on-site
during construction. PPSI has 4 craft inspectors, one
environmental inspector, one contaminated soils
inspector, and one Native American monitor inspecting the
work of approximately 15 contractor employees.
Construction progress from November 17 through 22, 1997
included the following:
Segment 3 Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
82.29 - no
progress |
Lower-In |
78.75 to 79.30 |
Trench |
78.69 to 79.30 |
NDT |
78.75 to 79.30 |
Stringing |
78.59 to 79.30 |
Coating |
78.75 to 79.30 |
Welding |
78.75 to 79.30 |
Backfill |
78.51 to 78.28 |
Segment 3 Comments:
One non-compliance event occurred.
Crews worked Saturday to backfill trench in order to
reduce the amount of open trench.
Non-Compliance Event
for Segment 3
Mitigation Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
T.1.1 - Street closures be avoided
between 3:30 p.m. and 6:30 p.m. |
Street closure in place past 3:30 p.m.,
Level 1 |
11/17/97
|
Yes
|
Acceptable
|
Segment 3 Schedule for Next
Week:
Conduit installation scheduled to
begin.
F. SEGMENT 4A CONSTRUCTION PROGRESS
This segment involves nighttime
construction (8:00 p.m. to 5:30 a.m.) in railroad and
roadway right-of-ways through mostly industrial areas
from downtown Los Angeles to Compton. Segment 4A EM,
Christopher Meyer, has been on-site during construction.
PPSI has one craft inspector, one environmental
inspector, and one contamination inspector inspecting the
work of approximately 10 contractor employees during
construction. Construction progress from November 17
through 21, 1997 included the following:
Segment 4A Activities:
Activity Milepost
(approximate)
Track removal 100.54 to
100.78
Pot-hole 99.50
Segment 4A Comments:
No non-compliance events occurred.
The first phase of track removal was completed. Los
Angeles City Inspector was on-site twice during the
week to observe traffic controls and progress of
project. A man was chased through the project by a
security officer with his gun drawn. No project
personnel were involved or injured.
Segment 4A Schedule for Next
Week:
Pot-holing will continue.
G. SEGMENT 4B CONSTRUCTION PROGRESS
This segment involves construction in
railroad and roadway right-of-ways through mostly
industrial areas from Watts Junction to El Segundo
Refinery area. Segment 4B EM, Neda Fioozat, has been
on-site during construction. PPSI has four craft
inspectors, one part-time environmental inspector, one
Native American monitor, and one contamination inspector
inspecting the work of approximately 15 contractor
employees. Construction progress from November 17 through
21, 1997 included the following:
Segment 4B Activities
Activity |
El Segundo
Milepost (approx) |
Activity |
El Segundo
Milepost (approx) |
Pot-hole |
no progress |
Boring |
10.34 to 10.44 |
Bore pit |
8.65 (Aviation Blvd) -
continued |
NDT |
10.34 to 10.44 |
Welding |
10.34 to 10.44 |
Coating |
10.34 to 10.44 |
Segment 4B Comments: No
non-compliance events occurred. Work continues in
railroad right-of-way. The environmental inspector
for PPSI divides her time between Segments 4B and 5.
Bore pits at Aviation Boulevard will be 27-feet deep.
Segment 4B Schedule for Next
Week:
Continue bore pit excavations and
installing pipe at bores along right-of-way.
H. SEGMENT 5 CONSTRUCTION PROGRESS
This segment involves construction in
railroad and roadway right-of-ways through mostly
industrial areas from Compton to the Long Beach Harbor.
Segment 5 EM, Pete Messick, has been on-site during
construction. PPSI has four craft inspectors, one
part-time environmental inspector, one Native American
monitor, and one contamination inspector inspecting the
work of approximately 15 contractor employees during
construction of Segment 5C. Construction is complete on
Segments 5A and 5B except where skips between segments
remain. Skips will be tied-in when the county contractors
are no longer working in the areas. Construction progress
from November 17 through 22, 1997 included the following:
Segment 5C Activities:
Activity
|
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
109.28 no
progress |
Welding |
108.07 to
108.54 |
Asphalt Grind |
109.43 no progress |
NDT |
108.07 to 108.54 |
Trench |
108.40 to 108.88 |
Coating |
107.95 to 108.54 |
Lower-In |
108.40 to 108.88 |
Conduit |
107.95 to 108.49 |
Segment 5 Comments: One
non-compliance event occurred. The environmental
inspector for PPSI divides her time between Segments
4B and 5. Crews worked Saturday, November 22 until
11:30 a.m. to compact and slurry trench adjacent to
Union Pacific Railroad track (at the request of Union
Pacific Railroad).
Non-Compliance Event
for Segment 5
Mitigation Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
T.5.1 - Implement Traffic Management
Plan |
Traffic restricted to one lane and no
flaggers were present, Level
3 |
11/18/97
|
Yes
|
Acceptable
|
Segment 5 Schedule for Next
Week:
Construction to continue along E.
Alameda Street in the City of Lynwood.
I. VARIANCES
No variances were approved November 17
through 21, 1997.
J. EXTRA WORK SPACE
No extra work spaces/equipment storage
areas were approved November 17 through 21, 1997.
K. GENERAL PLANS FOR NEXT WEEK
Segments 1, 2B, 3, 4A, 4B and 5C will
not work November 27 and 28, 1997 due to the Thanksgiving
holiday. Work will resume on all segments on December 1,
1997.
|