PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATION
MONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (November 17 through 23, 1997)

TO: Andrew Barnsdale, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: PPSI: Week 22 Report; November 17 through 23, 1997
DATE: November 24, 1997

A. INTRODUCTION

Construction continued on Segment 1 (Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73); Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108), Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108 to 118).

B. SEGMENT 1 CONSTRUCTION PROGRESS

This segment extends southward from the southern end of the San Joaquin Valley (Emidio), through the Tejon Pass, to the northern perimeter of the Angeles National Forest. Construction will occur through agricultural fields, along roads and across very steep slopes. Segment 1 Environmental Monitor (EM), Lynn Stafford has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 25 contractor employees. Construction progress from November 17 through 21, 1997 included the following:

Segment 1 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 29.65 to 27.91 • Trench 33.50
• Valve site 32.81 (Copco Road)    

Segment 1 Comments: No non-compliance events occurred. Excavation at MP 33.50 is slow because unstable sand needs to be shored and excavation needs to be at least 14 feet deep to avoid foreign lines.

Segment 1 Schedule for Next Week:

Continue pot-holing along Peace Valley Road north from Gorman School Road.

C. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles National Forest involves very steep slopes and required significant time and additional equipment for trenching, stringing, and other pipe-laying activities. All construction activities to Templin Highway, except revegetation, were completed by November 9. ANF will inform PPSI of additional work that needs to be done after final inspection that will occur at a later date.

Segment 2A Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole Complete to Templin Highway • Lower-In Complete to Templin Highway
• Clear & Grade Complete to Templin Highway • Backfill Complete to Templin Highway
• Stringing Complete to Templin Highway • Conduit Complete to Templin Highway
• Welding Complete to Templin Highway • Clean-up Complete to Templin Highway
• Coating Complete to Templin Highway • Reveg No progress on skips

Segment 2A Comments:

No construction or revegetation activities occurred.

Segment 2A Schedule for Next Week:

To be determined after meeting with ANF representative.

D. SEGMENT 2B CONSTRUCTION PROGRESS

This segment is primarily in open lands and roadway right-of-ways. Segment 2B EM, Stan Harding, has been on-site during construction. PPSI has two craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 10 contractor employees. Construction progress November 17 through 21, 1997 included the following:

Segment 2B Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 58.3 - no progress • Welding 56.8 to 56.9
• Trench 57.1 - no progress • Coating 56.8 to 56.9
• Lower-In 56.8 to 56.9 • Backfill 56.8+100 feet
• Conduit 56.8+100 feet    

Segment 2B Comments:

Nine non-compliance events occurred, but one was rescinded when it was determined that the non-compliance was prepared before sweeping activities had finished for the day.

Non-Compliance Events for Segment 2B

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

Castaic Yard Extra Work Space approval conditions (9/28/97) Equipment parked in area approved for personnel vehicle parking only

11/17/97

Yes

Acceptable

A.8.1 and .2 - Streets swept if visible soil on roads Soil was not removed from roadway at end of day, Level 2

11/17/97

Yes

Acceptable

A.7.1 and .2 - Trucks may not idle for more than 2 minutes Trucks were left idling for more than 2 minutes and signs were not posted, Level 2

11/17/97

Yes

Acceptable

Storm Water Pollution Prevention Plan More than 1 load of pipe stored on ROW and spoil stored on street

11/17/97

No* - see below

Un-acceptable* - see below

T.5.1 - Transportation Management Plan developed and followed Steel plates not tack-welded together, cold mix not used along plate edges, warning signs not in use, and barricades not placed around excavations, Level 1

11/17/97

Yes

Acceptable

V.1.3 - Excavated materials may not be stored within 50 yards of business Excavated materials stored within 50 yards of business, Level 2

11/17/97

Yes

Acceptable

A.1.2 - Water spoil piles twice daily Spoil piles were not watered, Level 2

11/17/97

Yes

Acceptable

Storm Water Pollution Prevention Plan (2nd notice) More than 1 load of pipe stored on ROW

11/18/97

*Yes

*Acceptable 11/19/97

A.8.1 and .2 - Streets swept if visible soil on roads Soil was not removed from roadway at end of day, Level 2

11/19/97

Yes

RESCINDED 11/20/97

Segment 2B Schedule for Next Week:

Continue laying pipe along Castaic Road and begin work on Lake Hughes Road.

E. SEGMENT 3 CONSTRUCTION PROGRESS

This segment is mostly within MTA rail right-of-way from Sylmar to Alameda Street in Los Angeles. Segment 3 EM, Brooke Langle, has been on-site during construction. PPSI has 4 craft inspectors, one environmental inspector, one contaminated soils inspector, and one Native American monitor inspecting the work of approximately 15 contractor employees. Construction progress from November 17 through 22, 1997 included the following:

Segment 3 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 82.29 - no progress • Lower-In 78.75 to 79.30
• Trench 78.69 to 79.30 • NDT 78.75 to 79.30
• Stringing 78.59 to 79.30 • Coating 78.75 to 79.30
• Welding 78.75 to 79.30 • Backfill 78.51 to 78.28

Segment 3 Comments:

One non-compliance event occurred. Crews worked Saturday to backfill trench in order to reduce the amount of open trench.

Non-Compliance Event for Segment 3

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

T.1.1 - Street closures be avoided between 3:30 p.m. and 6:30 p.m. Street closure in place past 3:30 p.m., Level 1

11/17/97

Yes

Acceptable

Segment 3 Schedule for Next Week:

Conduit installation scheduled to begin.

F. SEGMENT 4A CONSTRUCTION PROGRESS

This segment involves nighttime construction (8:00 p.m. to 5:30 a.m.) in railroad and roadway right-of-ways through mostly industrial areas from downtown Los Angeles to Compton. Segment 4A EM, Christopher Meyer, has been on-site during construction. PPSI has one craft inspector, one environmental inspector, and one contamination inspector inspecting the work of approximately 10 contractor employees during construction. Construction progress from November 17 through 21, 1997 included the following:

Segment 4A Activities:

Activity Milepost (approximate)

• Track removal 100.54 to 100.78

• Pot-hole 99.50

Segment 4A Comments:

No non-compliance events occurred. The first phase of track removal was completed. Los Angeles City Inspector was on-site twice during the week to observe traffic controls and progress of project. A man was chased through the project by a security officer with his gun drawn. No project personnel were involved or injured.

Segment 4A Schedule for Next Week:

Pot-holing will continue.

G. SEGMENT 4B CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Watts Junction to El Segundo Refinery area. Segment 4B EM, Neda Fioozat, has been on-site during construction. PPSI has four craft inspectors, one part-time environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 15 contractor employees. Construction progress from November 17 through 21, 1997 included the following:

Segment 4B Activities

Activity El Segundo Milepost (approx) Activity El Segundo Milepost (approx)
• Pot-hole no progress • Boring 10.34 to 10.44
• Bore pit 8.65 (Aviation Blvd) - continued • NDT 10.34 to 10.44
• Welding 10.34 to 10.44 • Coating 10.34 to 10.44

Segment 4B Comments: No non-compliance events occurred. Work continues in railroad right-of-way. The environmental inspector for PPSI divides her time between Segments 4B and 5. Bore pits at Aviation Boulevard will be 27-feet deep.

Segment 4B Schedule for Next Week:

Continue bore pit excavations and installing pipe at bores along right-of-way.

H. SEGMENT 5 CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during construction. PPSI has four craft inspectors, one part-time environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 15 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B except where skips between segments remain. Skips will be tied-in when the county contractors are no longer working in the areas. Construction progress from November 17 through 22, 1997 included the following:

Segment 5C Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 109.28 no progress • Welding 108.07 to 108.54
• Asphalt Grind 109.43 no progress • NDT 108.07 to 108.54
• Trench 108.40 to 108.88 • Coating 107.95 to 108.54
• Lower-In 108.40 to 108.88 • Conduit 107.95 to 108.49

Segment 5 Comments: One non-compliance event occurred. The environmental inspector for PPSI divides her time between Segments 4B and 5. Crews worked Saturday, November 22 until 11:30 a.m. to compact and slurry trench adjacent to Union Pacific Railroad track (at the request of Union Pacific Railroad).

Non-Compliance Event for Segment 5

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

T.5.1 - Implement Traffic Management Plan Traffic restricted to one lane and no flaggers were present, Level 3

11/18/97

Yes

Acceptable

Segment 5 Schedule for Next Week:

Construction to continue along E. Alameda Street in the City of Lynwood.

I. VARIANCES

No variances were approved November 17 through 21, 1997.

J. EXTRA WORK SPACE

No extra work spaces/equipment storage areas were approved November 17 through 21, 1997.

K. GENERAL PLANS FOR NEXT WEEK

Segments 1, 2B, 3, 4A, 4B and 5C will not work November 27 and 28, 1997 due to the Thanksgiving holiday. Work will resume on all segments on December 1, 1997.