PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATION
MONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (November 24 through 30, 1997)

TO: Andrew Barnsdale, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: PPSI: Week 23 Report; November 24 through 30, 1997
DATE: December 2, 1997

A. INTRODUCTION

Construction was completed, but restoration activities continued on Segment 2A, Angeles National Forest (Milepost (MP) 33 to 56); construction began on Segment 1 (MP 0 TO 33), Segment 2B (MP 56 to 73); and construction continued on Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108), Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108 to 118).

B. SEGMENT 1 CONSTRUCTION PROGRESS

This segment extends southward from the southern end of the San Joaquin Valley (Emidio), through the Tejon Pass, to the northern perimeter of the Angeles National Forest. Construction will occur through agricultural fields, along roads and across very steep slopes. Segment 1 Environmental Monitor (EM), Lynn Stafford has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 25 contractor employees. Construction progress from November 24 through 26, 1997 included the following:

Segment 1 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 27.91 to 25.31 • Trench 33.50 to 33.28
• Valve site 32.81 (Copco Road) • Bending 33.50 to 33.00

Segment 1 Comments: No non-compliance events occurred. All construction activity, except storm preparation, was shutdown on November 26. Crews did not work Thanksgiving holiday, November 27 and 28.

Segment 1 Schedule for Next Week:

Continue pot-holing in Kern County. Begin pipelaying activities.

C. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles National Forest involved very steep slopes and required significant time and additional equipment for trenching, stringing, and other pipe-laying activities. All construction activities to Templin Highway, except revegetation, were completed by November 9. ANF will inform PPSI of additional work that needs to be done after final inspection that will occur at a later date.

Segment 2A Comments:

No construction or revegetation activities occurred.

Segment 2A Schedule for Next Week:

To be determined after meeting with ANF representative.

D. SEGMENT 2B CONSTRUCTION PROGRESS

This segment is primarily in open lands and roadway right-of-ways from Castaic to Sylmar. Segment 2B EM, Stan Harding, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 45 contractor employees. Construction progress November 24 through 26, 1997 included the following:

Segment 2B Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 58.3 - no progress • Welding 56.9 to 57.3
• Trench 57.1 to 57.4 • Coating 56.8 to 56.9
• Lower-In 56.9 to 57.3 • Backfill 56.8 to 57.0
• Conduit 56.8 to 57.0 • Paving 56.3 to 56.9

Segment 2B Comments:

One non-compliance event occurred. All construction activity, except storm preparation, was shutdown on November 26. Crews did not work Thanksgiving holiday, November 27 and 28.

Non-Compliance Event for Segment 2B

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

T.5.1 - Transportation Management Plan developed and followed Construction signs not in place, no arrow board, no flagger at south end of construction, equipment parked off ROW, flagger using hand signals, and north- and south-bound traffic directed to use the same traffic lane simultaneously. Level 1

11/24/97

Yes

Acceptable

Segment 2B Schedule for Next Week:

Begin work on Lake Hughes Road.

E. SEGMENT 3 CONSTRUCTION PROGRESS

This segment is mostly within MTA rail right-of-way from Sylmar to Alameda Street in Los Angeles. Segment 3 EM, Chris Fazzari, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one contaminated soils inspector, and one Native American monitor inspecting the work of approximately 30 contractor employees. Construction progress from November 24 through 26, 1997 included the following:

Segment 3 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 82.29 - no progress • Lower-In 79.30 to 79.44
• Trench 79.30 to 79.54 • NDT 79.30 to 79.44
• Stringing 79.30 to 79.44 • Coating 79.30 to 79.44
• Welding 79.30 to 79.44 • Backfill 78.28 to 78.80

Segment 3 Comments:

No non-compliance events occurred. Crews did not work Thanksgiving holiday, November 27 and 28.

Segment 3 Schedule for Next Week:

Conduit installation scheduled to begin.

F. SEGMENT 4A CONSTRUCTION PROGRESS

This segment involves nighttime construction (8:00 p.m. to 5:30 a.m.) in railroad and roadway right-of-ways through mostly industrial areas from downtown Los Angeles to Compton. Segment 4A EM, Christopher Meyer, has been on-site during construction. PPSI has one craft inspector, one environmental inspector, and one contamination inspector inspecting the work of approximately 10 contractor employees during construction. Construction progress from November 24 through 26, 1997 included the following:

Segment 4A Activities:

Activity Milepost (approximate)
• Track removal 100.78 to 101.32
• Pot-hole 99.50 to 100.10

Segment 4A Comments:

No non-compliance events occurred. The first phase of track removal was completed. Los Angeles City Inspector was on-site twice during the week to observe traffic controls and progress of project. Construction activity was shutdown on November 26 because of rain. Crews did not work Thanksgiving holiday, November 27 and 28.

Segment 4A Schedule for Next Week:

Pot-holing and track removal will continue.

G. SEGMENT 4B CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Watts Junction to El Segundo Refinery area. Segment 4B EM, Neda Fioozat, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 25 contractor employees. Construction progress from November 24 through 26, 1997 included the following:

Segment 4B Activities

Activity El Segundo Milepost (approx) Activity El Segundo Milepost (approx)
• Pot-hole no progress • Boring 10.44 to 10.55
• Bore pit 8.65 (Aviation Blvd) - continued • NDT 10.44 to 10.55
• Welding 10.44 to 10.55 • Coating 10.44 to 10.5

Segment 4B Comments: No non-compliance events occurred. Work continues in railroad right-of-way. Construction activity was shutdown on November 26 because of rain. Crews did not work Thanksgiving holiday, November 27 and 28.

Segment 4B Schedule for Next Week:

Continue bore pit excavations and installing pipe at bores along right-of-way.

H. SEGMENT 5 CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 25 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B. Construction progress from November 24 through 26, 1997 included the following:

Segment 5C Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 109.28 to 110.10 • Welding 108.54 to 109.02
• Trench 108.88 to 109.29 • NDT 108.54 to 109.02
• Lower-In 108.88 to 109.20 • Coating 108.54 to 109.02
• Backfill 108.40 to 108.79 • Conduit 108.49 to 108.91

Segment 5 Comments: No non-compliance events occurred. Construction activities, except backfilling, were shutdown on November 26 because of rain. Crews did not work Thanksgiving holiday, November 27 and 28.

Segment 5 Schedule for Next Week:

Construction to continue along E. Alameda Street in the cities of Lynwood and Compton

I. VARIANCES

No variances were approved November 24 through 30, 1997.

J. EXTRA WORK SPACE

No extra work spaces/equipment storage areas were approved November 24 through 30, 1997.

K. GENERAL PLANS FOR NEXT WEEK

Construction activities on Segments 1, 2B, 3, 4A, 4B and 5C will resume on December 1, 1997.