DATE: December 16, 1997 A. INTRODUCTION
Construction continued on Segment 1
(Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73);
Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108),
Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108
to 118).
B. SEGMENT 1 CONSTRUCTION PROGRESS
This segment extends southward from the
southern end of the San Joaquin Valley (Emidio), through
the Tejon Pass, to the northern perimeter of the Angeles
National Forest. Construction will occur through
agricultural fields, along roads and across very steep
slopes. Segment 1 Environmental Monitor (EM), Lynn
Stafford has been on-site during construction. PPSI has
five craft inspectors, one environmental inspector, and
one Native American monitor inspecting the work of
approximately 25 contractor employees. Construction
progress from December 8 through 12, 1997 included the
following:
Segment 1 Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
Complete to
Frazier Park |
Non-DestructiveTesting (NDT) |
32.80 to 32.81 |
Trench |
32.64 to 32.58 |
Coating |
32.80 to 32.81 |
Bend |
32.80 to 32.64 |
Conduit |
32.80 to 32.81 |
Lower-In |
32.80 to 32.81 |
Backfill |
33.03 to 32.97 |
Bore 32.71 |
(continued) |
|
|
Segment 1 Comments: No
non-compliance events occurred. Copco Road restricted
to one lane during work hours with appropriate
traffic control measures in place. Pavement failure
along the 14-foot deep trench at EMP 33.35 was dug
out and shored on December 8 and backfilled by
December 10. Los Angeles County was notified and
inspected site.
Segment 1 Schedule for Next
Week:
Continue pipelaying activities
along Quail Lake Road (EMP 32.64). Finish bore at
Copco Road (EMP 32.71).
C. SEGMENT 2A CONSTRUCTION PROGRESS
This segment within the Angeles
National Forest involved very steep slopes and required
significant time and additional equipment for trenching,
stringing, and other pipe-laying activities. All
construction activities to Templin Highway, except
revegetation, were completed by November 9. ANF will
inform PPSI of additional work that needs to be done
after final inspection that will occur at a later date.
Segment 2A Comments:
No construction or revegetation
activities occurred. On Saturday, December 6, erosion
problems (due to a major storm and associated
run-off) were inspected and photographed.
Segment 2A Schedule for Next
Week:
PPSI to inspect erosion problems by
helicopter and then arrange to meet with ANF.
Requirements of final inspection to be determined
after meeting with ANF representative.
D. SEGMENT 2B CONSTRUCTION PROGRESS
This segment is primarily in open lands
and roadway right-of-ways from Castaic to Sylmar. Segment
2B EMs, Stan Harding and Chris Fazzari, have been on-site
during construction. PPSI has five craft inspectors, one
environmental inspector, and one Native American monitor
inspecting the work of approximately 45 contractor
employees. Construction progress December 8 through 12,
1997 included the following:
Segment 2B Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
58.3 - no
progress |
Welding
|
57.5 to 57.8 |
Trench |
57.7 to 58.0 |
Coating |
57.5 to 57.8 |
Lower-In |
57.5 to 57.8 |
Backfill |
57.5 to 57.8 |
Conduit |
57.5 to 57.8 |
Concrete |
57.4 to 57.7 |
Segment 2B Comments:
No non-compliance events occurred.
Crews working in 2300-foot long work zone. Traffic
control has been monitored daily by Los Angeles
County inspector, Scott Thompson. Erosion control
measures were installed in preparation for predicted
storm.
Segment 2B Schedule for Next
Week:
Finish construction on Lake Hughes
Road and begin on The Old Road.
E. SEGMENT 3 CONSTRUCTION PROGRESS
This segment is mostly within MTA rail
right-of-way from Sylmar to Alameda Street in Los
Angeles. Segment 3 EM, Brooke Langle, has been on-site
during construction. PPSI has four craft inspectors, one
environmental inspector, one contaminated soils
inspector, and one Native American monitor inspecting the
work of approximately 30 contractor employees.
Construction progress from December 8 through 12, 1997
included the following:
Segment 3 Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Shrub
removal |
82.30 to 83.71 |
Coating
|
79.84 to 80.07 |
Trench |
79.97 to 80.26 |
Conduit |
79.42 to 79.90 |
Lower-In |
79.89 to 80.23 |
Backfill |
79.37 to 79.90 |
Welding |
79.84 to 80.07 |
Clean-up |
79.22 to 79.30 |
NDT |
79.84 to 80.07 |
|
|
Segment 3 Comments:
No non-compliance events occurred.
High winds (average 20 mph, gusts 45 mph) recorded on
December 10 and 11, but no cessation of work was
required; however, there was increased implementation
of dust abatement measures. Bores continued at Paxton
Street (EMP 79.30) and Osborne Street (EMP 80.96)
Segment 3 Schedule for Next
Week:
Complete bore operations at Paxton
and Osborne Streets and begin bore at Branford Street
(EMP 81.47).
F. SEGMENT 4A CONSTRUCTION PROGRESS
This segment involves nighttime
construction (8:00 p.m. to 5:30 a.m.) in railroad and
roadway right-of-ways through mostly industrial areas
from downtown Los Angeles to Compton. Segment 4A EM,
Christopher Meyer, has been on-site during construction.
PPSI has two craft inspectors, one environmental
inspector, and one contamination inspector inspecting the
work of approximately 25 contractor employees during
construction. Construction progress from December 8
through 12, 1997 included the following:
Segment 4A Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Track
removal |
101.37
to101.53 |
Trench |
99.45 to 99.60
(skips) |
Segment 4A Comments:
Two non-compliance events occurred.
Traffic control conduit was damaged on December 11,
but the cables were not impacted and traffic lights
continued to operate. Notices were made and city
personnel enacted repairs to conduit. Although there
are sufficient signs and delineators, motorists
continue to purposely drive through and around
barriers and into the work area to avoid waiting.
This creates a hazard for both the motorist and
project personnel. Project personnel watch for errant
motorists.
Non-Compliance Events
for Segment 4A
Mitigation Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
T.5.1
- Transportation Management Plan developed and
followed |
Crews worked after removal of traffic
controls and past 5:30 a.m. restriction, Level 2
|
12/8/97
|
Yes
|
Acceptable
|
T.5.1
- Transportation Management Plan developed and
followed |
Crew worked until 6:45 a.m., past 5:30
a.m. restriction, Level 2
|
12/9/97
|
Yes
|
Acceptable
|
Segment 4A Schedule for Next
Week:
Continue using three crews: one for
track removal, one for saw-cutting asphalt, and one
for trenching.
G. SEGMENT 4B CONSTRUCTION PROGRESS
This segment involves construction in
railroad and roadway right-of-ways through mostly
industrial areas from Watts Junction to El Segundo
Refinery area. Segment 4B EM, Neda Fioozat, has been
on-site during construction. PPSI has four craft
inspectors, one environmental inspector, one Native
American monitor, and one contamination inspector
inspecting the work of approximately 25 contractor
employees. Construction progress from December 8 through
12, 1997 included the following:
Segment 4B Activities
Activity |
El Segundo
Milepost (approx) |
Activity |
El Segundo
Milepost (approx) |
Pot-hole |
7.81 to 7.97 |
Bore
pit |
8.84
(Eucalyptus Ave) |
Bore pit |
9.61 (Aviation Blvd) -
continued |
NDT |
10.58 - no progress |
Bore pit |
8.46 (Inglewood Av) -
continued |
Coating |
10.58 - no progress |
Segment 4B Comments: No
non-compliance events occurred. Progress at bore
sites was slow because of equipment breakdowns and
repair time.
Segment 4B Schedule for Next
Week:
Continue bore pit excavations and
pot-holing along right-of-way.
H. SEGMENT 5 CONSTRUCTION PROGRESS
This segment involves construction in
railroad and roadway right-of-ways through mostly
industrial areas from Compton to the Long Beach Harbor.
Segment 5 EM, Pete Messick, has been on-site during
construction. PPSI has five craft inspectors, one
environmental inspector, one Native American monitor, and
one contamination inspector inspecting the work of
approximately 30 contractor employees during construction
of Segment 5C. Construction is complete on Segments 5A
and 5B. Construction progress from December 8 through 13,
1997 included the following:
Segment 5C Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
110.10 to
111.74 |
Welding |
109.40 to
110.41 |
Trench |
109.93 to 111.47 |
NDT |
109.40 to 110.41 |
Lower-In |
109.40 to 110.17 |
Coating |
109.40 to 110.41 |
Backfill |
109.39 to 110.28 |
Conduit |
109.46 to 110.40 |
Clean-up |
108.67 to 109.42 |
|
|
Non-Compliance Event
for Segment 5
Mitigation Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
T.5.1
- Transportation Management Plan developed and
followed |
Warning signs and flaggers not in place,
Level 2
|
12/13/97
|
Yes
|
Acceptable
|
Segment 5 Comments: One
non-compliance event occurred. Progress is slow
because of numerous subsurface utilities. Motorists
obeying traffic signs and flaggers.
Segment 5 Schedule for Next
Week:
Construction to continue.
Contractor to provide traffic control re-training to
project personnel in the coming week.
I. VARIANCES
One variance was approved by CPUC or
ANF December 8 through 12, 1997.
Variance #
|
Description
|
Segment(s)
Variance Applies
|
Agency Decision
|
35
|
Allow
for refueling within 0.25 miles of streams at
directional drilling locations (Gorman Slide,
Castaic Creek, Santa Clara River, LA Aqueduct) |
1 and 2
|
Approved
|
J. EXTRA WORK SPACE
The following extra work
spaces/equipment storage areas were approved by CPUC or
ANF December 8 through 12, 1997.
Request #
|
Description
|
Segment(s)
Variance Applies
|
Agency Decision
|
20
|
Additional
work space/equipment storage on Alameda St.,
between 5th St. & Palmetto St, City of Los
Angeles |
4
|
Approved
|
21
|
Extra
work space for Castaic Creek directional drill,
Los Angeles County |
2B
|
Approved
|
K. GENERAL PLANS FOR
NEXT WEEK
Construction on Segments
1, 2B, 3, 4A, 4B and 5C will continue and erosion control
measures will be maintained.
|