DATE: December 23, 1997 A. INTRODUCTION
Construction continued on Segment 1
(Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73);
Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108),
Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108
to 118).
B. SEGMENT 1 CONSTRUCTION PROGRESS
This segment extends southward from the
southern end of the San Joaquin Valley (Emidio), through
the Tejon Pass, to the northern perimeter of the Angeles
National Forest. Construction will occur through
agricultural fields, along roads and across very steep
slopes. Segment 1 Environmental Monitor (EM), Lynn
Stafford has been on-site during construction. PPSI has
five craft inspectors, one environmental inspector, and
one Native American monitor inspecting the work of
approximately 25 contractor employees. Construction
progress from December 15 through 19, 1997 included the
following:
Segment 1 Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Paving |
33.33 to 33.01
|
Non-Destructive Testing (NDT) |
32.81 to 31.89 |
Trench |
32.58 to 32.20 |
Coating |
32.81 to 31.89 |
Bend |
32.64 to 31.61 |
Conduit |
32.81 to 32.44 |
Lower-In |
32.81 to 31.61 |
Backfill |
32.97 to 32.44 |
Segment 1 Comments: No
non-compliance events occurred. Copco Road restricted
to one lane during work hours with appropriate
traffic control measures in place. Rain on December
18 limited construction activities. California
Highway Patrol officers have inspected the
construction zone and have commented on the good
traffic control.
Segment 1 Schedule for Next
Week:
Begin construction activities along
Peace Valley Road (EMP 32.29).
C. SEGMENT 2A CONSTRUCTION PROGRESS
This segment within the Angeles
National Forest involved very steep slopes and required
significant time and additional equipment for trenching,
stringing, and other pipe-laying activities. All
construction activities to Templin Highway, except
revegetation, were completed by November 9. ANF will
inform PPSI of additional work that needs to be done
after final inspection that will occur at a later date.
Segment 2A Comments:
No construction or revegetation
activities occurred. On December 16, PPSI inspected
and videotaped erosion problems (due to a major storm
and associated run-off) from a helicopter.
Segment 2A Schedule for Next
Week:
PPSI to arrange to meet with ANF
after the holidays. Requirements of final inspection
to be determined after meeting with ANF
representative.
D. SEGMENT 2B CONSTRUCTION PROGRESS
This segment is primarily in open lands
and roadway right-of-ways from Castaic to Sylmar. Segment
2B EM, Chris Fazzari, has been on-site during
construction. PPSI has five craft inspectors, one
environmental inspector, and one Native American monitor
inspecting the work of approximately 45 contractor
employees. Construction progress December 15 through 19,
1997 included the following:
Segment 2B Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
58.3 to 58.42 |
Welding
|
57.8 to 58.15 |
Trench |
58.0 to 58.40 |
Coating |
57.8 to 58.15 |
Lower-In |
57.8 to 58.24 |
Backfill |
57.8 to 58.13 |
Conduit |
57.8 to 58.15 |
Concrete |
57.7 to 57.86 |
Segment 2B Comments:
One non-compliance event occurred.
Traffic control has been monitored daily by Los
Angeles County inspector, Scott Thompson. A pilot car
was used to guide traffic through the construction
zone on The Old Road. A 96" storm drain was
located near Parker Road (EMP 58.51). It isnt
currently known if it will be required to bore under
the drain. Rain on December 18 slowed construction
activities.
Non-Compliance Events
for Segment 2B
Mitigation Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
A.2.1 - Limit construction activities
off the ROW |
Crew cleared area
and put spoil pile outside ROW, Level 3
|
12/16/97
|
Yes
|
Acceptable
|
Segment 2B Schedule for Next
Week:
Continue construction on The Old
Road.
E. SEGMENT 3 CONSTRUCTION PROGRESS
This segment is mostly within MTA rail
right-of-way from Sylmar to Alameda Street in Los
Angeles. Segment 3 EM, Brooke Langle, has been on-site
during construction. PPSI has four craft inspectors, one
environmental inspector, one contaminated soils
inspector, and one Native American monitor inspecting the
work of approximately 30 contractor employees.
Construction progress from December 15 through 20, 1997
included the following:
Segment 3 Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Shrub
removal |
82.30 to 83.71
(complete) |
Coating
|
80.07 to 80.47 |
Trench |
80.07 to 80.87 |
Conduit |
79.90 to 80.43 |
Lower-In |
80.23 to 80.64 |
Backfill |
79.90 to 80.43 |
Welding |
80.07 to 80.58 |
Valve |
81.48 |
NDT |
80.07 to 80.47 |
|
|
Segment 3 Comments:
No non-compliance events occurred.
Strong winds (10 to 15 mph) continued to blow all
week. Bore completed at Osborne Street (EMP 80.56)
and continued at Branford Street (EMP 81.47). Rain on
December 18 slowed construction activities.
Segment 3 Schedule for Next
Week:
Complete bore operations at
Branford Street (EMP 81.47).
F. SEGMENT 4A CONSTRUCTION PROGRESS
This segment involves nighttime
construction (8:00 p.m. to 5:30 a.m.) in railroad and
roadway right-of-ways through mostly industrial areas
from downtown Los Angeles to Compton. Segment 4A EM,
Christopher Meyer, has been on-site during construction.
PPSI has two craft inspectors, one environmental
inspector, and one contamination inspector inspecting the
work of approximately 25 contractor employees during
construction. Construction progress from December 15
through 19, 1997 included the following:
Segment 4A Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
99.51 to
100.01 |
Welding |
99.50 to 99.54 |
Trench |
99.60 to 99.82 |
Coating |
99.50 to 99.54 |
Lower-In |
99.50 to 99.60 |
Track removal |
101.53 (no progress) |
Segment 4A Comments:
Two non-compliance events occurred.
On December 16 the sidewalls of a bell hole
collapsed. Steel plates were used to shore the trench
and the cavities were filled with soil. No one was
injured.
Non-Compliance Events
for Segment 4A
Mitigation Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
SS.2.2 - Use hand tools within 24"
of underground structures. |
Crews failed to excavate by hand and
broke a 10" sewer line, Level 3 |
12/15/97
|
Yes
|
Acceptable
|
T.1.2 - Lane closures avoided and
Transportation Management Plan developed and
followed |
Lanes closed past
6:00 a.m. restriction, Level 3
|
12/15/97
|
Yes
|
Acceptable
|
Segment 4A Schedule for Next
Week:
Continue having three work areas:
one for track removal, one for saw-cutting asphalt,
and one for trenching and pipelaying.
G. SEGMENT 4B CONSTRUCTION PROGRESS
This segment involves construction in
railroad and roadway right-of-ways through mostly
industrial areas from Watts Junction to El Segundo
Refinery area. Segment 4B EM, Neda Fioozat, has been
on-site during construction. PPSI has four craft
inspectors, one environmental inspector, one Native
American monitor, and one contamination inspector
inspecting the work of approximately 25 contractor
employees. Construction progress from December 15 through
19, 1997 included the following:
Segment 4B Activities
Activity |
El Segundo
Milepost (approx) |
Activity |
El Segundo
Milepost (approx) |
Pot-hole |
7.97 - no
progress |
Bore
pit |
8.84
(Eucalyptus Ave) |
Bore pit |
9.61 (Aviation Blvd) -
continued |
Bore pit |
8.09 (Grevillea Ave) |
Bore pit |
8.46 (Inglewood Av) -
continued |
Drill |
10.60 (Douglas &
Sepulveda) |
Segment 4B Comments: No
non-compliance events occurred. Construction
activities halted at 2:00 p.m. on December 18 due to
heavy rains. Bore equipment continues to breakdown
and need repair.
Segment 4B Schedule for Next
Week:
Continue bore pit excavations and
directional drill.
H. SEGMENT 5 CONSTRUCTION PROGRESS
This segment involves construction in
railroad and roadway right-of-ways through mostly
industrial areas from Compton to the Long Beach Harbor.
Segment 5 EM, Pete Messick, has been on-site during
construction. PPSI has five craft inspectors, one
environmental inspector, one Native American monitor, and
one contamination inspector inspecting the work of
approximately 30 contractor employees during construction
of Segment 5C. Construction is complete on Segments 5A
and 5B. Construction progress from December 15 through
19, 1997 included the following:
Segment 5C Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
111.74 (no
progress) |
NDT |
110.41 to
110.70 |
Trench |
111.47 to 111.09 |
Coating |
110.41 to 110.70 |
Lower-In |
110.17 to 110.70 |
Conduit |
110.40 to 110.59 |
Backfill |
110.28 to 110.59 |
Paving |
110.28 to 110.44 |
Non-Compliance Event
for Segment 5
Mitigation Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
T.1 - Follow Work Zone Traffic Controls
as directed by affected public agency |
Lane closures past
4:30 p.m., Level 1
|
12/19/97
|
Yes
|
Acceptable
|
Segment 5 Comments: One
non-compliance event occurred. Progress is slow
because of numerous subsurface utilities. On December
18, a motorist failed to negotiate a turn and the
front end of vehicle slid partially into trench at
intersection of Myrrh and E. Alameda Streets. No one
was injured and vehicle sustained minor damage and no
one was injured. Work was suspended early on December
18 because of heavy rain.
Segment 5 Schedule for Next
Week:
Construction to continue.
I. VARIANCES
Five variances were approved by CPUC or
ANF December 15 through 19, 1997.
Variance #
|
Description
|
Segment(s)
Variance Applies
|
Agency Decision
|
20
|
Reroute along El Segundo Branch between
Normandie and Western Avenues from 120th Aven to
railroad ROW |
4B
|
Approved
|
32
|
Allow refueling with 0.25 miles of
streams along Peace Valley Road at designated
locations |
1
|
Approved/Denied
(for specific locations)
|
33
|
Use of solar/battery powered fraffic
signs in lieu of alternatively feuled vehicles |
All
|
Approved
|
37
|
Allow for storage of spoils in ROW
withing 50 yards of residences, schools, and
businesses |
1, 2, and 3
|
Approved
|
39
|
Allow the use of water trucks to remove
dirt from surface streets to help in complying
with Mitigation Measure A-8 |
All
|
Approved
|
J. EXTRA WORK SPACE
The following extra work
spaces/equipment storage area was approved by CPUC or ANF
December 15 through 19, 1997.
Request #
|
Description
|
Segment(s)
Variance Applies
|
Agency Decision
|
22
|
Additional work space/equipment storage
end of Castaic Road, Los Angeles |
2B
|
Approved
|
K. GENERAL PLANS FOR NEXT WEEK
Construction on Segments 1, 2B, 3, 4A,
4B and 5C will continue and construction zones will be
secured for Christmas holiday. All crews will be off
December 24 through 28 for Christmas holiday.
|