PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATION
MONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (December 15 through 21, 1997)

TO: Andrew Barnsdale, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: PPSI: Week 26 Report; December 15 through 21, 1997
DATE: December 23, 1997

A. INTRODUCTION

Construction continued on Segment 1 (Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73); Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108), Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108 to 118).

B. SEGMENT 1 CONSTRUCTION PROGRESS

This segment extends southward from the southern end of the San Joaquin Valley (Emidio), through the Tejon Pass, to the northern perimeter of the Angeles National Forest. Construction will occur through agricultural fields, along roads and across very steep slopes. Segment 1 Environmental Monitor (EM), Lynn Stafford has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 25 contractor employees. Construction progress from December 15 through 19, 1997 included the following:

Segment 1 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Paving 33.33 to 33.01 • Non-Destructive Testing (NDT) 32.81 to 31.89
• Trench 32.58 to 32.20 • Coating 32.81 to 31.89
• Bend 32.64 to 31.61 • Conduit 32.81 to 32.44
• Lower-In 32.81 to 31.61 • Backfill 32.97 to 32.44

Segment 1 Comments: No non-compliance events occurred. Copco Road restricted to one lane during work hours with appropriate traffic control measures in place. Rain on December 18 limited construction activities. California Highway Patrol officers have inspected the construction zone and have commented on the good traffic control.

Segment 1 Schedule for Next Week:

Begin construction activities along Peace Valley Road (EMP 32.29).

C. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles National Forest involved very steep slopes and required significant time and additional equipment for trenching, stringing, and other pipe-laying activities. All construction activities to Templin Highway, except revegetation, were completed by November 9. ANF will inform PPSI of additional work that needs to be done after final inspection that will occur at a later date.

Segment 2A Comments:

No construction or revegetation activities occurred. On December 16, PPSI inspected and videotaped erosion problems (due to a major storm and associated run-off) from a helicopter.

Segment 2A Schedule for Next Week:

PPSI to arrange to meet with ANF after the holidays. Requirements of final inspection to be determined after meeting with ANF representative.

D. SEGMENT 2B CONSTRUCTION PROGRESS

This segment is primarily in open lands and roadway right-of-ways from Castaic to Sylmar. Segment 2B EM, Chris Fazzari, has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 45 contractor employees. Construction progress December 15 through 19, 1997 included the following:

Segment 2B Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 58.3 to 58.42 • Welding 57.8 to 58.15
• Trench 58.0 to 58.40 • Coating 57.8 to 58.15
• Lower-In 57.8 to 58.24 • Backfill 57.8 to 58.13
• Conduit 57.8 to 58.15 • Concrete 57.7 to 57.86

Segment 2B Comments:

One non-compliance event occurred. Traffic control has been monitored daily by Los Angeles County inspector, Scott Thompson. A pilot car was used to guide traffic through the construction zone on The Old Road. A 96" storm drain was located near Parker Road (EMP 58.51). It isn’t currently known if it will be required to bore under the drain. Rain on December 18 slowed construction activities.

Non-Compliance Events for Segment 2B

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

A.2.1 - Limit construction activities off the ROW

Crew cleared area and put spoil pile outside ROW, Level 3

12/16/97

Yes

Acceptable

Segment 2B Schedule for Next Week:

Continue construction on The Old Road.

E. SEGMENT 3 CONSTRUCTION PROGRESS

This segment is mostly within MTA rail right-of-way from Sylmar to Alameda Street in Los Angeles. Segment 3 EM, Brooke Langle, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one contaminated soils inspector, and one Native American monitor inspecting the work of approximately 30 contractor employees. Construction progress from December 15 through 20, 1997 included the following:

Segment 3 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Shrub removal 82.30 to 83.71 (complete) • Coating 80.07 to 80.47
• Trench 80.07 to 80.87 • Conduit 79.90 to 80.43
• Lower-In 80.23 to 80.64 • Backfill 79.90 to 80.43
• Welding 80.07 to 80.58 • Valve 81.48
• NDT 80.07 to 80.47    

Segment 3 Comments:

No non-compliance events occurred. Strong winds (10 to 15 mph) continued to blow all week. Bore completed at Osborne Street (EMP 80.56) and continued at Branford Street (EMP 81.47). Rain on December 18 slowed construction activities.

Segment 3 Schedule for Next Week:

Complete bore operations at Branford Street (EMP 81.47).

F. SEGMENT 4A CONSTRUCTION PROGRESS

This segment involves nighttime construction (8:00 p.m. to 5:30 a.m.) in railroad and roadway right-of-ways through mostly industrial areas from downtown Los Angeles to Compton. Segment 4A EM, Christopher Meyer, has been on-site during construction. PPSI has two craft inspectors, one environmental inspector, and one contamination inspector inspecting the work of approximately 25 contractor employees during construction. Construction progress from December 15 through 19, 1997 included the following:

Segment 4A Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 99.51 to 100.01 • Welding 99.50 to 99.54
• Trench 99.60 to 99.82 • Coating 99.50 to 99.54
• Lower-In 99.50 to 99.60 • Track removal 101.53 (no progress)

Segment 4A Comments:

Two non-compliance events occurred. On December 16 the sidewalls of a bell hole collapsed. Steel plates were used to shore the trench and the cavities were filled with soil. No one was injured.

Non-Compliance Events for Segment 4A

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

SS.2.2 - Use hand tools within 24" of underground structures. Crews failed to excavate by hand and broke a 10" sewer line, Level 3

12/15/97

Yes

Acceptable

T.1.2 - Lane closures avoided and Transportation Management Plan developed and followed

Lanes closed past 6:00 a.m. restriction, Level 3

12/15/97

Yes

Acceptable

Segment 4A Schedule for Next Week:

Continue having three work areas: one for track removal, one for saw-cutting asphalt, and one for trenching and pipelaying.

G. SEGMENT 4B CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Watts Junction to El Segundo Refinery area. Segment 4B EM, Neda Fioozat, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 25 contractor employees. Construction progress from December 15 through 19, 1997 included the following:

Segment 4B Activities

Activity El Segundo Milepost (approx) Activity El Segundo Milepost (approx)
• Pot-hole 7.97 - no progress • Bore pit 8.84 (Eucalyptus Ave)
• Bore pit 9.61 (Aviation Blvd) - continued • Bore pit 8.09 (Grevillea Ave)
• Bore pit 8.46 (Inglewood Av) - continued • Drill 10.60 (Douglas & Sepulveda)

Segment 4B Comments: No non-compliance events occurred. Construction activities halted at 2:00 p.m. on December 18 due to heavy rains. Bore equipment continues to breakdown and need repair.

Segment 4B Schedule for Next Week:

Continue bore pit excavations and directional drill.

H. SEGMENT 5 CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 30 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B. Construction progress from December 15 through 19, 1997 included the following:

Segment 5C Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
• Pot-hole 111.74 (no progress) • NDT 110.41 to 110.70
• Trench 111.47 to 111.09 • Coating 110.41 to 110.70
• Lower-In 110.17 to 110.70 • Conduit 110.40 to 110.59
• Backfill 110.28 to 110.59 • Paving 110.28 to 110.44

Non-Compliance Event for Segment 5

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

T.1 - Follow Work Zone Traffic Controls as directed by affected public agency

Lane closures past 4:30 p.m., Level 1

12/19/97

Yes

Acceptable

Segment 5 Comments: One non-compliance event occurred. Progress is slow because of numerous subsurface utilities. On December 18, a motorist failed to negotiate a turn and the front end of vehicle slid partially into trench at intersection of Myrrh and E. Alameda Streets. No one was injured and vehicle sustained minor damage and no one was injured. Work was suspended early on December 18 because of heavy rain.

Segment 5 Schedule for Next Week:

Construction to continue.

I. VARIANCES

Five variances were approved by CPUC or ANF December 15 through 19, 1997.

Variance #

Description

Segment(s) Variance Applies

Agency Decision

20

Reroute along El Segundo Branch between Normandie and Western Avenues from 120th Aven to railroad ROW

4B

Approved

32

Allow refueling with 0.25 miles of streams along Peace Valley Road at designated locations

1

Approved/Denied (for specific locations)

33

Use of solar/battery powered fraffic signs in lieu of alternatively feuled vehicles

All

Approved

37

Allow for storage of spoils in ROW withing 50 yards of residences, schools, and businesses

1, 2, and 3

Approved

39

Allow the use of water trucks to remove dirt from surface streets to help in complying with Mitigation Measure A-8

All

Approved

J. EXTRA WORK SPACE

The following extra work spaces/equipment storage area was approved by CPUC or ANF December 15 through 19, 1997.

Request #

Description

Segment(s) Variance Applies

Agency Decision

22

Additional work space/equipment storage end of Castaic Road, Los Angeles

2B

Approved

K. GENERAL PLANS FOR NEXT WEEK

Construction on Segments 1, 2B, 3, 4A, 4B and 5C will continue and construction zones will be secured for Christmas holiday. All crews will be off December 24 through 28 for Christmas holiday.