PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATION
MONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (December 22 through 28, 1997)

TO: Andrew Barnsdale, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: PPSI: Week 27 Report; December 22 through 28, 1997
DATE: December 29, 1997

A. INTRODUCTION

Construction continued on Segment 1 (Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73); Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108), Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108 to 118).

B. SEGMENT 1 CONSTRUCTION PROGRESS

This segment extends southward from the southern end of the San Joaquin Valley (Emidio), through the Tejon Pass, to the northern perimeter of the Angeles National Forest. Construction will occur through agricultural fields, along roads and across very steep slopes. Segment 1 Environmental Monitor (EM), Sandy Etchell has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 25 contractor employees. Construction progress from December 22 through 26, 1997 included the following:

Segment 1 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Paving 33.01 to 31.90  
Trench
32.20 to 31.44
Non-DestructiveTesting
(NDT)
31.89 to 31.59
Bend 31.61 to 31.44 Coating 31.89 to 31.59
Lower-In 31.61 to 31.44 Conduit 32.44 to 31.69
Backfill 32.44 to 31.69

Segment 1 Comments:

One non-compliance event occurred. Peace Valley Road restricted to one lane during work hours with appropriate traffic control measures in place. Construction activities did not occur during the Christmas holiday, December 24 through 26.

 

Non-Compliance Event for Segment 1

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

A.2.1 - Confine construction activities to ROW

Pipe x-rayed and coated off ROW - Level 3

12/22/97

Yes

Acceptable

Segment 1 Schedule for Next Week:

Construction activities will be suspended January 1 and 2 for New Year’s holiday.

C. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles National Forest involved very steep slopes and required significant time and additional equipment for trenching, stringing, and other pipe-laying activities. All construction activities to Templin Highway, except revegetation, were completed by November 9. ANF will inform PPSI of additional work that needs to be done after final inspection that will occur at a later date.

Segment 2A Comments:

No construction or revegetation activities occurred. On December 16, PPSI inspected and videotaped erosion problems (due to a major storm and associated run-off) from a helicopter.

Segment 2A Schedule for Next Week:

PPSI to arrange to meet with ANF after the holidays. Requirements of final inspection to be determined after meeting with ANF representative.

D. SEGMENT 2B CONSTRUCTION PROGRESS

This segment is primarily in open lands and roadway right-of-ways from Castaic to Sylmar. Segment 2B EM, Chris Fazzari, has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 45 contractor employees. Construction progress December 22 through 26, 1997 included the following:

Segment 2B Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Pot-hole 58.42 to 58.70 Welding 58.15 to 58.26
Trench 58.40 to 58.67 Coating 58.15 to 58.26
Lower-In 58.24 to 58.48 Backfill 58.13 to 58.24
Conduit 58.15 to 58.26    

Segment 2B Comments:

No non-compliance events occurred. Traffic control being monitored daily by Los Angeles County inspector, Scott Thompson. Construction activities did not occur during the Christmas holiday, December 24 through 26 .

Segment 2B Schedule for Next Week:

Continue construction on The Old Road toward Hwy 126. Construction activities will be suspended January 1 and 2 for New Year’s holiday.

E. SEGMENT 3 CONSTRUCTION PROGRESS

This segment is mostly within MTA rail right-of-way from Sylmar to Alameda Street in Los Angeles. Segment 3 EM, Brooke Langle, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one contaminated soils inspector, and one Native American monitor inspecting the work of approximately 30 contractor employees. Construction progress from December 22 through 26, 1997 included the following:

Segment 3 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Trench 80.87 to 80.93 Coating 80.47 to 80.60
Lower-In 80.64 to 80.71 Conduit 80.43 to 80.52
NDT 80.47 to 80.60 Backfill 80.43 to 80.61
Valve 81.48 (continued)

Segment 3 Comments:

No non-compliance events occurred. Strong winds (10 to 15 mph) continued to blow Monday. Construction activities did not occur during the Christmas holiday, December 24 through 26

Segment 3 Schedule for Next Week:

Construction activities will be suspended January 1 and 2 for New Year’s holiday.

F. SEGMENT 4A CONSTRUCTION PROGRESS

This segment involves nighttime construction (8:00 p.m. to 5:30 a.m.) in railroad and roadway right-of-ways through mostly industrial areas from downtown Los Angeles to Compton. Segment 4A EM, Christopher Meyer, has been on-site during construction. PPSI has two craft inspectors, one environmental inspector, and one contamination inspector inspecting the work of approximately 25 contractor employees during construction. Construction progress from December 22 through 26, 1997 included the following:

Segment 4A Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Pot-hole 100.01 to 100.06 Welding 99.54 to 99.61
Trench 99.82 to 99.91 Coating 99.54 to 99.61
Lower-In 99.60 to 99.70 Track removal 101.53 (no progress)

Segment 4A Comments:

No non-compliance events occurred. Progress is slow because of the number of subsurface utilities.

Segment 4A Schedule for Next Week:

Continue having three work areas: one for track removal, one for saw-cutting asphalt, and one for trenching and pipelaying. Construction activities will be suspended January 1 and 2 for New Year’s holiday.

G. SEGMENT 4B CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Watts Junction to El Segundo Refinery area. Segment 4B EM, Neda Fioozat, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 25 contractor employees. Construction progress from December 22 through 26, 1997 included the following:

Segment 4B Activities

Activity El Segundo Milepost (approx) Activity El Segundo Milepost (approx)
Pot-hole Hawthorne and Birch Avenues Bore pit 8.84 (Eucalyptus Ave) - cont
Bore pit 9.61 (Aviation Blvd) - complete Bore pit 8.09 (Grevillea Ave) - cont
Bore pit 8.46 (Inglewood Av) - continued Drill 10.60 (Sepulveda Blvd)

Segment 4B Comments:

No non-compliance events occurred. Bore equipment continues to breakdown and need repair.

Segment 4B Schedule for Next Week:

Continue bore pit excavations and directional drill. Construction activities will be suspended January 1 for New Year’s holiday.

H. SEGMENT 5 CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 30 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B. Construction progress from December 22 through 26, 1997 included the following:

Segment 5C Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Pot-hole 111.74 to 110.90 NDT 110.70 (no progress)
Trench 111.47 to 111.90 Coating 110.70 (no progress)
Lower-In 110.70 to 110.90 Conduit 110.59 to 110.70
Backfill 110.59 to 110.70 Paving 110.44 to 109.67

Segment 5 Comments:

No non-compliance events occurred. Construction activities did not occur during the Christmas holiday, December 24 through 26.

Segment 5 Schedule for Next Week:

Construction activities will be suspended January 1 and 2 for New Year’s holiday.

I. VARIANCES

No variances were approved by CPUC or ANF December 22 through 26, 1997.

J. EXTRA WORK SPACE

No extra work spaces/equipment storage area were approved by CPUC or ANF December 22 through 26, 1997.

K. GENERAL PLANS FOR NEXT WEEK

Construction on Segments 1, 2B, 3, 4A, 4B and 5C will continue and construction zones will be secured for New Year’s holiday.