PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATIONMONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (January 5 through 11, 1998)

TO: Andrew Barnsdale, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: PPSI: Week 29 Report; January 5 through 11, 1998
DATE: January 12, 1998

A. INTRODUCTION

Construction continued on Segment 1 (Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73); Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108), Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108 to 118).

B. SEGMENT 1 CONSTRUCTION PROGRESS

This segment extends southward from the southern end of the San Joaquin Valley (Emidio), through the Tejon Pass, to the northern perimeter of the Angeles National Forest. Construction will occur through agricultural fields, along roads and across very steep slopes. Segment 1 Environmental Monitor (EM), Sandy Etchell has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 30 contractor employees. Construction progress from January 5 through 9, 1998 included the following:

Segment 1 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Paving 31.90 to 31.79 NDT (x-ray) 30.97 to 30.00
Trench 30.45 to 31.08 Coating 30.97 to 30.00
Bend 30.45 to 31.08 Conduit 31.56 to 31.32
Lower-In 30.45 to 31.08 Backfill 31.56 to 31.32

Segment 1 Comments: No non-compliance events occurred. Crew lowered-in and welded valve pipes at San Andreas block valve No. 8 (MP 30.4). Construction activities limited to along Peace Valley Road. Only a few crews worked January 9 because of rain.

Segment 1 Schedule for Next Week:

Complete construction along Peace Valley Road. Work on valve No. 8 at Gorman scheduled to begin January 19.

C. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles National Forest involved very steep slopes and required significant time and additional equipment for trenching, stringing, and other pipe-laying activities. All construction activities to Templin Highway, except revegetation, were completed by November 9.

Segment 2A Comments:

PPSI has not implemented a more aggressive implementation of the erosion control plan as requested by Mike Wickman (ANF) in a letter to PPSI dated December 15, 1997.

Segment 2A Schedule for Next Week:

PPSI has not provided a schedule for restoration and erosion control on Segment 2A.

D. SEGMENT 2B CONSTRUCTION PROGRESS

This segment is primarily in open lands and roadway right-of-ways from Castaic to Sylmar. Segment 2B EM, Chris Fazzari, has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 50 contractor employees. Construction progress January 5 through 9, 1998 included the following:

Segment 2B Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Pot-hole 62.00 (no progress) Coating 58.48 to 58.84
Trench 58.81 to 61.93 (with skips) Backfill 58.48 to 58.84
Lower-In 58.66 to 58.86 Paving 58.35 to 58.81
Conduit 58.48 to 58.84  

Segment 2B Comments:

No non-compliance events occurred. Traffic control has been monitored daily by Los Angeles County inspector, Scott Thompson. Pilot car used along The Old Road and contractor sent letter to local school district residents notifying them of potential traffic delays and suggesting alternate routes. Work halted on January 9 at 11:00 a.m. because of rain.

Segment 2B Schedule for Next Week:

Horizontal directional drill at Santa Clarita River to begin.

E. SEGMENT 3 CONSTRUCTION PROGRESS

This segment is mostly within MTA rail right-of-way from Sylmar to Alameda Street in Los Angeles. Segment 3 EM, Brooke Langle, has been on-site during construction. PPSI has three craft inspectors, one environmental inspector, one contaminated soils inspector, and two Native American monitor inspecting the work of approximately 30 contractor employees. Construction progress from January 5 through 9, 1998 included the following:

Segment 3 Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Trench 81.07 to 81.58 Coating 80.90 to 81.27
Lower-In 80.71 to 81.34 Conduit 80.71 to 81.21
NDT (x-ray) 80.90 to 81.27 Backfill 80.86 to 81.21
Valve 81.48 (completed)

Segment 3 Comments:

Two non-compliance events occurred. Boring operations continue at Pierce, Branford, and Sheldon streets. Work halted on January 9 at 2:30 p.m. because of rain.

Non-Compliance Events for Segment 3

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

A.8.2/P.2a.1/U.2.3 - Reclaimed water be used in street sweepers/make arrangements to use reclaimed water/water truck drivers keep log.

Reclaimed water not obtained - Level 2

1/5/98

Yes

Acceptable

Storm Water Pollution Prevention Plan - do not store materials on the ROW for more than 3 days

Concrete-coated pipe stored on the ROW for more than 3 days - Level 2

1/6/98

Yes

Acceptable

Segment 3 Schedule for Next Week:

Crew from Segment 5 to start an additional construction zone on Segment 3.

F. SEGMENT 4A CONSTRUCTION PROGRESS

This segment involves nighttime construction (8:00 p.m. to 5:30 a.m.) in railroad and roadway right-of-ways through mostly industrial areas from downtown Los Angeles to Compton. Segment 4A EM, Christopher Meyer, has been on-site during construction. PPSI has three craft inspectors, one environmental inspector, and one contamination inspector inspecting the work of approximately 35 contractor employees during construction. Construction progress from January 5 through 9, 1998 included the following:

Segment 4A Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Pot-hole 100.06 to 100.10 Welding 99.63 to 99.70
Trench 99.96 (no progress) Coating 99.63 to 99.70
Lower-In 99.70 to 99.77 Backfill 99.50 to 99.61
Saw-cutting 101.78 (no progress) Track removal 101.57 to 101.67
 

Segment 4A Comments:

No non-compliance events occurred. No work occurred January 9 because of rain.

Segment 4A Schedule for Next Week:

Excavation of 31-foot deep ditch at 3rd Street and Alameda Street intersection.

G. SEGMENT 4B CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Watts Junction to El Segundo Refinery area. Segment 4B EM, Neda Fioozat, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 25 contractor employees. Construction progress from January 5 through 9, 1998 included the following:

Segment 4B Activities

Activity El Segundo Milepost (approx) Activity El Segundo Milepost (approx)
Bore pit 9.61 (Aviation Blvd) - continue Bore pit 8.84 (Eucalyptus Ave) - cont
Backfill 9.84 (Douglas Blvd bore pit) Bore pit 8.09 (Grevillea Ave) - continue
Bore pit 8.46 (Inglewood Av) - continue Trenching 10.60 to 10.40

Segment 4B Comments:

Three non-compliance events occurred. The contractor indicated that corrections will be made beginning January 12. Working space cramped in railroad ROW that runs between buildings, a school, and residences.

Non-Compliance Events for Segment 4B

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

T.9.1 - Advance signing (at least 72 hrs) when construction will cause loss of parking spaces

Construction equipment causing loss of parking spaces without signage- Level 2.

1/9/98

No

Unacceptable

V.1.1 - Do not store spoils less than 50 yards from residences, schools and businesses

Spoils stored less than 50 yards from residences, businesses, and a school - Level 1.

1/9/98

No

Unacceptable

Hazardous Materials Management Plan, Section 9.1(d) - remove contaminated soils and dispose of properly

Motor fluid puddled under construction equipment - Level 2.

1/9/98

No

Unacceptable

Segment 4B Schedule for Next Week:

Address non-compliances.

H. SEGMENT 5 CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 30 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B. Construction progress from January 5 through 9, 1998 included the following:

Segment 5C Activities:

Activity Milepost (approximate) Activity Milepost (approximate)
Pot-hole 111.90 (no progress) NDT (x-ray) 111.38 to 111.73
Trench 111.90 (no progress) Coating 111.38 to 111.73
Lower-In 111.38 to 111.73 Conduit 110.94 to 111.73
Backfill 110.94 to 111.73 Paving 110.65 to 111.62

Segment 5 Comments:

No non-compliance events occurred. Construction activities halted on January 9 at 12 noon because of rain. An underground vault was installed in Alameda Street north of Auto Drive South (MP 111.72).

Segment 5 Schedule for Next Week:

While waiting for permits to be approved, construction activities shutting down and moving to Segment 3. Only clean-up activities will occur.

I. VARIANCES

No variances were approved by CPUC or ANF January 5 through 9, 1998.

J. EXTRA WORK SPACE

No extra work spaces/equipment storage area were approved by CPUC or ANF January 5 through 9, 1998.

K. GENERAL PLANS FOR NEXT WEEK

Construction on Segments 1, 2B, 3, 4A, and 4B will continue. Clean-up and shut-down activities will occur on Segment 5C.