DATE: Februrary 6, 1998 A. INTRODUCTION
Construction continued on Segment 1
(Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73);
Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108),
Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108
to 118).
B. SEGMENT 1 CONSTRUCTION PROGRESS
This segment extends southward from the
southern end of the San Joaquin Valley (Emidio), through
the Tejon Pass, to the northern perimeter of the Angeles
National Forest. Construction will occur through
agricultural fields, along roads and across very steep
slopes. Segment 1 Environmental Monitor (EM), Sandy
Etchell has been on-site during construction. PPSI has
five craft inspectors, one environmental inspector, and
one Native American monitor inspecting the work of
approximately 30 contractor employees. Construction
progress from January 12 through 16, 1998 included the
following:
Segment 1 Activities:
Milepost |
(approximate) |
Milepost |
(approximate) |
Paving |
31.79
to 31.47 |
NDT (x-ray) |
30.00
to 30.68 |
Trench |
31.08
to 30.40 |
Coating |
30.00
to 30.68 |
Bend |
31.08
to 30.51 |
Conduit |
31.32
to 30.58 |
Lower-In
|
31.08
to 30.51 |
Backfill |
31.32
to 30.58 |
Segment 1 Comments: On
January 15 at 3:15 p.m. the Senior Construction
Inspector for the County of Los Angeles issued an
inspection notice instructing the project to clean-up
and shorten the operation to applicable permit
specifications. In addition, once the project meets
the permit specifications, a two-day shutdown of all
construction activities will occur. The CPUC/ANF
monitor agreed with the County inspector, and did not
issue a non-compliance because the County had already
enacted a stop-work order. Crew began installing
block valve No. 8 (MP 30.4). Construction activities
limited to along Peace Valley Road. Heavy rain halted
work at noon on January 15 and 16.
- Segment 1 Schedule for Next
Week:
- No further work north until
the project is approved by the Senior
Construction Inspector for the County of Los
Angeles. Contractor efforts will be limited
bringing the project back to county permit
specifications.
C. SEGMENT 2A CONSTRUCTION PROGRESS
This segment within the Angeles
National Forest involved very steep slopes and required
significant time and additional equipment for trenching,
stringing, and other pipe-laying activities. All
construction activities to Templin Highway, except
revegetation, were completed by November 9.
- Segment 2A Comments:
- PPSI has not implemented a
more aggressive implementation of the erosion
control plan as requested by Mike Wickman
(ANF) in a letter to PPSI dated December 15,
1997.
- Segment 2A Schedule for
Next Week:
- PPSI has not provided a
schedule for restoration and erosion control
on Segment 2A.
D. SEGMENT 2B CONSTRUCTION PROGRESS
This segment is primarily in open lands
and roadway right-of-ways from Castaic to Sylmar. Segment
2B EM, Chris Fazzari, has been on-site during
construction. PPSI has six craft inspectors, one
environmental inspector, and one Native American monitor
inspecting the work of approximately 65 contractor
employees. Construction progress January 12 through 17,
1998 included the following:
Segment 2B Activities:
Activitiy |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
62.00
to 61.51 |
Coating |
58.84
to 61.93 |
Trench |
61.93
to 61.56 (with skips) |
Backfill |
58.84
to 61.93 |
Lower-In |
58.86
to 61.90 |
Paving |
58.81
to 61.51 |
Conduit
|
58.84
to 61.96 |
Directional
Drill |
61.12
Castaic Creek |
- Segment 2B Comments:
- No non-compliance events
occurred. Traffic control has been monitored
daily by Los Angeles County inspector. Steel
plates covering excavated trench shifted and
were reset over the weekend.
- Segment 2B Schedule for
Next Week:
- Horizontal directional drill
at Castaic Creek to continue from 7 a.m.
until 7 p.m. Monday through Saturday.
E. SEGMENT 3 CONSTRUCTION PROGRESS
This segment is mostly within MTA rail
right-of-way from Sylmar to Alameda Street in Los
Angeles. Segment 3 EM, Brooke Langle, has been on-site
during construction. PPSI has two construction zones. In
the north zone, one craft inspector, one environmental
inspector, and one Native American monitor are inspecting
the work of approximately 10 contractor employees. In the
south zone, five craft inspectors, one environmental
inspector, one contaminated soils inspector, and two
Native American monitors are inspecting the work of
approximately 30 contractor employees. Construction
progress from January 12 through 17, 1998 included the
following:
Segment 3-North Activities:
Activity /Milepost
(approximate)
Pot-hole 76.32 Shrub
removal 76.32
Segment 3-South Activities:
Activity /Milepost
(approximate)
Trench 81.58 to 82.23
Coating 81.27 to 82.00
Lower-In 81.34 to 82.21
Conduit 81.21 to 82.00
NDT (x-ray) 81.27 to 82.04
Backfill 81.21 to 81.87
Segment 3-North Comments:
No non-compliance events occurred.
Crews pot-holed along the railroad ROW and removed
shrubs.
Segment 3-South Comments:
No non-compliance events occurred.
Welding operations began at bores of Paxton, Pierce,
Branford, and Sheldon streets.
Segment 3 Schedule for Next
Week:
Continue with two work zones.
F. SEGMENT 4A CONSTRUCTION PROGRESS
This segment involves nighttime
construction (8:00 p.m. to 5:30 a.m.) in railroad and
roadway right-of-ways through mostly industrial areas
from downtown Los Angeles to Compton. Segment 4A EM,
Christopher Meyer, has been on-site during construction.
PPSI has three craft inspectors, one environmental
inspector, and one contamination inspector inspecting the
work of approximately 35 contractor employees during
construction. Construction progress from January 12
through 16, 1998 included the following:
Segment 4A Activities:
Activity Milepost
(approximate)
Pot-hole 100.10 to 100.51
Welding 99.70 to 99.80
Trench 99.96 to 101.74
Coating 99.70 to 99.80
Lower-In 99.77 to 99.87
Backfill 99.61 to 99.67
Saw-cutting 101.78 (no
progress) Track removal 101.67 to 101.76
Segment 4A Comments:
No non-compliance events occurred.
Applicant working with contractor to ensure that the
traffic lanes are cleaned and road repairs compacted
properly before the end of the shift. Projected rain
storm limited work on January 16. Also on January 16,
steel plates in road intersection shifted and had to
be reset.
Segment 4A Schedule for Next
Week:
Excavation of 31-foot deep ditch at
3rd Street and Alameda Street intersection (postponed
from last week because of rain and flooding).
G. SEGMENT 4B CONSTRUCTION PROGRESS
This segment involves construction in
railroad and roadway right-of-ways through mostly
industrial areas from Watts Junction to El Segundo
Refinery area. Segment 4B EM, Neda Fioozat, has been
on-site during construction. PPSI has four craft
inspectors, one environmental inspector, one Native
American monitor, and one contamination inspector
inspecting the work of approximately 35 contractor
employees. Construction progress from January 12 through
16, 1998 included the following:
Segment 4B Activities
Activity El Segundo
Milepost (approx)
Pot-hole 7.45 Bore
pit 8.84 (Eucalyptus Ave) - cont
Bore pit 7.97 (Hawthorne
Blvd) Bore pit 8.09 (Grevillea Ave) - continue
Bore pit 8.46 (Inglewood Av)
- continue Trenching 10.60 to 10.66
Segment 4B Comments:
No new non-compliance events
occurred. Three non-compliance events from last week
were rectified. Working space cramped in railroad ROW
that runs between buildings, a school, and
residences. Boring equipment continues to breakdown,
causing delays.
Non-Compliance Events
for Segment 4B
Mitigation Measure/PC |
Description/Non-compliance
Level
|
First Observed
|
Corrected
|
Status
|
T.9.1 - Advance signing (at least 72
hrs) when construction will cause loss of parking
spaces |
Construction
equipment causing loss of parking spaces without
signage- Level 2.
|
1/9/98
|
Yes, 1/13/98
|
Acceptable
|
V.1.1 - Do not store spoils less than 50
yards from residences, schools and businesses |
Spoils stored less
than 50 yards from residences, businesses, and a
school - Level 1.
|
1/9/98
|
Yes, 1/14/98
|
Acceptable
|
Hazardous Materials Management Plan,
Section 9.1(d) - remove contaminated soils and
dispose of properly |
Motor fluid puddled
under construction equipment - Level 2.
|
1/9/98
|
Yes, 1/12/98
|
Acceptable
|
Segment 4B Schedule for Next
Week:
Repair boring equipment.
H. SEGMENT 5 CONSTRUCTION PROGRESS
This segment involves construction in
railroad and roadway right-of-ways through mostly
industrial areas from Compton to the Long Beach Harbor.
Segment 5 EM, Pete Messick, has been on-site during
construction. PPSI has four craft inspectors, one
environmental inspector, one Native American monitor, and
one contamination inspector inspecting the work of
approximately 20 contractor employees during construction
of Segment 5C. Construction is complete on Segments 5A
and 5B. Construction progress from January 12 through 17,
1998 included the following:
Segment 5C Activities:
Activity |
Milepost
(approximate) |
Activity |
Milepost
(approximate) |
Pot-hole |
111.90 (no
progress) |
NDT (x-ray) |
111.73 (no
progress) |
Trench |
111.90 (no progress) |
Coating |
111.73 (no progress) |
Lower-In |
111.73 (no progress) |
Conduit |
111.73 (no progress) |
Backfill |
111.73 to 111.90 |
Paving |
111.62 to 111.73 |
- Segment 5 Comments:
- No non-compliance events
occurred. Construction activities halted on
January 15 at 1:30 p.m. because of rain.
Fiber optic cable was fed through conduit at
Dominguez Channel Bridge (EMP 116.23).
Removal of spoil piles remaining along East
Alameda between Weber Avenue and Pine Street
(EMP 108.86 to 109.42) and Alondra Blvd and
Auto Drive South (EMP 110.99 to 111.60)
began.
-
- Segment 5 Schedule for Next
Week:
- While waiting for local
permits to be approved, construction
activities are shutting down and moving to
Segment 3. Only clean-up activities will
occur.
I. VARIANCES
The following variances were
approved/denied by CPUC or ANF January 5 through 16,
1998.
Variance #
|
Description
|
Segment(s)
Variance Applies
|
Agency Decision
|
36
|
Modification of Storm Water Pollution
Prevention Plan to increase the amount of pipe
that can be stored along the ROW |
All
|
Denied
|
40
|
Relocated block/check valve from station
3109+26 to 3123+00 |
2B
|
Approved
|
J. EXTRA WORK SPACE
The following extra work
spaces/equipment storage area were approved by CPUC or
ANF January 5 through 16, 1998.
- Request #
|
- Description
|
- Segment(s) Variance
Applies
|
- Agency Decision
|
23
|
Extra work space for Gorman Slide
directional drill, Los Angeles County |
1
|
Approved
|
24
|
Extra work space for Santa Clara River
directional drill, Los Angeles County |
2B
|
Approved
|
K. GENERAL PLANS FOR NEXT WEEK
Construction on Segments 2B, 3, 4A, and
4B will continue. Clean-up and shut-down activities will
occur on Segment 5C. Segment 1 will prepare for 2-day Los
Angles County imposed shut-down.
|