WEEKLY REPORT (January 19 through 25, 1998)
TO: Andrew Barnsdale, CPUC/Rich Borden, ANF | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
FROM: Hamid Rastegar/Kris Thorne | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
RE: PPSI: Week 31 Report; January 19 through 25, 1998 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
DATE: Februrary 6, 1998 A. INTRODUCTION Construction continued on Segment 1 (Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73); Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108), Segment 4B (El Segundo MP 0 to 11), and Segment 5 (MP 108 to 118). B. SEGMENT 1 CONSTRUCTION PROGRESS This segment extends southward from the southern end of the San Joaquin Valley (Emidio), through the Tejon Pass, to the northern perimeter of the Angeles National Forest. Construction will occur through agricultural fields, along roads and across very steep slopes. Segment 1 Environmental Monitor (EM), Sandy Etchell has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 65 contractor employees. Construction progress from January 19 through 23, 1998 included the following: Segment 1 Activities:
C. SEGMENT 2A CONSTRUCTION PROGRESS This segment within the Angeles National Forest involved very steep slopes and required significant time and additional equipment for trenching, stringing, and other pipe-laying activities. All construction activities to Templin Highway, except revegetation, were completed by November 9.
D. SEGMENT 2B CONSTRUCTION PROGRESS This segment is primarily in open lands and roadway right-of-ways from Castaic to Sylmar. Segment 2B EM, Chris Fazzari, has been on-site during construction. PPSI has six craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 95 contractor employees. Construction progress January 19 through 24, 1998 included the following: Segment 2B Activities:
E. SEGMENT 3 CONSTRUCTION PROGRESS This segment is mostly within MTA rail right-of-way from Sylmar to Alameda Street in Los Angeles. Segment 3 EM, Brooke Langle, has been on-site during construction. PPSI has two construction zones. In the north zone, one craft inspector, one environmental inspector, and one Native American monitor are inspecting the work of approximately 20 contractor employees. In the south zone, five craft inspectors, one environmental inspector, one contaminated soils inspector, and two Native American monitors are inspecting the work of approximately 80 contractor employees. Construction progress from January 19 through 23, 1998 included the following: Segment 3-North Activities:
Segment 3-South Activities:
F. SEGMENT 4A CONSTRUCTION PROGRESS This segment involves nighttime construction (8:00 p.m. to 5:30 a.m.) in railroad and roadway right-of-ways through mostly industrial areas from downtown Los Angeles to Compton. Segment 4A EM, Christopher Meyer, has been on-site during construction. PPSI has three craft inspectors, one environmental inspector, and one contamination inspector inspecting the work of approximately 60 contractor employees during construction. Construction progress from January 19 through 23, 1998 included the following: Segment 4A Activities:
G. SEGMENT 4B CONSTRUCTION PROGRESS This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Watts Junction to El Segundo Refinery area. Segment 4B EM, Neda Fioozat, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 60 contractor employees. Construction progress from January 19 through 23, 1998 included the following:
H. SEGMENT 5 CONSTRUCTION PROGRESS This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Compton to the Long Beach Harbor. Segment 5 EM, Pete Messick, has been on-site during construction. PPSI has two craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 15 contractor employees during construction of Segment 5C. Construction is complete on Segments 5A and 5B. While waiting for local access to be granted, construction activities shut down. Only spoil pile removal activities will occur. There was no construction progress from January 26 through 30, 1998.
The shutdown is expected to continue. I. VARIANCES The no variances were approved/denied by CPUC or ANF January 19 through 23, 1998. J. EXTRA WORK SPACE The no extra work spaces/equipment storage area were approved by CPUC or ANF January 19 through 23, 1998. K. GENERAL PLANS FOR NEXT WEEK Construction on Segments 1, 2B, 3, 4A, and 4B will continue. Clean-up activities will occur on Segment 5C. |