PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATIONMONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (February 23 through March 1, 1998)

TO: Andrew Barnsdale, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: Week 36 Report; February 23 through March 1, 1998
DATE: March 18, 1998

A. INTRODUCTION

Construction continued on Segment 1 (Milepost (MP) 0 TO 33), Segment 2B (MP 56 to 73); Segment 3 (MP 73 to 99), Segment 4A (MP 99 to 108), and Segment 4B (El Segundo MP 0 to 11). Construction has resumed on Segment 5 (MP 108 to 118).

B. SEGMENT 1 CONSTRUCTION PROGRESS

This segment extends southward from the southern end of the San Joaquin Valley (Emidio), through the Tejon Pass, to the northern perimeter of the Angeles National Forest. Construction will occur through agricultural fields, along roads and across very steep slopes. Segment 1 Environmental Monitor (EM), Lynn Stafford has been on-site during construction. PPSI has five craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 65 contractor employees. Construction progress from February 23 through 27, 1998 included the following:

Segment 1 Activities:

Activity Milepost (approximate)
• Pot-hole 22.99 to 21.45
• NDT (x-ray) 25.84 (no progress)
• Trench 27.85 to 27.09
• Coating 27.15 (no progress)
• Bend 27.15 (no progress)
• Conduit 26.61 to 27.09
• Lower-In 27.85 to 27.09
• Backfill 26.61 to 27.24

Segment 1 Comments:

No non-compliances occurred. Traffic control has been monitored daily by Los Angeles County inspector. Boring operations at Gorman Creek (MP 32.40) continued with fiber optic conduit being pushed into place. Rain halted construction on February 23 and 24. Erosion and silt control efforts were satisfactory.

Segment 1 Schedule for Next Week:

Finish bore at Gorman Creek then continue north on Peace Valley Road. Continue to monitor dust control along closed-lane portion of Peace Valley Road from EMP 28.28 to 27.52.

C. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles National Forest involved very steep slopes and required significant time and additional equipment for trenching, stringing, and other pipe-laying activities. All construction activities to Templin Highway, except revegetation, were completed by November 9.

Segment 2A Comments:

PPSI has not implemented a more aggressive implementation of the erosion control plan as requested by Mike Wickman (ANF District Ranger) in a letter to PPSI dated December 15, 1997. PPSI provided a schedule for restoration and erosion control on Segment 2A. ANF requested that PPSI provide an explanation on the use of the unapproved fiber optic conduit that was installed on ANF lands.

Segment 2A Schedule for Next Week:

ANF to review and comment on restoration and erosion control schedule. PPSI to meet with ANF to respond to ANF’s request for an explanation of the installation and use of excess fiber optic conduits.

D. SEGMENT 2B CONSTRUCTION PROGRESS

This segment is primarily in open lands and roadway right-of-ways from Castaic to Sylmar. Segment 2B EM, Chris Fazzari, has been on-site during construction. PPSI has six craft inspectors, one environmental inspector, and one Native American monitor inspecting the work of approximately 95 contractor employees. Construction progress February 23 through 28, 1998 included the following:

Segment 2B Activities:

Activity Milepost (approximate)
• Pot-hole 60.12 to 59.87
• Conduit 60.22 to 60.01
• Trench 60.14 to 59.78
• Backfill 60.22 to 60.01
• Lower-In 60.00 to 59.89
• Paving 59.97 to 60.07
• Coating 60.22 to 59.98

Segment 2B Comments:

No non-compliance events occurred. Traffic control has been monitored daily by Los Angeles County inspector. Direction drill at Santa Clara River was completed. Rain halted construction on February 23 and 24. Eight-hour hydrostatic test of Castaic Creek direction drill was successfully completed.

Segment 2B Schedule for Next Week:

Work along The Old Road north of Hasley Canyon Road to continue.

E. SEGMENT 3 CONSTRUCTION PROGRESS

This segment is mostly within MTA rail right-of-way from Sylmar to Alameda Street in Los Angeles. Segment 3 EM, Brooke Langle, has been on-site during construction. PPSI has two active construction zones: Seg 3 - North has five craft inspectors, one environmental inspector, and one contaminated soils inspector inspecting the work of approximately 80 contractor employees. Seg 3 - Los Feliz has two craft inspectors, one environmental inspector and one contaminated soils inspector. Construction progress from February 23 through 28, 1998 included the following:

Segment 3 - North Activities

Activity Milepost (approximate)

• Trench 84.58 to 85.00
• Coating 84.14 to 84.86
• Lower-In 84.29 to 84.97
• Conduit 84.14 to 84.86
• NDT (x-ray) 84.20 to 84.91
• Backfill 84.01 to 84.83

Segment 3 - North Comments:

No non-compliance events occurred. Rain halted construction on February 23 and 24. Crews worked Saturday, February 28, to complete work near Roscoe Elementary School. Boring operations were completed at Arvilla Avenue. Bore crew began to set-up at Buena Vista Avenue. Directional drilling operations began to move equipment to drill site near EMP 86.91.

Segment 3 - North Schedule for Next Week:

Directional drilling to begin at Burbank Crossing (dog pound) mid-week.

Segment 3 - Los Feliz Activities

Activity Milepost (approximate)
• Trench 93.35 to 93.75
• Coating 93.14 to 93.75
• Lower-In 93.14 to 93.75
• Conduit 93.14 to 93.75
• NDT (x-ray) 93.14 to 93.75
• Backfill 93.14 to 93.75

Segment 3 - Los Feliz Comments:

No non-compliance events occurred. Rain halted construction on February 23 and 24. Crew excavated bore pit at Casitas Street. Continuing contract negotiations with the StorItAll storage facility property owner halted construction on February 25.

Segment 3 - Los Feliz Schedule for Next Week:

Continue to close the trench and asphalt over it each night at the StorItAll facility. Excavate bore pit and begin bore at Casitas Avenue.

F. SEGMENT 4A CONSTRUCTION PROGRESS

This segment involves nighttime construction (8:00 p.m. to 5:30 a.m.) in railroad and roadway right-of-ways through mostly industrial areas from downtown Los Angeles to Compton. Segment 4A EM, Christopher Meyer, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 60 contractor employees during construction. Construction progress from February 23 through 27, 1998 included the following:

Segment 4A Activities:

Activity Milepost (approximate)
• Pot-hole 102.10 (no progress)
• Coating 102.01 to 100.17
• Trench 102.01 to 100.45
• Backfill 102.01 to 100.17
• Lower-In 102.01 to 100.17
• Conduit 102.02 to 100.16

Segment 4A Comments:

One non-compliance event occurred on February 27. For the fourth time on Segment 4A, the contractor damaged a marked underground utility. This incident was added to an on-going investigation of the PPSI project by the CPUC. Rain halted construction on February 23.

Non-Compliance Event for Segment 4A

Mitigation Measure/PC

Description/Non-compliance Level

First Observed

Corrected

Status

SS.2 - Use hand tools to excavate within 24 inches of underground structures and in utility intensive areas.

Marked, 1-inch water line cut by backhoe during excavation - Level 3

2/27/98

Under review by CPUC

Under review by CPUC

Segment 4A Schedule for Next Week:

Continue general construction activities with emphasis on looking for utility markings on roadways and avoiding underground utilities during construction.

G. SEGMENT 4B CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Watts Junction to El Segundo Refinery area. Segment 4B EM, Neda Fioozat, has been on-site during construction. PPSI has four craft inspectors, one environmental inspector, one part-time Native American monitor, and one contamination inspector inspecting the work of approximately 60 contractor employees. Construction progress from February 23 through 27, 1998 included the following:

Segment 4B Activities

Activity El Segundo Milepost (approx)
• Bore pit 8.84 (Eucalyptus Ave) - continue
• Bore pit 7.76 (Cedar Ave) - continue
• Bore pit 8.46 (Inglewood Ave) - continue
• Bore pit 7.64 (Menlo Ave) - continue
• Bore pit 7.70 (Freeman Ave) - continue
• Bore pit 7.58 (Oxford Ave) - continue
• Bore pit 8.09 (Grevillea Ave) - continue
• Bore pit 7.52 (Yourk Ave)

Segment 4B Comments:

No non-compliance events occurred. Contractor continues to bore roads. No construction activities occurred on February 23 and 24 because of rain. Spoil being stored in such a manner as to not cause a visual impact along the ROW.

Segment 4B Schedule for Next Week:

Continue bores and monitor bore pits for stability.

H. SEGMENT 5 CONSTRUCTION PROGRESS

This segment involves construction in railroad and roadway right-of-ways through mostly industrial areas from Compton to the Long Beach Harbor. Segment 5C EM, Pete Messick, has been on-site during construction. PPSI has three craft inspectors, one environmental inspector, one Native American monitor, and one contamination inspector inspecting the work of approximately 40 contractor employees. Construction is complete on Segments 5A and 5B. Construction progress from February 23 through 28, 1998 included the following.

Segment 5C Activities:

Activity Milepost (approximate)
• Pot-hole 115.62 to 115.87
• Lower-In 115.87 to 115.85
• Trench 115.68; 115.80 to 115.87

Segment 5C Comments:

No non-compliances occurred. Construction resumed on February 26 after a delay imposed by the Los Angeles County Alameda Corridor contractor. On February 28 a conduit for a mismarked fiber optic line was cracked, but service was not interrupted.

Segment 5C Schedule for Next Week:

Complete laying and backfilling pipe in 1000-foot segment before March 9 (window of construction given by Los Angeles County Alameda Corridor contractor.

I. VARIANCES

The following variances were approved/denied by CPUC or ANF February 23 through 27, 1998.

Variance #

Description

Segment(s) Variance Applies

Agency Decision

47

Refueling withing 0.25 miles of streams along Peace Valley Road (riparian habitat at Hungry Valley State Park)

1

Denied

49

Open cut Birch Avenue, City of Hawthorne

4B

Approved

J. EXTRA WORK SPACE

The following extra work space/equipment storage area was approved by CPUC or ANF February 23 through 27, 1998.

Request #
Description
Segment(s) Variance Applies
Agency Decision

28

Extra work space for Burbank directional drill, Los Angeles County

3

Approved

K. GENERAL PLANS FOR NEXT WEEK

Construction on Segments 1, 2B, 3, 4A, 4B and 5C will continue. Small crew from Segment 5 to continue working the Los Feliz Blvd area of Segment 3.

Back to Weekly Reports

Back to MMCRP Home Page