PROJECT MEMORANDUM - PACIFIC PIPELINE MITIGATION
MONITORING, COMPLIANCE, AND REPORTING PROGRAM
 

WEEKLY REPORT (August 18 through 23)

 
TO: Martha Sullivan, CPUC/Rich Borden, ANF
FROM: Hamid Rastegar/Kris Thorne
RE: PPSI: Week Nine Report; August 18 through 23, 1997
DATE: August 26, 1997

 

A. INTRODUCTION

Construction continued on Segment 5B (Milepost [MP] 108 to 118) and Segment 2, Angeles National Forest (MP 33 to 57).

B. SEGMENT 2A CONSTRUCTION PROGRESS

This segment within the Angeles Forest Service involves very steep slopes and requires significant time and additional equipment for trenching, stringing, and other pipe laying activities. Segment 2A Environmental Monitor (EM), Stan Harding was on-site. PPSI has 12 craft inspectors, eight environmental inspectors, and six Native American monitors inspecting the work of approximately 103 contractor employees. Construction progress from August 18 through 23, 1997 included the following:

 

Segment 2A Activities:

Milepost (all mileposts are approximate)

Segment 2A Comments:

No non-compliances were observed. Frequent Level III (as defined in the ANF Fire Plan) fire conditions have required that clear and grade, and welding activities be suspended at 1:00 p.m. All crews are beginning at 5:30 a.m. and some crews are working until 7:00 p.m. Clear and grade activities south of Forest Inn (MP 45.81) were suspended by the ANF until the ANF is able to review and approve the contractor’s construction schedule for completion of construction activities on ANF lands. This suspension of activities was enacted by the ANF because of the concern that graded soils would not be revegetated prior to seasonal rains.

Segment 2A Schedule for Next Week:

No new crews are scheduled to begin. Construction will continue, with the exception of the clear and grade crew, as noted above.

C. SEGMENTS 5A and 5B CONSTRUCTION PROGRESS

This segment involves construction in railroad and road right-of-ways through industrial areas. Segment 5B EM, Pete Messick has been on-site during all construction hours. PPSI has four craft inspectors, two environmental inspectors, and one Native American monitor inspecting the work of approximately 25 contractor employees. Crews worked 9-hour days. Construction progress from August 18 through 22, 1997 included the following:

Segment 5B Activities:

  Milepost (all mileposts are approximate)
Pot-hole Complete
Trench Complete, except at Anaheim Street crossing (MP 118.71)
Welding & Lower-In Complete, except at Anaheim Street crossing (MP 118.71)
Slurry Backfill Complete, except at Anaheim Street crossing (MP 118.71)
Road Bores In progress at Pacific Coast Highway (MP 117.92)

Segment 5B Comments:

No non-compliances occurred.

Segment 5B Schedule for Next Week:

The road bore will continue at Pacific Coast Highway. Construction is scheduled to begin at Anaheim Street crossing. Segment 5C has received approval for construction in the railroad right-of-way.

D. VARIANCES

The following variances were approved August 18 through 22, 1997.

Variance #
Description
Segment(s) Variance Applies
Agency Decision
8
Night (9 p.m. to 5:30 a.m.) construction between College and N. Spring Street to Slauson Avenue
4
Approved
9
Modify ANF Transportation Management Plan to permit equipment haul-arounds on Old Ridge Route
2A (ANF)
Approved
11
Modify ANF Fire Protection Plan to reduce vegetation buffer from 50 to 25 feet when welding curtain is used
2A (ANF)
Approved

 

E. EXTRA WORK SPACE

The following construction yard was approved August 18 through 22, 1997.

 

Construction Yard/Staging Area

Applicable Segment(s)

Agency Decision

Construction Yard and Offices, 1326 San Fernando Road, City of San Fernando, CA

3

Approved

 

F. GENERAL PLANS FOR NEXT WEEK

Segment 2A and Segment 5B to continue, Segment 5C to begin. Segments 1, 3 and 4 (downtown LA only) expected to begin in September; El Segundo (Segment 4) expected to begin in October.