PACIFIC PIPELINE PROJECT MITIGATION MONITORING,
COMPLIANCE, AND REPORTING PROGRAM
AUGUST 1998 - MONTHLY REPORT

 

The following constitutes the August 1998 Monthly Report for the Pacific Pipeline Mitigation Monitoring, Compliance, and Reporting Program (MMCRP) contract. It should be noted that since the start of construction daily and weekly reports summarizing monitoring activities have been issued and are available on the project web site for review.

CONSTRUCTION MONITORING

Segment 1 Construction: Segment 1 runs from the southern end of the San Joaquin Valley at Emidio, through the Tejon Pass, to the northern boundary of the ANF in Los Angeles County. Construction of Segment 1 commenced on November 5, 1997. Primary activities during the month of August are presented in Table 1. No non-compliance events occurred on Segment 1 during August.

During August, construction along Segment 1 was conducted by three separate mainline crews, plus two station crews (Emidio and Grapevine). Trenching, pipelaying, and tie-in through the Tejon wetland (EMP 20.11 to 20.44) progressed slowly during August, partially as a result of the need to dewater. During the third week of August, the directional drill at Cuddy Creek (EMP 25.15 to 25.52) had a frac-out (drilling mud reaching the surface through a natural fracture in the ground) due to a badly worn drill head which was replaced. Work was conducted at the Grapevine bore (Interstate 5 crossing at Tejon Ranch - EMP 13.33) and Wheeler Ridge Road bore (EMP 10.63). Tie-in of the block valve north of the California Aqueduct (EMP 12.02) also continued through August. The open cut of Laval Road (instead of boring) was completed in accordance with approved Variance Request #103. Foundation work at the Emidio Pump Station (EMP 0.00) and grading at the Grapevine Pump Station (EMP 15.57) was also conducted during August.

Table 1. Construction Activities for Segment 11

Activity

Milepost (approximate)

Pot-hole

0.00 to 7.41, 18.78 to 19.98

Clearing

2.79 to 8.23, 18.90 to 19.98

Trench

5.81 to 6.00, 7.09 to 12.18, 19.12 to 19.98,

20.27 to 20.54

Lower-In

7.09 to 13.30, 19.41 to 19.98, 20.27 to 20.54

Coating

7.43 to 13.30. 19.45 to 19.98, 20.27 to 20.54

Conduit

7.43 to 13.30, 19.69 to 19.98, 20.27 to 20.54

Backfill

7.43 to 13.30, 19.69 to 19.98, 20.27 to 20.54

Emidio Pump Station - In Progress

0.00

Bore (Wheeler Ridge Road) - In Progress

10.63

Block Valve (North side California Aqueduct) - In Progress

12.02

Bore (I-5 crossing @ Tejon Ranch) - In Progress

13.33

Grapevine Pump Station - In Progress

15.57

Bore (I-5, north of Lebec Road overpass) - Complete

20.79

Bore (Lebec Road, south of overpass) - Complete

21.20

Bore (Lebec Road, Specimen Tree #2) - Complete

24.82

Directional Drill (Peace Valley & Lebec Roads, Cuddy Creek) - In Progress

25.15 to 25.52

Check Valve (Peace Valley Road, Cuddy Creek) - Complete

25.92

Bore (Stream Crossing #20) - Complete

27.43

Bore (Stream Crossing #21) - Complete

27.81

Bore (Stream Crossing #23) - Complete

28.10

Block Valve (Gorman) - Complete

28.33

Directional Drill (Gorman Slide) - Complete

28.68 to 29.68

Block Valve (San Andreas) - Complete

30.43

Bore (Stream Crossing #29) - Complete

32.38

Bore (Stream Crossing #30) - Complete

32.71

Block Valve (Copco Road) - Complete

32.81

1. Construction progress from August 3 through August 30.

Segment 2A/C (ANF) Construction: Construction within the ANF (Segment 2A) began on June 27, 1997 and was completed to Templin Highway on November 9, with the exception of some erosion repair, revegetation, valve, and conduit requirements. This follow-up work commenced in June 1998. Construction of Segment 2C, Templin Highway to Castaic, several miles south of the southern ANF boundary, commenced on June 22, 1998; portions of Segment 2C also traverse private lands. Construction of both Segment 2A and 2C is required by the ANF to be completed by October 3, 1998. Primary activities during the month of August are presented in Table 2. Table 3 presents the non-compliance events that occurred on Segments 2A or 2C during August.

Table 2. Construction Activities for Segment 2A/C1

Segment

Activity

Milepost (approximate)

2A

Erosion Repair/Prevention

38.90 to 39.45, 43.14, 45.54 to 45.62, 47.68 to 48.35, 48.44 to 48.92, 49.22 to 49.48

  Fiber Optic Conduit Repair

42.42 to 42.45

  Fiber Optic Cable Installation

43.14 to 43.72, 44.16 to 44.73, 45.43 to 45.90, 48.75 to 49.48

  Reseeding

38.92 to 39.45, 44.16 to 44.75, 45.43 to 45.62, 47.68 to 48.35, 48.96 to 49.26

  Roadway Repair

48.90 to 49.41

  Lowering of Block Valve

44.33

2C

Pot-hole

50.82 to 54.17

  Clearing

50.78 to 56.50

  Trench

50.82 to 50.96, 51.93 to 54.67

  Lower-In

50.88 to 51.32, 55.34 to 56.65

  Coating

52.51 to 52.56, 54.79 to 56.65

  Conduit

52.23 to 52.58, 56.55 to 57.05

  Backfill

52.30 to 52.58, 54.79 to 56.65

  Whitaker Pressure Relief Station - In Progress

51.35

  Bore (Under I-5) - In Progress

53.48

  Block Valve (Lake Hughes) - Complete

56.53

  Bore (Marple-Violin Canyon Creek) - Complete

56.74

1. Construction progress from August 3 through August 30.

Table 3. Non-Compliance Events for Segment 2A/C (ANF)1

Segment

Mitigation Measure/PC

Description/

Non-Compliance Level

First

Observed

Corrected

Status

2C

C-4.1: Qualified archaeological monitor present during ground disturbing activities. Access road widened without archaeological monitor present - Level 2.

8/4/98

8/4/98

Acceptable

2C

B-V-2.3: Set aside and protect topsoil during construction. Spoils mixed in with topsoil - Level 3.

8/20/98

8/21/98

Acceptable

1. Non-compliance reports issued from August 3 through August 30.

Segment 2A - During August, erosion repair, including installation of erosion control materials and reseeding, was conducted on Segment 2A. Repair of fiber optic conduit and roadways also continued. A 50-foot section of pipe was removed from EMP 44.35 in preparation for future hydrotesting activities. By the end of the month, installation of fiber optic cable began, and some crews and equipment began to move to Segment 2C to help complete construction on the ANF by the October 3 deadline.

Segment 2C - During August, flume pipe was installed to protect a running stream at EMP 53.01. Hog and silt fences were installed along culverts and stream crossings to protect them from falling rocks. Whitaker access road was widened for passage of pipe trucks. Other approved access roads were repaired so project vehicles could drive safely on them. Contaminated soils were encountered at EMP 52.46. Fire retardant was sprayed along the active right-of-way. Construction progress during August was slow due to shutdowns based on fire danger. During the last week of August, two construction crews were activated for Segment 2C. Also during the last week of August, a water truck slid off a slick road and landed on an exposed gas line. No injuries occurred and the gas line was x-rayed. It was determined that no damage to the exposed pipe had occurred. All appropriate emergency contacts were made.

Segment 2B (Non-ANF) Construction: Segment 2B runs from Castaic to Sylmar, paralleling I-5. Construction of Segment 2B commenced on November 6, 1997. Primary activities during the month of August are presented in Table 4. Table 5 presents the non-compliance events that occurred on Segment 2B during August.

During August, crews continued to complete all work on the Newhall Land and Farming property between Valencia Boulevard and McBean Parkway, including the tie-in to the mainline at Valencia Boulevard. During the first week of August, the bore at Calgrove was halted when the auger encountered boulders that altered the alignment of the casing. Crews worked throughout August to free the mis-aligned bore sleeve and install a new sleeve. During the third week of August, during backfill operations along The Old Road, an end-dump truck became unbalanced and overturned. No one was injured and spilled fuel was contained immediately.

Table 4. Construction Activities for Segment 2B1

Activity

Milepost (approximate)

Pot-hole

70.32 to 71.80

Trench

69.96 to 71.80

Lower-In

69.77 to 71.71

Coating

69.77 to 71.71

Conduit

69.66 to 71.71

Backfill

69.55 to 71.71

Paving

69.55 to 71.71

Bore (Church Street) - Complete

58.24

Check & Block Valves (South of Church Street) - Complete

59.15

Bore (South of Romero Canyon) - Complete

59.39

Bore (Hillcrest Parkway) - Complete

59.77

Block Valve (Live Oak) - Complete

61.10

Directional Drill (Castaic Creek/Live Oak) - Complete

61.14

Check Valve (South of Live Oak) - Complete

61.56

Bore (South of Highway 126) - Complete

62.78

Check Valve (South of Highway 126) - Complete

63.17

Directional Drill (Santa Clara River) - Complete

63.46

Bore (Feedmill Road) - Complete

63.93

Check Valve (Magic Mtn. Parkway) - Complete

64.01

Bore (PGA Ranch) - Complete

65.38

Bore (PGA Ranch) - Complete

65.52

Bore (PGA Ranch) - Complete

65.62

Block Valve (Pico Canyon Road) - Complete

67.46

Check Valve (Lyons, Old Road) - Complete

68.68

Bore (Calgrove Avenue) - Complete

69.13

Bore (Old Road @ I-5) - Complete

69.99

1. Construction progress from August 3 through August 30.

Table 5. Non-Compliance Events for Segment 2B1

Segment

Mitigation Measure/PC

Description/

Non-Compliance Level

First

Observed

Corrected

Status

2B

SS-5: Adhere to Fire Protection Plan. Welding occurred without standing fire watch - Level 3.

8/26/98

8/26/98

Acceptable

1. Non-compliance reports issued from August 3 through August 30.

Segment 3 Construction: Segment 3 runs from Sylmar to Dodger Stadium, primarily within MTA right-of-way. Construction within the City of San Fernando, between Wolfskill and Jessie Streets (approximately 190 feet), began on September 30, 1997, and was completed on October 7, 1997. Construction of the remaining portions of Segment 3 commenced on October 28. 1997. On February 5, 1998, a mini-crew began work on Segment 3 in the vicinity of Los Feliz (referred to as "Los Feliz" crew). This crew worked primarily at the StorItAll facility and the Glendale Boulevard bore which were completed during April 1998. In April 1998, Segment 3 construction was divided into two spreads (Segment 3A which runs from San Fernando to south of Taylor Yard, and Segment 3B which runs from Taylor Yard to Alameda Street). Primary activities during the month of August are presented in Table 6. No non-compliance events occurred on Segment 3 during August.

Table 6. Construction Activities for Segment 31

Segment

Activity

Milepost (approximate)

Wolfskill to Jessie Streets Cased bore - Completed

78.52

  Pipeline/conduit installation - Completed

78.37 to 78.57

Segment 3A

Trench

95.79 to 96.00

  Lowering-In

95.79 to 96.00

  Coating

95.60 to 96.00

  Conduit

94.58 to 96.00

  Backfill

94.58 to 96.00

  Bore (Maclay Avenue) - Complete

78.02

  Bore (Brand Boulevard) - Complete

78.16

  Bore (Wolfskill Street) - Complete

78.33

  Bore (railroad crossing) - Complete

78.37

  Bore (Paxton Street) - Complete

79.11

  Bore (Pierce Avenue) - Complete

79.93

  Bore (Osborne Street) - Complete

80.74

  Bore (box culvert) - Complete

81.19

  Bore (Branford Street) - Complete

81.29

  Block Valve (Tujunga Wash) - Complete

81.48

  Bore (Sheldon Street) - Complete

82.11

  Bore (Penrose Street) - Complete

83.48

  Bore (Sunland Avenue) - Complete

84.09

  Bore (Arvilla Avenue) - Complete

85.02

  Bore (Buena Vista Avenue) - Complete

86.37

  Block Valve (RITC) - Complete

87.43

  Directional Drill (Burbank Crossing) - Complete

87.48 to 88.65

  Bore (Bekins Way) - Complete

90.86

  Block Valve (Verdugo Wash) - Complete

90.95

  Bore (Aviation Avenue) - Complete

91.21

  Bore (Broadway/Brazil) - Complete

91.69

  Bore (Workers Center) - Complete

91.89

  Bore (Riverdale Avenue) - Complete

92.32

  Block Valve (Hollywood Fault) - Complete

93.36

  Check Valve (Hollywood Fault) - Complete

93.59

  Bore (Glendale Boulevard) - Complete

93.76

  Bore (railroad crossing) - Complete

93.79

  Bore (railroad crossing) - Complete

94.56

  Block Valve (Tyburn Street) - Complete

94.71

  Bore (Sycamore Wash) - Complete

94.92

  Bore (UP railroad crossing) - Complete

95.42

  Block Valve (Los Angeles River) - Complete

95.96

Segment 3B

Lower-In

96.05 to 96.78

  Coating

96.05 to 96.78

  Conduit

96.05 to 96.15

  Backfill

96.05 to 96.15

  Bore (entry road to MTA) - Complete

96.00

  Bore (railroad crossing) - Complete

96.10

  Bore (railroad crossing) - In Progress

97.10

  Bore (railroad crossing) - Complete

97.33

  Block Valve (Cornfield Yard) - Complete

98.48

Los Feliz

Pipeline Installation - Completed

93.14 to 93.78

  Valves (StorItAll) - Completed

93.48

  Bore (Glendale Blvd.) - Completed

93.78

1. Construction progress from August 3 through August 30.

Segment 3A - During August, open cut trenching of West Chevy Chase Drive, instead of boring, was conducted in accordance with approved Variance Request #69. Fiber optic crews completed the tie-in at Olive Street. A crew prepared for the pipe insert into the abandoned SoCal line just north of Allen street. Clean-up activities occurred at Fletcher and Linden Streets.

Segment 3B - During August, construction activities within the MTA facility were completed, with the exception of the bore under the rail tracks at EMP 97.10. On August 27, MTA shutdown all construction activities on MTA property until a void under the tracks was repaired.

Segment 4 Construction: Segment 4 is being constructed by two separate crews. Construction of Segment 4A, from downtown Los Angeles to Watts Junction, began on October 20, 1997, and is being conducted from 7:30 p.m. to 6:00 a.m., Monday night through Friday night, to minimize traffic impacts. A Segment 4A-day crew was added the end of June. Segment 4B construction (daytime), from Watts Junction to the Chevron El Segundo Refinery, commenced on October 23, 1997. Primary activities during the month of August are presented in Table 7. Non-compliance events that occurred on Segment 4 during August are summarized in Table 8.

Segment 4A (nights) - During August, crews worked at both the north and south ends of the segment. A Native American monitor and archaeological specialists monitored the excavation and granite block removal in the Bruno Street environs. Preparation of the Highway 101 overcrossing bridge began for installation of the casing pipe. During the forth week of August, a water hydrant on Nadeau Street was run over by a subcontractor. All appropriate notifications were made and the water feeding the hydrant was shut off.

Segment 4A (days) - During August, construction activities along Segment 4A (days) were completed, including the bore at Fernwood Avenue. Crews will be returning to Segment 4B.

Segment 4B - During the second week of August, Union Pacific Railroad conducted a one-hour safety training for all project personnel. Construction activities were halted on August 21, while a staffing conflict between the contractor and a local contractor associated was resolved. Construction activities resumed on August 25.

Table 7. Construction Activities for Segment 41

Segment

Activity

Milepost (approximate)

4A

(nights)

Pot-hole

98.86 to 99.12, 104.96 to 106.15

  Trench

98.96 to 99.12, 104.89 to 106.13

  Lower-In

99.05 to 99.12, 104.80 to 105.84

  Coating

104.80 to 105.62

  Conduit

104.45 to 105.54

  Backfill

99.12 to 99.28, 104.45 to 105.44

  Block Valve (7th Street) - Complete

100.69

  Bore (railroad crossing) - Complete

102.08

  Block Valve (25th Street) - Complete

102.17

  Bore (Slauson Avenue) - Complete

103.89

  Bore (Randolph Street) - Complete

104.07

  Block Valve (Southgate) - Complete

105.85

4A

(days)

Conduit

106.49 to 106.78

  Backfill

106.49 to 106.78

  Bore (Alameda St. & Fernwood Ave.) - Complete

107.86

  Bore (E. Alameda & Martin Luther King Jr. Blvd) - Complete

108.50

4B

Trench

ESMP 1.40

  Lower-In

ESMP 1.47 to 1.57

  Coating

ESMP 1.51 to 1.62

  Backfill

ESMP 1.80 to 1.88

  Bore (108th Street) - In Progress

ESMP 1.10

  Bore (108th Street) - Completed

ESMP 1.15

  Block Valve (Between 109th and 110th Street) - Complete

ESMP 1.22

  Bore (109th Street) - Complete

ESMP 1.25

  Bore (Compton Street) - Complete

ESMP 1.38

  Bore (by LAFCD, east of Slater) - Complete

ESMP 1.56

  Bore (Slater Avenue) - Complete

ESMP 1.68

  Bore (Central Avenue) - Complete

ESMP 1.70

  Check Valve (by Compton Creek) - Complete

ESMP 1.91

  Bore (Avalon Street) - Complete

ESMP 2.52

  Bore (San Pedro & Emperial Hwy #1) - Complete

ESMP 2.74

  Bore (San Pedro & Emperial Hwy #2) - Complete

ESMP 2.79

  Bore (San Pedro & Emperial Hwy #3) - Complete

ESMP 2.81

  Directional Drill (Hoover to Main) - Complete

ESMP 3.04 to 3.84

  Bore (Vermont Avenue) - Complete

ESMP 4.12

  Bore (Budlong Avenue) - Complete

ESMP 4.34

  Bore (Van Ness Avenue) - Complete

ESMP 5.90

  Bore (Wilkie Avenue) - Complete

ESMP 6.27

  Block Valve (east of Dominguez Channel) - Complete

ESMP 6.36

  Bore (by Dominques Channel) - In Progress

ESMP 6.41

  Bore (Crenshaw Blvd.) - Complete

ESMP 6.46

  Check Valve (east side of Crenshaw) - Complete

ESMP 6.48

  Bore (Prairie Avenue) - Complete

ESMP 7.45

  Bore (York Avenue) - Complete

ESMP 7.51

  Bore (Oxford Avenue) - Complete

ESMP 7.57

  Bore ( Menlo Avenue) - Complete

ESMP 7.64

  Bore (Freeman Ave.) - Complete

ESMP 7.70

  Bore (Cedar Avenue) - Complete

ESMP 7.76

  Bore (Birch Avenue) - Complete

ESMP 7.82

  Bore (Hawthorne Blvd.) - Complete

ESMP 7.99

  Bore (Grevillea Avenue) - Complete

ESMP 8.09

  Bore (Eucalyptus Avenue) - Complete

ESMP 8.34

  Bore (Inglewood Avenue) - Complete

ESMP 8.50

  Directional Drill (El Segundo & I-405) - Complete

ESMP 8.93 to 9.38

  Bore (Aviation Blvd.) - Complete

ESMP 9.60

  Bore (Douglas Blvd) - Complete

ESMP 9.87

  Bore (between Sepulveda & Douglas) - Complete

ESMP 10.44

  Bore (between Sepulveda & Douglas) - Complete

ESMP 10.55

1. Construction progress from August 3 through August 30.

 

Table 8. Non-Compliance Events for Segment 41

Segment

Mitigation Measure/PC

Description/

Non-Compliance Level

First

Observed

Corrected

Status

4B

A-8, P-2(a)* and U-2: Use reclaimed water. Contractor using water from fire hydrant - Level 2.

8/3/98

8/3/98

Acceptable

1. Non-compliance reports issued from August 3 through August 30.

Segment 5 Construction: This segment involved 3 phases of operation, construction of Segment 5A (Dominguez Channel to Sepulveda Blvd. - MP 116.21 to 116.75) has been completed. Construction of Segment 5B (along Alameda Street south of Sepulveda Blvd. and south along Henry Ford to Anaheim Street - MP 116.75 to 118.83) was completed during September 1997. Construction of Segment 5C (remainder of Segment 5 - MP 107.95 to 116.21) commenced on August 29, 1997. Primary activities during the month of August are presented in Table 9. Non-compliance events that occurred on Segment 5 during August are summarized in Table 10.

On August 5, construction of Segment 5C on the Compton Creek levee berm resumed after an extended hiatus. Existing fencing was moved to the west to allow for full right-of-way width while still restricting public access to site and flood channel. A temporary truck crossing was installed at EMP 112.89 across the Union Pacific Railroad tracks. Tie-in to the pipe laid in Fall 1997 was conducted during the latter half of the month.

Table 9. Construction Activities for Segment 51

Activity

Milepost (approximate)

Pot-hole

112.27 to 113.14

Clearing

112.27 to 113.14

Trench

112.27 to 113.14

Lower-In

112.27 to 112.99

Coating

112.27 to 112.99

Conduit

112.27 to 112.95

Backfill

112.27 to 112.95

1. Construction progress from August 3 through August 30.

Table 10. Non-Compliance Events for Segment 51

Segment

Mitigation Measure/PC

Description/

Non-Compliance Level

First

Observed

Corrected

Status

5C

A-2.1: Confine construction activities to approved right-of-way. Vehicles and equipment parked off of right-of-way - Level 3.

8/28/98

8/28/98

Acceptable

1. Non-compliance reports issued from August 3 through August 30.

VARIANCES

During August, the following variances were approved/denied:

Table 11. Variance Approvals/Denials

Variance #

Description

Segment(s) Variance Applies

Agency Decision

69 (resubmittal)

Open cut trenching of West Chevy Chase Drive, City of Glendale

3

Approved

(previously denied)

89

Route change across Tejon Ranch between station numbers 767+60 to 777+54.

1

Approved

92

Reroute between station numbers 2918+09 and 2953+89.

2C

Approved

97

Night construction at Los Feliz Underpass, City of Glendale.

3

Approved

98

Relocation of right-of-way at Colorado Street and San Fernando Road, City of Glendale.

3

Approved

102

Relocate Santa Susana block valve, Los Angeles County.

2B

Approved

103

Open cut (instead of bore) Laval Road, Kern County.

1

Approved

104

Refuel within 0.25 miles of stream courses along The Old Road and San Fernando Road.

2B

Approved

105

Open cut (instead of bore) Grandview Avenue, City of Glendale

3

Approved

106

Night construction along The Old Road and San Fernando Road between stations 3785+65 and 3904+61.

2B

Approved

107

Night construction at Hollywood Way and the MTA right-of-way, City of Burbank.

3

Approved

108

Night construction at Victory Place and the MTA right-of-way, City of Burbank.

3

Approved

 

CONSTRUCTION YARDS/STAGING AREAS

During August, the following construction yards/staging areas were approved/denied:

Table 12. Construction Yard/Staging Area Approvals/Denials

Request #

Construction Yard/Staging Area

Applicable Segment(s)

Agency Decision

51

Seven extra work spaces adjacent to right-of-way.

1

Sites 2, 3, 4, 6 approved; Sites 1, 5, & 7 denied

54

Access roads on Tejon Ranch between station numbers 520+17 and 536+43 from Wheeler Ridge Road, Kern County.

1

Approved

57

Access road and truck turn-arounds

2C

Approved

60

Access roads on non-ANF lands between station numbers 2686+84 and 2991+39 from Templin Hwy and Castaic Road.

2C

Approved

60 (mod)

Use of and improvements to Forest Service roads for Whitaker Station construction.

2C

Approved

63

Extra work space at Templin Highway and "Old" Whitaker Pressure Reduction Station.

2C

Approved

65

Extra work space along shoulder of The Old Road at Weldon Canyon Road, Los Angeles County.

2B

Approved

66

Staging area for erosion repairs at 2nd bore of the Ridge Route.

2A

Approved

67

Additional cut slopes for erosion repairs on ANF.

2A

Approved

68

Extension of waterbars off of the right-of-way for erosion repair on ANF.

2A

Approved

 

Compliance Documentation: PPSI’s general plans and reports have been submitted and approved by the CPUC and ANF. Outstanding plan issues relate only to proposed revisions to approved plans (submitted by PPSI as variance requests, documented above) or updated plans. The remaining compliance issues that must be documented prior to or during construction on each segment relate to: (1) obtaining permits or landowner agreements from local jurisdictions and landowners, (2) completion of Traffic Control Plans and their approval by local jurisdictions, and (3) completion of the landowner, resident, and business notification processes. In addition, during August, pre-construction compliance review for the Whitaker Pressure Relief Station was conducted.

CONSTRUCTION SCHEDULE

Table 13 presents the current construction schedule for Pacific Pipeline.

Table 13. Construction Segment Schedule

Segment

Original Construction Schedule

Revised Construction Start Date

Estimated Construction Completion Date1

Segment 1

July 1, 1997

Under construction since November 5, 1997

October 16, 1998

Segment 2A2

June 2, 1997

Erosion repairs, valve & conduit completion, & revegetation underway since June 18, 1998

August 15, 19984

Segment 2B

Mid-August, 1997

Under construction since November 6, 1997

October 18, 1998

Segment 2C3

Originally scheduled for completion as part of Segment 2A

Under construction since June 22, 1998

September 18, 1998

Segment 3

July 1, 1997

Under construction since September 30, 1997

October 11, 1998

Segment 4A

July 1, 1997

Under construction since October 20, 1997

September 15, 1998

Segment 4B

August 25, 1997

Under construction since October 23, 1997

September 16, 19984

Segment 5

July 1, 1997

Under construction since July 14, 1997

October 1, 19984

Emidio Pump Station

October 1997

Under construction since June 11, 1998

July 29, 19984

Grapevine Pump Station  

Under construction since June 29, 1998

July 29, 19984

Whitaker Pressure Relief Station  

September 1998

September 27, 19985

Lynwood Station  

September 1998

October 22, 19985

El Segundo  

September 1998

October 21, 19985

Wilmington  

September 1998

October 31, 19985

Ultramar  

September 1998

August 14, 19984,6

1. Estimated construction schedule per PPSI, July 23, 1998 (segments only).
2. Initial construction completed from June 27 through November 9, 1997.
3. Templin Highway to ANF southern boundary.
4. Construction has not been completed as planned.
5. Estimated station completion schedule per PPSI, August 24, 1998 memorandum.
6. Not included in August 24, 1998 memorandum from PPSI.

 

PUBLIC ACCESS PROGRAM

• Due to the lack of public interest in visiting the MMCRP Walk-In Sites (that was in operation from July 1997 through February 1998), our Student Interns no longer staff the Valley Family Center site in San Fernando, and the Parents of Watts site in Watts on a scheduled basis. However, project documents and PPSI computers remain at the sites for public use, and MMCRP Student Interns available on an as-needed basis (i.e., by appointment). The project information hotline and project newsletter, provide information on how to make an appointment for the Walk-In Sites

• During August, no members of the public made appointments to visit the MMCRP Walk-In sites in San Fernando and Watts.

• The hotline message and project web site continue to be updated as the project progresses. During August, no messages were left on the hotline, and the web site received 61 hits.

Environmental Justice: As of August, PPSI is in compliance with all construction-related aspects of the mitigation measures applicable to minority populations and low-income populations. These measures include: ML-1 (Community Outreach and Communications Program), ML-2 (Community Partnership Program), ML-3 (Local Community and MBE Hiring Program), and ML-6 (implementation of the BIMP)