The following constitutes the February 1998 Monthly Report for the Pacific Pipeline Mitigation Monitoring, Compliance, and Reporting Program (MMCRP) contract. It should be noted that since the start of construction daily and weekly reports summarizing monitoring activities have been issued and are available on the project web page for review.
CONSTRUCTION MONITORING
Segment 1 Construction: Segment 1 runs from the southern end of the San Joaquin Valley at Emidio, through the Tejon Pass, to the northern boundary of the ANF in Los Angeles County. Construction of Segment 1 commenced on November 5, 1997. Primary activities during the month of February are presented in Table 1. Table 2 presents the non-compliance events for Segment 1 during February.
During February, the bore at Gorman Creek (MP 32.40) was conducted. During the last week of February, traffic control was monitored daily by a Los Angeles County inspector. Rain limited construction activities on February 2, 3, 5, 6, 23, and 24. Because of excessive rainfall during February, trench dewatering was required. Trench dewatering methods were modified to adequately contain and control the volume and turbidity of discharged waters into adjacent fields, stream crossing #29, and Gorman Creek. Snow slowed construction on February 17 and 20.
Table 1. Construction Activities for Segment 11
|
|
Pot-hole | 21.45 to 25.46 |
Trench | 27.09 to 29.58 |
Bending | 25.84 to 29.57 |
Lower-In | 27.09 to 29.57 |
NDT (x-ray) | 25.84 to 29.57 |
Coating | 25.84 to 29.57 |
Conduit | 26.61 to 29.67 |
Backfill | 26.61 to 29.67 |
Bore (Gorman Creek) | 32.40 |
Bore (Copco Road) Completed | 32.71 |
Valve Site (Copco Road) Completed | 32.81 |
1. Construction progress from February 2 through February 28.
Table 2. Non-Compliance Events for Segment 11
Mitigation Measure/PC |
Description/ Non-Compliance Level |
First Observed |
Corrected |
Status |
BAQ.1.7 - Implement remedial measures when measurable increase in turbidity downstream. | Silt-laden water entering marsh adjacent to Gorman Creek - Level 3 | 2/12/98 |
Yes |
Acceptable |
1. Non-compliance reports issued from February 2 to February 28.
Segment 2A (ANF) Construction: Construction within the ANF began on June 27, 1997 and was completed to Templin Highway on November 9, with the exception of some revegetation requirements. On February 7, 1998, the ANF approved the Scope of Work, with comments, for erosion repairs as requested by Mike Wickman (ANF District Ranger) in a letter to PPSI dated December 15, 1997. However, implementation of repair activities was not conducted by PPSI during February due to excessive rainfall. ANF requested that PPSI provide an explanation on the use of the unapproved fiber optic conduit that was installed on ANF lands. Remaining construction within the ANF, from the Templin Highway to the southern ANF boundary, will commence in Spring 1998.
Segment 2B Construction: Segment 2B runs from the southern boundary of the ANF to Sylmar, paralleling I-5. Construction of Segment 2B commenced on November 6, 1997. Primary activities during the month of February are presented in Table 3. No non-compliance events occurred on Segment 2B during February.
During February, traffic control was monitored daily by a Los Angeles County inspector. The directional drill of the Santa Clara River commenced and was completed during February. However, the directional drill fractured out ("frac-out" - inert drilling mud traveled up a natural ground fractures to the surface) numerous times during the month which slowed progress. At each frac-out, containment areas were installed and a suction truck removed the drilling muds. Also during February, an eight-hour hydrostatic test of the Castaic Creek directional drill was successfully completed. Rain limited construction activities on February 2, 3, 6, 17, 23, and 24.
Table 2. Construction Activities for Segment 2B1
Activity |
Milepost (approximate) |
Pot-hole | 59.87 to 61.60 |
Trench | 59.78 to 60.34 |
Lower-In | 59.89 to 60.37 |
Conduit | 60.01 to 60.72 |
Coating | 59.98 to 60.56 |
Backfill | 60.01 to 60.68 |
Paving | 59.97 to 60.72 |
Directional Drill (Castaic Creek) Completed |
61.12 |
Directional Drill (Santa Clara River) - Completed | 64.02 |
1. Construction progress from February 2 to February 28.
Segment 3 Construction: Segment 3 runs from Sylmar to Dodger Stadium. Construction within the City of San Fernando, between Wolfskill and Jessie Streets (approximately 190 feet), began on September 30 and was completed on October 7. Construction of the remaining portions of Segment 3 (referred to as Segment 3B) commenced on October 28. On February 5, a mini-crew began work on Segment 3 in the vicinity of Los Feliz (referred to as Segment 3C). Primary activities during the month of February are presented in Table 4. Table 5 presents the non-compliance events for Segment 3 during February.
Segment 3B - During February, bores were completed at the following roadways along the Segment 3B right-of-way: Paxton Street, Pierce Avenue, Branford Street, Sheldon Street, Penrose Street, Sunland Avenue, and Arvilla Avenue. The bore of Buena Vista Avenue commenced. Emergency crew worked from approximately 6:30 p.m. to 10:00 p.m. on February 6 to secure a Sprint communication line that was in danger of being exposed at Penrose Street. Crew work Sunday, February 8 to clean Tuxford Road intersection and County drains of foreign materials that were not project-related. Crews worked Saturdays and on President Day near Roscoe Elementary School (construction not allowed during school hours).
Segment 3C - Excavation of two valve sites were completed and valves put in place along Segment 3C right-of-way in the StorItAll storage facility driveway. Bore pit excavation at Casitas Street for the Glendale Boulevard bore commenced. Property owner of the StorItAll storage facility halted construction on February 25 due to contract negotiations.
Rain limited construction activities on both Segments 3B and 3C on February 2, 3, 6, 23, and 24.
Table 4. Construction Activities for Segment 31
Segment |
Activity |
Milepost (approximate) |
Wolfskill to Jessie Streets | Cased bore | 78.52 (completed) |
Pipeline/conduit installation | 78.37 to 78.57 (completed) |
|
3B |
Trench | 83.37 to 85.00 |
Lowering-In | 83.35 to 84.97 |
|
NDT (x-ray) | 83.16 to 84.91 |
|
Coating | 83.16 to 84.86 |
|
Conduit | 83.16 to 84.86 |
|
Backfill | 83.05 to 84.83 |
|
Bore (Paxton Street) Completed | 79.11 |
|
Bore (Pierce Avenue) Completed | 79.93 |
|
Bore (Osborne Street) Completed | 80.74 |
|
Bore (Branford Street) Completed | 81.29 |
|
Bore (Sheldon Street) Completed | 82.11 |
|
Bore (Penrose Street) Completed | 83.48 |
|
Bore (Sunland Avenue) Completed |
84.09 |
|
Bore (Arvilla Avenue) Completed |
85.02 |
|
Bore (Buena Vista Avenue) | 86.43 |
|
Valve - Completed | 81.48 |
|
3C |
Pot-hole | 93.14 to 93.75 |
Trench | 93.14 to 93.75 |
|
NDT (x-ray) | 93.14 to 93.75 |
|
Coating | 93.14 to 93.75 |
|
Conduit | 93.14 to 93.75 |
|
Backfill | 93.14 to 93.75 |
|
Bore (Glendale Blvd.) | 93.78 |
|
Valves (StorItAll) | 93.48 |
1. Construction progress from February 2 to February 28.
Table 5. Non-Compliance Events for Segment 31
Segment |
Mitigation Measure/PC |
Description/ Non-Compliance Level |
First Observed |
Corrected |
Status |
3C |
A.7.1 - Vehicles will not idle for more than 2 minutes. | Contractor lowboy was left unattended and idling for more than 10 minutes - Level 2 | 2/10/98 |
Yes |
Acceptable |
Clearance 27 - No clearing or grading shall occur at Los Feliz Yard. | Yard was cleared by front-end loader - Level 1 | 2/10/98 |
Yes |
Acceptable |
1. Non-compliance reports issued from February 2 to February 28.
Segment 4 Construction: Segment 4 is being constructed by two separate crews. Construction of Segment 4A, from downtown Los Angeles to Watts Junction, began on October 20 and is being conducted from 8:00 pm to 5:30 am, Monday night through Friday night, to minimize traffic impacts. Segment 4B construction (day time),
from Watts Junction to the Chevron El Segundo Refinery, commenced on October 23. Primary activities during the month of February are presented in Table 6. Table 7 summarizes the non-compliance events for Segment 4.
Segment 4A - Track removal along the Segment 4A right-of-way was completed in February. Emergency crews worked on Tuesday, February 3 and Sunday, February 8 from 1:00 p.m. until approximately 4:30 p.m. to repair loosened temporary paving and potholes on Alameda Street between Washington Boulevard and 20th Street. Trench walls sloughed at 3rd Street; crew backfilled trench with slurry to stop collapse. On February 12, a representative from the Los Angeles Sheriffs Department presented a personal safety talk for all Segment 4A personnel. On February 18, hydraulic fluid from a backhoe being repaired by the Contractor on Traction Avenue leaked into roadway gutter. PPSI Environmental Inspector worked with contractor to stop flow before it entered the storm drain. Also on February 18, it was discovered that an unmarked, 6-inch sere line had been damaged during previous excavations at the site (early-February). A Los Angeles City utility worked inspected repairs. On February 27, the contractor damaged a marked underground utility. This is the fourth such incident and in under investigation by the CPUC.
Segment 4B - On February 12, a representative from the Los Angeles Sheriffs Department presented a personal safety talk for all Segment 4B personnel. Boring of roadways along the Segment 4B right-of-way continued during February. Spoils were stored along the right-of-way in such a manner as to not cause a visual impact.
Rain limited construction activities on both Segments 4A and/or 4B on February 2, 3, 4, 6, 17, 23, and 24.
Table 6. Construction Activities for Segment 41
Segment |
Activity |
Milepost (approximate) |
4A |
Track removal | 101.90 to 102.01 |
Pot-hole | 102.00 to 102.10 |
|
Saw-cutting | 101.91 to 102.10 |
|
Trench | 100.30 to 102.01 |
|
Lower-In | 100.17 to 102.01 |
|
Welding | 100.16 to 102.01 |
|
Coating | 100.16 to 102.01 |
|
Conduit | 100.16 to 102.02 |
|
Backfill | 99.87 to 102.01 |
|
4B |
Pot-hole | 5.90 (Van Ness Avenue) |
Bore (York Ave.) | 7.52 |
|
Bore (Oxford Ave.) | 7.58 |
|
Bore ( Menlo Ave.) | 7.64 |
|
Bore (Freeman Ave.) | 7.70 |
|
Bore (Cedar Ave.) | 7.76 |
|
Bore (Hawthorne Blvd.) Completed |
7.97 |
|
Bore (Grevillea Ave.) | 8.09 |
|
Bore (Inglewood Ave.) | 8.46 |
|
Bore (Eucalyptus Ave.) | 8.84 |
|
Bore (Aviation Blvd.) Completed |
9.61 |
|
Bore ( Douglas Blvd) completed | 9.84 |
|
Directional Drill (Douglas & Sepulveda) - Completed | 10.60 |
1. Construction progress from February 2 to February 28.
Table 7. Non-Compliance Events for Segment 41
Segment |
Mitigation Measure/PC |
Description/ Non-Compliance Level |
First Observed |
Corrected |
Status |
4A |
SS.2.2 - Use hand tools within 24" of underground structures and in utility intensive areas. | Marked, 1-inch water line cut by backhoe during excavation - Level 3 | 2/27/98 (also observed on 1/30/98, 12/13/97, 12/39/97) |
Under investigation by CPUC |
Unacceptable - Under investigation by CPUC |
1. Non-compliance reports issued from February 2 to February 28.
Segment 5 Construction: This segment involved 3 phases of operation, construction of Segment 5A (Dominguez Channel to Sepulveda Blvd. - MP 116.21 to 116.75) was completed on July 18 with the exception of a section of suspended pipe at Dominguez Channel (approximately 300 feet) and where skips between segments remain. Construction of Segment 5B (along Alameda Street south of Sepulveda Blvd. and south along Henry Ford to Anaheim Street - MP 116.75 to 118.83) was completed during September. Construction of Segment 5C (remainder of Segment 5 - MP 107.95 to 116.21) commenced on August 29. Primary activities during the month of February are presented in Table 8. No non-compliance events occurred on Segment 5 during February.
During February, construction activities on Segment 5C were shut down for the majority of the month while local permits were being secured from Los Angeles County. Construction resumed on February 26. On February 28, a conduit for a mismarked fiber optic line was cracked, but service was not interrupted.
Table 8. Construction Activities for Segment 51
Segment |
Activity |
Milepost (approximate) |
5A |
Completed except where skips between segments remain | 115.62 to 115.87 |
Dominguez Channel crossing - completed | 116.21 |
|
5B |
Completed except where skips between segments remain | 116.75 to 117.30 |
5C |
Pot-hole | 115.62 to 115.87 |
Trench | 115.68; 115.80 to 115.87 |
|
Lower-In | 115.85 to 115.87 |
|
Road Bore (Dominguez Street) | 114.50 (Completed) |
|
Road Bore (Del Amo Blvd) | 113.98 (Completed) |
1. Construction progress from February 26 to 28.
VARIANCES
During February, the following variances were approved/denied:
Table 8. Variance Approvals/Denials
Variance # |
Description |
Segment(s) Variance Applies |
Agency Decision |
41 |
Relocate Castaic Creek check valve. | 2B |
Approved |
43 |
Refueling within 0.25 miles of streams along Peace Valley Road. | 1 |
2 Sites Denied 3 Sites Approved |
44 |
Expedite work space clearance requests (e.g., no CPUC approval). | All |
Denied |
45 |
Open trench Ramona Avenue to install HDPE geomembrane material to protect water well. | 4B |
Approved |
47 |
Refueling within 0.25 miles of streams along Peace Valley Road - additional location requested (see Variance Request #43). | 1 |
Denied |
49 |
Open cutting of Birch Avenue (instead of boring), City of Hawthorne. | 4B |
Approved |
CONSTRUCTION YARDS/STAGING AREAS
During February, the following construction yards/staging areas were approved/denied:
Table 9. Construction Yard/Staging Area Approvals/Denials
Request # |
Construction Yard/Staging Area |
Applicable Segment(s) |
Agency Decision |
25 |
Construction office and materials yard, northwest corner of San Fernando Road and Tyler Avenue, City of San Fernando. | 3, north of Hubbard |
Approved |
26 |
Extra work space/material storage for boring contractor at Castaic Creek (expansion of existing work space area - see Clearance #21), Ol Road near Hasley Canyon Road, Los Angeles County. | 2B |
Approved |
27 |
Construction office and materials yard, 2861 Los Feliz Blvd., Glendale. | 3 |
Approved |
COMPLIANCE DOCUMENTATION
PPSIs general plans and reports have been submitted and approved by the CPUC and ANF. Outstanding plan issues relate only to proposed revisions to approved plans (submitted by PPSI as variance requests, documented above) or updated plans. The remaining compliance issues that must be documented prior to or during construction on each segment relate to: (1) obtaining permits or landowner agreements from local jurisdictions and landowners, (2) completion of Traffic Control Plans and their approval by local jurisdictions, and (3) completion of the landowner, resident, and business notification processes. Because the pre-construction notification process has been completed by PPSI for all segments, future compliance activity will be limited to the three activities noted, and will be managed in the field by the Environmental Monitors.
CONSTRUCTION SCHEDULE
Table 10 presents the current construction schedule for Pacific Pipeline.
Table 10. Construction Segment Schedule
Segment |
Original Construction Schedule |
Revised Construction Start Date |
Estimated Construction Completion Date2 |
Segment 1 | July 1, 1997 |
Under construction since November 5, 1997 |
August 18, 1998 |
Segment 2A | June 2, 1997 |
June 27, 1997 |
Construction completed to Templin Highway November 9, 1997 |
Segment 2B | Mid-August, 1997 |
Under construction since November 6, 1997 |
August 11, 1998 |
Segment 2C1 | Originally scheduled for completion as part of Segment 2A |
May 4, 19982 |
August 4, 1998 |
Segment 3 | July 1, 1997 |
Under construction since September 30, 1997 |
June 17, 1998 |
Segment 4A1 | July 1, 1997 |
Under construction since October 20, 1997 |
August 14, 1998 |
Segment 4A2 | Originally scheduled for completion as part of Segment 4A1 |
April 1, 19982 |
July 17, 1998 |
Segment 4B | August 25, 1997 |
Under construction since October 23, 1997 |
June 15, 1998 |
Segment 5 | July 1, 1997 |
Under construction since July 14, 1997 |
May 28, 1998 |
Emidio Pump Station | October 1997 |
March 26, 19982 |
July 29, 1998 |
Grapevine Pump Station | March 26, 19982 |
July 29, 1998 |
|
Whitaker Pressure Relief Station | May 11, 19982 |
August 10, 1998 |
|
Lynwood Station | April 10, 19982 |
June 9, 1998 |
|
El Segundo | April 27, 19982 |
July 27, 1998 |
|
Wilmington | May 25, 19982 |
August 10, 1998 |
|
Ultramar | June 9, 19982 |
August 14, 1998 |
1. Templin Highway to ANF southern boundary.
2. Estimated construction start date per PPSI, March 9, 1998.
PUBLIC ACCESS PROGRAM
Our Student Interns continued to staff the Watts and San Fernando Walk-In Sites through February 28. No members of the public interested about the pipeline project visited either of the sites. Starting in March 1998, MMCRP Student Interns will be available on an as-needed basis (i.e., by appointment).
The hotline message and project web site continue to be updated as the project progresses. During February, no messages were left on the hotline, and the web site received 60 hits.
Environmental Justice: During the month of February, our Student Interns continued updating matrices of information from the PPSI Local and Minority Hiring Questionnaires. Currently, we are working on extrapolating the final minority percentages from the data.