The following constitutes the July 1998 Monthly Report for the Pacific Pipeline Mitigation Monitoring, Compliance, and Reporting Program (MMCRP) contract. It should be noted that since the start of construction daily and weekly reports summarizing monitoring activities have been issued and are available on the project web site for review.
CONSTRUCTION MONITORING
Segment 1 Construction: Segment 1 runs from the southern end of the San Joaquin Valley at Emidio, through the Tejon Pass, to the northern boundary of the ANF in Los Angeles County. Construction of Segment 1 commenced on November 5, 1997. Primary activities during the month of July are presented in Table 1. No non-compliance events occurred on Segment 1 during July.
During July, construction within the Tejon Wetland (EMP 20.73 to 20.60) was conducted. In San Joaquin kit fox habitat (EMP 0.0 to 15.5), wildlife ramps were installed in open trenches and the PPSI biologist checked the trench each morning prior to the start of work to ensure no wildlife had become entrapped in the trench. During the last week of July, a young badger was moved into the spoil piles on the east side of Interstate 5 (EMP 13.30). The PPSI biologist monitored its location to ensure its protection. During July, potholing at the Emidio Pump Station was completed and construction of the foundation commenced. Cement for the foundation was poured in early morning hours to avoid the high daytime temperatures. Grading and potholing began at the Grapevine Pump Station, but work was halted while asbestos-coated pipe that was discovered during potholing was removed and disposed of by a licensed hazardous materials operator. Limited clearing along the Tejon Bench was conducted the first week of July and equipment was assembled for the Cuddy Creek directional drill (EMP 25.15 to 25.52) the last week of July.
Table 1. Construction Activities for Segment 11
Activity |
Milepost (approximate) |
Pot-hole | 7.44 to 14.39, 19.71 to 19.98 |
Clearing | 10.10 - 10.16, 18.59 to 18.82 |
Trench | 9.19 to 9.90, 11.61 to 14.92, 20.54 to 21.11 |
Lower-In | 9.83 to 10.10, 14.38 to 15.18, 20.54 to 20.98 |
Coating | 9.91 to 10.10, 14.38 to 15.45, 20.54 to 20.98 |
Conduit | 9.91 to 10.10, 14.38 to 15.45, 20.54 to 21.09 |
Backfill | 9.91 to 10.10, 14.38 to 15.45, 20.54 to 21.09 |
Emidio Pump Station | 0.00 |
Bore (Wheeler Ridge Road) - In Progress | 10.63 |
Block Valve (North side California Aqueduct) - In Progress | 12.02 |
Bore (I-5 crossing @ Tejon Ranch) - In Progress | 13.33 |
Grapevine Pump Station | 15.57 |
Bore (I-5, north of Lebec Road overpass) - Complete | 20.79 |
Bore (Lebec Road, south of overpass) - Complete | 21.20 |
Bore (Lebec Road, Specimen Tree #2) - Complete | 24.82 |
Directional Drill (Peace Valley & Lebec Roads, Cuddy Creek) - In Progress | 25.15 to 25.52 |
Check Valve (Peace Valley Road, Cuddy Creek) - Complete | 25.92 |
Bore (Stream Crossing #20) - Complete | 27.43 |
Bore (Stream Crossing #21) - Complete | 27.81 |
Bore (Stream Crossing #23) - Complete | 28.10 |
Block Valve (Gorman Block Valve) - Complete | 28.33 |
Directional Drill (Gorman Slide) - Complete | 28.68 to 29.68 |
Block Valve (San Andreas Block Valve) - Complete | 30.43 |
Bore (Stream Crossing #29) - Complete | 32.38 |
Bore (Stream Crossing #30) - Complete | 32.71 |
Block Valve (Copco Road) - Complete | 32.81 |
1. Construction progress from June 29 through August 2.
Segment 2A/C (ANF) Construction: Construction within the ANF (Segment 2A) began on June 27, 1997 and was completed to Templin Highway on November 9, with the exception of some erosion repair, revegetation, valve, and conduit requirements. This follow-up work commenced in June 1998. Construction of Segment 2C, Templin Highway to southern ANF boundary, commenced on June 22, 1998. Primary activities during the month of July are presented in Table 2. No non-compliance events occurred on Segments 2A or 2C during July.
Segment 2A - During July, work at the valve sites (Copco Road and Reservoir Summit) and installation of fiber optic cable and pull boxes continued. Erosion repair and reseeding activities were also conducted.
Segment 2C - In July, the CPUC and ANF conditionally approved the elimination of the pressure relief tank from the Whitaker Pressure Relief Station. This decision was based on the review of the Whitaker Station Tank Report by Aspen and its technical expert to determine if the elimination of the pressure relief tank was feasible (as concluded by the report).
Table 2. Construction Activities for Segment 2C1
Activity |
Milepost (approximate) |
Pot-hole | 53.03 to 55.95 |
Trench | 54.34 to 56.53 |
Grade | 53.28 to 55.19 |
Lower-In | 55.47 to 56.65 |
Block Valve (Lake Hughes) - In Progress | 56.53 |
Bore (Marple-Violin Canyon Creek) - In Progress | 56.74 |
1. Construction progress from June 29 through August 2.
During July, potholing, grading, and trenching along Segment 2C were conducted. Trenching was slowed by repeated discoveries of unmarked and unexpected underground pipelines. Trenching was halted at EMP 55.07 pending approval from the utility to install pipe under high tension power lines. Excavation of a bore pit and installation of pipe for Marple Canyon Creek was completed. At the request of Los Angeles County Fire Department, fire roads were graded to allow safe ingress/egress along Segment 2C in the canyon between I-5 north and south in the event a fire were to start. Construction activities were halted for a day when high-fire-danger criteria (as determined by the Los Angeles County Fire Marshall) was reached. During the last week of July, several small fires were ignited, but quickly extinguished by fire guards and contractor personnel.
Segment 2B (Non-ANF) Construction: Segment 2B runs from the southern boundary of the ANF to Sylmar, paralleling I-5. Construction of Segment 2B commenced on November 6, 1997. Primary activities during the month of July are presented in Table 3. Table 4 presents the non-compliance events that occurred on Segment 2B during July.
During July, excavation and dewatering of the deep bore pits at Feedmill Road and Calgrove Avenue was conducted. Construction across Newhall Land and Farming property continued, including completion of the tie-in at McBean Parkway. Underground utilities within The Old Road and unmarked storm drains slowed progress during July. Traffic control measures were monitored daily by the Los Angeles County inspector and was modified as necessary to ensure smooth traffic flow through the restricted construction zone.
Table 3. Construction Activities for Segment 2B1
Activity |
Milepost (approximate) |
Pot-hole | 67.93 to 70.32 |
Trench | 67.75 to 69.96 |
Lower-In | 67.70 to 69.77 |
Conduit | 67.37 to 69.55 |
Coating | 67.70 to 69.77 |
Backfill | 67.37 to 69.55 |
Paving | 67.22 to 69.55 |
Bore (Church Street) - Complete | 58.24 |
Check & Block Valves (South of Church Street) - Complete | 59.15 |
Bore (South of Romero Canyon) - Complete | 59.39 |
Bore (Hillcrest Parkway) - Complete | 59.77 |
Block Valve (Live Oak) - Complete | 61.10 |
Directional Drill (Castaic Creek/Live Oak) - Complete | 61.14 |
Check Valve (South of Live Oak) - Complete | 61.56 |
Bore (South of Highway 126) - Complete | 62.78 |
Check Valve (South of Highway 126) - Complete | 63.17 |
Directional Drill (Santa Clara River) - Complete | 63.46 |
Bore (Feedmill Road) - In Progress | 63.93 |
Check Valve (Magic Mtn. Parkway) - Complete | 64.01 |
Bore (PGA Ranch) - Complete | 65.38 |
Bore (PGA Ranch) - Complete | 65.52 |
Bore (PGA Ranch) - Complete | 65.62 |
Valve (Pico Canyon Road) - Complete | 67.46 |
Check Valve (Lyons, Old Road) - Complete | 68.68 |
Bore (Calgrove Avenue) - In Progress | 69.13 |
Bore (Old Road @ I-5) - In Progress | 69.99 |
1. Construction progress from June 29 through August 2.
Table 4. Non-Compliance Events for Segment 2B1
Segment |
Mitigation Measure/PC |
Description/ Non-Compliance Level |
First Observed |
Corrected |
Status |
2B |
B-AQ-1.8: Follow approved Storm Water Pollution Prevention Plan. | Asphalt stored on right-of-way. Level 1 | 7/3/98 |
7/3/98 |
Acceptable |
2B |
B-AQ-3.2.4: Deposit soil where unlikely to enter aquatic system. | Equipment crossing in drainage built with spoil. Level 2 | 7/7/98 |
7/7/98 |
Acceptable |
2B |
SS-2.2: Use hand tools to excavate when within 24 inches of underground utilities. | Marked two-inch phone line cut by a backhoe. Level 3 | 7/29/98 |
7/29/98 |
Acceptable |
1. Non-compliance reports issued from June 29 through August 2.
Segment 3 Construction: Segment 3 runs from Sylmar to Dodger Stadium, primarily within MTA right-of-way. Construction within the City of San Fernando, between Wolfskill and Jessie Streets (approximately 190 feet), began on September 30, 1997, and was completed on October 7, 1997. Construction of the remaining portions of Segment 3 commenced on October 28. 1997. On February 5, 1998, a mini-crew began work on Segment 3 in the vicinity of Los Feliz (referred to as "Los Feliz" crew). This crew worked primarily at the StorItAll facility and the Glendale Boulevard bore which were completed during April 1998. In April 1998, Segment 3 construction was divided into two spreads (Segment 3A which runs from San Fernando to south of Taylor Yard, and Segment 3B which runs from Taylor Yard to Alameda Street). Primary activities during the month of July are presented in Table 5. Table 6 presents the non-compliance events that occurred on Segment 3 during July.
Segment 3A - During July, work was conducted at the following bore sites: Aviation Avenue (EMP 91.21), railroad crossing (EMP 94.56), Sycamore Wash (EMP 94.92), and railroad crossing near Los Angeles River (95.07). Crews continued to work along skipped sections of San Fernando Boulevard, including: Tyburn Street, Casitas Street, and Goodwin Avenue. Construction was also conducted within the MTA right-of-way (EMP 88.68 to 89.02).
Segment 3B - During July, Segment 3B crews worked two shifts: front-end crew (trenching, laying, and welding) worked from 5:30 p.m. to 2:00 a.m. and the back-end crew (tie-in, x-ray, coating, and backfill) worked from 9:30 p.m. to 6:00 a.m. Work was conducted at the deep bore (26 feet) at the north end of Taylor Yard, the bore under the access road to Taylor Yard, and the bore under the rail tracks in Midway Yard.
Table 5. Construction Activities for Segment 31
Segment |
Activity |
Milepost (approximate) |
Wolfskill to Jessie Streets | Cased bore - Completed | 78.52 |
Pipeline/conduit installation - Completed | 78.37 to 78.57 |
|
Segment 3A |
Trench | 94.49 to 95.79 |
Lowering-In | 94.23 to 95.79 |
|
Coating | 94.23 to 95.60 |
|
Conduit | 94.02 to 94.58 |
|
Backfill | 94.02 to 94.58 |
|
Bore (Maclay Avenue) - Complete | 78.02 |
|
Bore (Brand Boulevard) - Complete | 78.16 |
|
Bore (Wolfskill Street) - Complete | 78.33 |
|
Bore (railroad crossing) - Complete | 78.37 |
|
Bore (Paxton Street) - Complete | 79.11 |
|
Bore (Pierce Avenue) - Complete | 79.93 |
|
Bore (Osborne Street) - Complete | 80.74 |
|
Bore (box culvert) - Complete | 81.19 |
|
Bore (Branford Street) - Complete | 81.29 |
|
Valve - Complete | 81.48 |
|
Bore (Sheldon Street) - Complete | 82.11 |
|
Bore (Penrose Street) - Complete | 83.48 |
|
Bore (Sunland Avenue) - Complete | 84.09 |
|
Bore (Arvilla Avenue) - Complete | 85.02 |
|
Bore (Buena Vista Avenue) - Complete | 86.37 |
|
Directional Drill (Burbank Crossing) - Complete | 87.48 to 88.65 |
|
Bore (Bekins Way) - Complete | 90.86 |
|
Bore (Aviation Avenue) - Complete | 91.21 |
|
Bore (Broadway/Brazil) - Complete | 91.69 |
|
Bore (Workers Center) - Complete | 91.89 |
|
Bore (Riverdale Avenue) - Complete | 92.32 |
|
Bore (Glendale Boulevard) - Complete | 93.76 |
|
Bore (railroad crossing) - Complete | 93.79 |
|
Bore (railroad crossing) - Complete | 94.56 |
|
Bore (Sycamore Wash) - Complete | 94.92 |
|
Bore (UP railroad crossing) - Complete | 95.42 |
|
Segment 3B |
Pot-hole | 96.34 to 97.12 |
Trench | 96.34 to 97.12 |
|
Lower-In | 96.34 to 96.95 |
|
Coating | 96.34 to 96.95 |
|
Conduit | 96.34 to 96.36 |
|
Backfill | 96.34 to 96.36 |
|
Bore (entry road to MTA) - Complete | 96.00 |
|
Bore (railroad crossing) - Complete | 96.10 |
|
Bore (railroad crossing) - In Progress | 97.33 |
|
Valve | 98.48 |
|
Los Feliz |
Pipeline Installation - Completed | 93.14 to 93.78 |
Valves (StorItAll) - Completed | 93.48 |
|
Bore (Glendale Blvd.) - Completed | 93.78 |
1. Construction progress from June 29 through August 2.
Table 6. Non-Compliance Events for Segment 31
Segment |
Mitigation Measure/PC |
Description/ Non-Compliance Level |
First Observed |
Corrected |
Status |
3A |
T-5.1: Implement approved Traffic Plan. | Backhoe backed into flowing traffic lanes without flagger. Level 1 | 7/29/98 |
7/29/98 |
Acceptable |
3A |
A-2.1: Construction equipment remain on right-of-way. | Vehicles were parked across street in landscaped area off of right-of-way. Level 2 | 7/2/98 |
7/29/98 |
Acceptable |
1. Non-compliance reports issued from June 29 through August 2.
Segment 4 Construction: Segment 4 is being constructed by two separate crews. Construction of Segment 4A, from downtown Los Angeles to Watts Junction, began on October 20, 1997, and is being conducted from 7:30 p.m. to 6:00 a.m., Monday night through Friday night, to minimize traffic impacts. A Segment 4A-day crew was added the end of June. Segment 4B construction (daytime), from Watts Junction to the Chevron El Segundo Refinery, commenced on October 23, 1997. Primary activities during the month of July are presented in Table 7. Non-compliance events that occurred on Segment 4 during July are summarized in Table 8.
Segment 4A (nights) - During July, construction activities near Commercial Street (EMP 99.38) were completely halted because of the dense concentration of underground utilities until the southern end of the project is completed. Scattered historic artifacts continue to be uncovered, evaluated, and recorded by the project archaeologist and Native American monitor. During the second week of July, workers were evacuated from the area where removal of an abandoned 8-inch gas line was being conducted because of fumes existing the cut pipe. The deep trench at Randolph Street collapsed during the third week of July requiring emergency repairs for continued traffic flow. In the last week of July, contaminated soils were unearthed at Florence Avenue and hand-hewn granite blocks were discovered during asphalt cutting activities. A project memo was issued to remind PPSI that intact hand-hewn granite blocks have been determined to be historically significant and should not be impacted by the project.
Segment 4B (days) - During the first half of July, crews worked north towards Tweedy Boulevard (EMP 107.50). The later half of the month was spent working north up E. Alameda past Illinois Avenue (EMP 106.56) and completed the crossing at Tweedy Boulevard.
Segment 4B - During the first half of July, construction activities were concentrated at the Northrup facility. Crews continued to finish small skipped areas and bring sites up to grade in preparation of paving operations. During July, construction was also conducted east and west of Van Ness Avenue, at Wilkie Avenue, Western Avenue, Normandie Avenue, and at 108th Street
Table 7. Construction Activities for Segment 41
Segment |
Activity |
Milepost (approximate) |
4A (nights) |
Pot-hole | 103.89 to 104.96 |
Trench | 103.45 to 104.89 |
|
Lower-In | 103.30 to 104.80 |
|
Coating | 103.22 to 104.80 |
|
Conduit | 103.11 to 104.45 |
|
Backfill | 103.02 to 104.45 |
|
Block Valve (7th Street) - Complete | 100.69 |
|
Bore (railroad crossing) - Complete | 102.08 |
|
Block Valve (25th Street) - Complete | 102.17 |
|
Bore (Slauson Avenue) - Complete | 103.89 |
|
Bore (Randolph Street) - Complete | 104.07 |
|
Block Valve (Southgate) - Complete | 105.85 |
|
4A (days) |
Pot-hole | 106.45 to 108.50 |
Trench | 106.45 to 108.50 |
|
Lower-In | 106.42 to 108.50 |
|
Coating | 106.42 to 108.50 |
|
Conduit | 106.78 to 108.50 |
|
Backfill | 106.78 to 108.50 |
|
Bore (Alameda St. & Fernwood Ave.) - In Progress | 107.86 |
|
Bore (E. Alameda & Martin Luther King Jr. Blvd) - Complete | 108.50 |
|
4B |
Trench | ESMP 0.95, 4.13, 5.26 |
Lower-In | ESMP 6.27, 6.63 to 7.17 |
|
Coating | ESMP 6.27, 6.63 to 7.17 |
|
Backfill | ESMP 6.27, 6.63 to 7.17 |
|
Bore (108th Street) - In Progress | ESMP 1.16 |
|
Block Valve (Between 109th and 110th Street) - Complete | ESMP 1.22 |
|
Bore (109th Street) - Complete | ESMP 1.25 |
|
Bore (by LAFCD, east of Slater) - Complete | ESMP 1.56 |
|
Bore (Compton Street) - In Progress | ESMP 1.38 |
|
Bore (Slater Avenue) - In Progress | ESMP 1.68 |
|
Bore (Central Avenue) - In Progress | ESMP 1.70 |
|
Check Valve (by Compton Creek) - Complete | ESMP 1.91 |
|
Bore (Avalon Street) - Complete | ESMP 2.52 |
|
Bore (San Pedro & Emperial Hwy #1) - Complete | ESMP 2.74 |
|
Bore (San Pedro & Emperial Hwy #2) - In Progress | ESMP 2.79 |
|
Bore (San Pedro & Emperial Hwy #3) - Complete | ESMP 2.81 |
|
Directional Drill (Hoover to Main) - Complete | ESMP 3.04 to 3.84 |
|
Bore (Vermont Avenue) - Complete | ESMP 4.12 |
|
Bore (Budlong Avenue) - Complete | ESMP 4.34 |
|
Bore (Van Ness Avenue) - Complete | ESMP 5.90 |
|
Bore (Wilkie Avenue) - Complete | ESMP 6.27 |
|
Block Valve (east of Dominguez Channel) - Complete | ESMP 6.36 |
|
Bore (by Dominques Channel) - In Progress | ESMP 6.41 |
|
Bore (Crenshaw Blvd.) - Complete | ESMP 6.46 |
|
Check Valve (east side of Crenshaw) - Complete | ESMP 6.48 |
|
Bore (Prairie Avenue) - Complete | ESMP 7.45 |
|
Bore (York Avenue) - Complete | ESMP 7.51 |
|
Bore (Oxford Avenue) - Complete | ESMP 7.57 |
|
Bore ( Menlo Avenue) - Complete | ESMP 7.64 |
|
Bore (Freeman Ave.) - Complete | ESMP 7.70 |
|
Bore (Cedar Avenue) - Complete | ESMP 7.76 |
|
Bore (Birch Avenue) - Complete | ESMP 7.82 |
|
Bore (Hawthorne Blvd.) - Complete | ESMP 7.99 |
|
Bore (Grevillea Avenue) - Complete | ESMP 8.09 |
|
Bore (Eucalyptus Avenue) - Complete | ESMP 8.34 |
|
Bore (Inglewood Avenue) - Complete | ESMP 8.50 |
|
Directional Drill (El Segundo & I-405) - Completed | ESMP 8.93 to 9.38 |
|
Bore (Aviation Blvd.) - Complete | ESMP 9.60 |
|
Bore (Douglas Blvd) - Complete | ESMP 9.87 |
|
Bore (between Sepulveda & Douglas) - Complete | ESMP 10.44 |
|
Bore (between Sepulveda & Douglas) - Complete | ESMP 10.55 |
1. Construction progress from June 29 through August 2.
Table 8. Non-Compliance Events for Segment 41
Segment |
Mitigation Measure/PC |
Description/ Non-Compliance Level |
First Observed |
Corrected |
Status |
4A (days) |
SS-2.2: Use hand tools to excavate when within 24-inches of underground utilities. | Marked water line damaged by a backhoe. Level 3 | 7/24/98 |
7/24/98 |
Acceptable |
1. Non-compliance reports issued from June 29 through August 2.
Segment 5 Construction: This segment involved 3 phases of operation, construction of Segment 5A (Dominguez Channel to Sepulveda Blvd. - MP 116.21 to 116.75) has been completed. Construction of Segment 5B (along Alameda Street south of Sepulveda Blvd. and south along Henry Ford to Anaheim Street - MP 116.75 to 118.83) was completed during September 1997. Construction of Segment 5C (remainder of Segment 5 - MP 107.95 to 116.21) commenced on August 29, 1997. No construction occurred on Segment 5C during July.
VARIANCES
During July, the following variances were approved/denied:
Table 7. Variance Approvals/Denials
Variance # |
Description |
Segment(s) Variance Applies |
Agency Decision |
88 |
Relocate fiber optic cable in Burbank on MTA right-of-way. | 3 |
Approved |
90 |
Refuel within 0.25 miles of Compton Creek. | 4 |
Approved |
91 |
Open cut trenching of Lebec Road, Tejon Ranch, Kern County. | 1 |
Approved |
93 |
Refuel within 0.25 miles of Towsley Canyon near Station 3649+81 and in extra work space at Station 3647+56. | 2B |
Approved |
94 |
Modify construction start time from 7:00 a.m. to 5:00 a.m. during "High Fire Danger Season" on rural lands between Valencia Blvd. And McBean Parkway. | 2C |
Approved |
96 |
Night construction at Tuxford Avenue, City of LA. | 3 |
Approved |
100 |
Reroute between stations 2686+84 to 2708+88, south of Templin Highway. | 2C |
Approved |
CONSTRUCTION YARDS/STAGING AREAS
During July, the following construction yards/staging areas were approved/denied:
Table 8. Construction Yard/Staging Area Approvals/Denials
Request # |
Construction Yard/Staging Area |
Applicable Segment(s) |
Agency Decision |
47 |
Extra work space along Compton Creek on LAFCD levee. | 5 |
Approved |
48 |
Additional construction yard and offices, and pumping of water for dust abatement and compaction. | 1 |
Approved |
50 |
Access roads on Tejon Ranch to access project right-of-way. | 1 |
Approved |
52 |
Two excavation locations to obtain fill for erosion repairs. | 2A |
Approved |
53 |
Access roads on Tejon Ranch, from Laval Road to California Aqueduct. | 1 |
Approved |
55 |
Material and equipment storage areas at intersection of Bruno Street and Alameda Street, City of Los Angeles | 4A |
Approved |
56 |
Extra work space at UPRR and San Pedro Street. | 4B |
Approved |
58 |
Extra work space at The Old Road and Calgrove Boulevard. | 2B |
Approved |
59 |
Materials and equipment storage area for directional drill, Auto Drive South, Compton. | 5 |
Approved |
61 |
Relocate water tank from Reservoir Summit staging area to Road 15 staging area. | 2A |
Approved |
62 |
Extra work space at Valencia Boulevard and Newhall Ranch PGA Golf Course. | 2B |
Approved |
64 |
Minor road repairs along the Old Ridge Route. | 2A |
Approved |
Compliance Documentation: PPSIs general plans and reports have been submitted and approved by the CPUC and ANF. Outstanding plan issues relate only to proposed revisions to approved plans (submitted by PPSI as variance requests, documented above) or updated plans. The remaining compliance issues that must be documented prior to or during construction on each segment relate to: (1) obtaining permits or landowner agreements from local jurisdictions and landowners, (2) completion of Traffic Control Plans and their approval by local jurisdictions, and (3) completion of the landowner, resident, and business notification processes.
In July, the CPUC and ANF conditionally approved the elimination of the pressure relief tank from the Whitaker Pressure Relief Station. This decision was based on the review of the Whitaker Station Tank Report by Aspen and its technical expert to determine if the elimination of the pressure relief tank was feasible (as concluded by the report).
CONSTRUCTION SCHEDULE
Table 9 presents the current construction schedule for Pacific Pipeline.
Table 9. Construction Segment Schedule
Segment |
Original Construction Schedule |
Revised Construction Start Date |
Estimated Construction Completion Date1 |
Segment 1 | July 1, 1997 |
Under construction since November 5, 1997 |
October 16, 1998 |
Segment 2A2 | June 2, 1997 |
Erosion repairs, valve & conduit completion, & revegetation underway since June 18, 1998 |
August 15, 1998 |
Segment 2B | Mid-August, 1997 |
Under construction since November 6, 1997 |
October 18, 1998 |
Segment 2C3 | Originally scheduled for completion as part of Segment 2A |
Under construction since June 22, 1998 |
September 18, 1998 |
Segment 3 | July 1, 1997 |
Under construction since September 30, 1997 |
October 11, 1998 |
Segment 4A | July 1, 1997 |
Under construction since October 20, 1997 |
September 15, 1998 |
Segment 4B | August 25, 1997 |
Under construction since October 23, 1997 |
September 16, 19984 |
Segment 5 | July 1, 1997 |
Under construction since July 14, 1997 |
October 1, 19984 |
Emidio Pump Station | October 1997 |
Under construction since June 11, 1998 |
July 29, 19984 |
Grapevine Pump Station | Under construction since June 29, 1998 |
July 29, 19984 |
|
Whitaker Pressure Relief Station | August 1998 |
August 10, 1998 |
|
Lynwood Station | August 1998 |
June 9, 19984 |
|
El Segundo | August 1998 |
July 27, 19984 |
|
Wilmington | August 1998 |
August 10, 1998 |
|
Ultramar | August 1998 |
August 14, 1998 |
1. Estimated construction schedule per PPSI, July 23, 1998 (segments only).
2. Initial construction completed from June 27 through November 9, 1997.
3. Templin Highway to ANF southern boundary.
4. Construction has not been completed as planned.
PUBLIC ACCESS PROGRAM
Due to the lack of public interest in visiting the MMCRP Walk-In Sites (that was in operation from July 1997 through February 1998), our Student Interns no longer staff the Valley Family Center site in San Fernando, and the Parents of Watts site in Watts on a scheduled basis. However, project documents and PPSI computers remain at the sites for public use, and MMCRP Student Interns available on an as-needed basis (i.e., by appointment). The project information hotline and project newsletter, provide information on how to make an appointment for the Walk-In Sites
During July, no members of the public made appointments to visit the MMCRP Walk-In sites in San Fernando and Watts.
The hotline message and project web site continue to be updated as the project progresses. During July, no messages were left on the hotline, and the web site received 119 hits.
Environmental Justice: As of July, PPSI is in compliance with all construction-related aspects of the mitigation measures applicable to minority populations and low-income populations. These measures include: ML-1 (Community Outreach and Communications Program), ML-2 (Community Partnership Program), ML-3 (Local Community and MBE Hiring Program), and ML-6 (implementation of the BIMP)