Table 1. Construction Activities for Segment 11

Activity

Milepost (approximate)

Trench

17.93 to 18.10, 21.48 to 21.69

Lower-In

15.41 to 15.90, 17.97 to 18.10, 21.48 to 21.68

Coating

15.41 to 15.98, 17.97 to 18.10, 21.50 to 21.68

Conduit/Backfill

15.41 to 17.12, 18.00 to 18.08, 21.51 to 21.65

Emidio Pump Station - In Progress

0.00

Bore (Highway 166) - Complete

1.18

Bore (Aqueduct Access Road B) - Complete

6.00

Bore (Stream Crossing #4) - Complete

9.03

Bore (Tecuya Creek/I-5) - Complete

9.88

Bore (Wheeler Ridge Road) - Complete

10.63

Block Valve (North side California Aqueduct) - Complete

12.02

Bore (California Aqueduct) - Complete

12.22

Bore (I-5 crossing @ Tejon Ranch) - Complete

13.33

Bore (I-5/Grapevine) - Complete

14.62

Bore (Stream Crossing #9) - Complete

15.35

Grapevine Pump Station - In Progress

15.57

Bore (I-5 Truck Ramp) - Complete

16.49

Bore (SCE Tower) - Complete

20.28

Bore (I-5, north of Lebec Road overpass) - Complete

20.79

Bore (Lebec Road, south of overpass) - Complete

21.20

Bore (Lebec Road, Specimen Tree #2) - Complete

24.82

Directional Drill (Peace Valley & Lebec Roads, Cuddy Creek) - Complete

25.15 to 25.52

Bore (Cuddy Creek Tributary) - Complete

25.47

Check Valve (Peace Valley Road, Cuddy Creek) - Complete

25.92

Bore (Stream Crossing #20) - Complete

27.43

Bore (Stream Crossing #21) - Complete

27.81

Bore (Stream Crossing #23) - Complete

28.10

Block Valve (Gorman) - Complete

28.33

Directional Drill (Gorman Slide) - Complete

28.68 to 29.68

Block Valve (San Andreas) - Complete

30.43

Bore (Stream Crossing #29) - Complete

32.38

Bore (Stream Crossing #30) - Complete

32.71

Block Valve (Copco Road) - Complete

32.81

1. Construction progress from November 30 through January 3.