Table 3. Construction Activities for Segment 2B1
Activity |
Milepost (approximate) |
Trench | 71.40 to 72.64 |
Lower-In | 72.15 to 72.25 |
Coating | 72.15 to 72.25 |
Conduit | 72.23 to 72.64 |
Backfill | 72.23 to 72.64 |
Bore (Church Street) - Complete | 58.24 |
Check & Block Valves (South of Church Street) - Complete | 59.15 |
Bore (South of Romero Canyon) - Complete | 59.39 |
Bore (Hillcrest Parkway) - Complete | 59.77 |
Block Valve (Live Oak) - Complete | 61.10 |
Directional Drill (Castaic Creek/Live Oak) - Complete | 61.14 |
Check Valve (South of Live Oak) - Complete | 61.56 |
Bore (South of Highway 126) - Complete | 62.78 |
Check Valve (South of Highway 126) - Complete | 63.17 |
Directional Drill (Santa Clara River) - Complete | 63.46 |
Bore (Feedmill Road) - Complete | 63.93 |
Check Valve (Magic Mtn. Parkway) - Complete | 64.01 |
Bore (PGA Ranch) - Complete | 65.38 |
Bore (PGA Ranch) - Complete | 65.52 |
Bore (PGA Ranch) - Complete | 65.62 |
Block Valve (Pico Canyon Road) - Complete | 67.46 |
Check Valve (Lyons, Old Road) - Complete | 68.68 |
Bore (Calgrove Avenue) - Complete | 69.13 |
Bore (Old Road @ I-5) - Complete | 69.99 |
Block Valve (Balboa Blvd) - Complete | 73.81 |
1. Construction progress from November 30 through January 3.