Table 3. Construction Activities for Segment 2B1

Activity

Milepost (approximate)

Trench

71.40 to 72.64

Lower-In

72.15 to 72.25

Coating

72.15 to 72.25

Conduit

72.23 to 72.64

Backfill

72.23 to 72.64

Bore (Church Street) - Complete

58.24

Check & Block Valves (South of Church Street) - Complete

59.15

Bore (South of Romero Canyon) - Complete

59.39

Bore (Hillcrest Parkway) - Complete

59.77

Block Valve (Live Oak) - Complete

61.10

Directional Drill (Castaic Creek/Live Oak) - Complete

61.14

Check Valve (South of Live Oak) - Complete

61.56

Bore (South of Highway 126) - Complete

62.78

Check Valve (South of Highway 126) - Complete

63.17

Directional Drill (Santa Clara River) - Complete

63.46

Bore (Feedmill Road) - Complete

63.93

Check Valve (Magic Mtn. Parkway) - Complete

64.01

Bore (PGA Ranch) - Complete

65.38

Bore (PGA Ranch) - Complete

65.52

Bore (PGA Ranch) - Complete

65.62

Block Valve (Pico Canyon Road) - Complete

67.46

Check Valve (Lyons, Old Road) - Complete

68.68

Bore (Calgrove Avenue) - Complete

69.13

Bore (Old Road @ I-5) - Complete

69.99

Block Valve (Balboa Blvd) - Complete

73.81

1. Construction progress from November 30 through January 3.