Table 6. Construction Activities for Segment 31
Segment |
Activity |
Milepost (approximate) |
Wolfskill to Jessie Streets | Cased bore - Complete | 78.52 |
Pipeline/conduit installation - Complete | 78.37 to 78.57 |
|
Segment 3A |
Bore (Maclay Avenue) - Complete | 78.02 |
Bore (Brand Boulevard) - Complete | 78.16 |
|
Bore (Wolfskill Street) - Complete | 78.33 |
|
Bore (railroad crossing) - Complete | 78.37 |
|
Bore (Paxton Street) - Complete | 79.11 |
|
Bore (Van Nuys Blvd) - Complete | 79.65 |
|
Bore (Pierce Avenue) - Complete | 79.93 |
|
Bore (Osborne Street) - Complete | 80.74 |
|
Bore (box culvert) - Complete | 81.19 |
|
Bore (Branford Street) - Complete | 81.29 |
|
Block Valve (Tujunga Wash) - Complete | 81.48 |
|
Bore (Sheldon Street) - Complete | 82.11 |
|
Bore (Tuxford Street) - In Progress | 83.21 |
|
Bore (Penrose Street) - Complete | 83.48 |
|
Bore (Sunland Avenue) - Complete | 84.09 |
|
Bore (Arvilla Avenue) - Complete | 85.02 |
|
Bore (Buena Vista Avenue) - Complete | 86.37 |
|
Block Valve (RITC) - Complete | 87.43 |
|
Directional Drill (Burbank Crossing) - Complete | 87.48 to 88.65 |
|
Block Valve (Allen Avenue) - Complete | 89.43 |
|
Bore (Sonora Avenue) - Complete | 90.04 |
|
Bore (Bekins Way) - Complete | 90.86 |
|
Block Valve (Verdugo Wash) - Complete | 90.95 |
|
Bore (Aviation Avenue) - Complete | 91.21 |
|
Bore (Broadway/Brazil) - Complete | 91.69 |
|
Bore (Workers Center) - Complete | 91.89 |
|
Bore (Riverdale Avenue) - Complete | 92.32 |
|
Block Valve (Hollywood Fault) - Complete | 93.36 |
|
Check Valve (Hollywood Fault) - Complete | 93.59 |
|
Bore (Glendale Boulevard) - Complete | 93.76 |
|
Bore (railroad crossing) - Complete | 93.79 |
|
Bore (railroad crossing) - Complete | 94.56 |
|
Block Valve (Tyburn Street) - Complete | 94.71 |
|
Bore (Sycamore Wash) - Complete | 94.92 |
|
Bore (UP railroad crossing) - Complete | 95.42 |
|
Block Valve (Los Angeles River) - Complete | 95.96 |
|
Segment 3B |
Bore (entry road to MTA) - Complete | 96.00 |
Bore (railroad crossing) - Complete | 96.10 |
|
Bore (railroad crossing) - Complete | 97.10 |
|
Bore (railroad crossing) - Complete | 97.33 |
|
Bore (railroad crossing) - Complete | 97.35 |
|
Block Valve (Cornfield Yard) - Complete | 98.48 |
|
Segment 3C |
Trench | 73.86 to 73.97 |
Lower-In | 73.29 to 74.50 |
|
Coating | 73.29 to 74.65 |
|
Conduit | 73.29 to 75.21 |
|
Backfill | 73.29 to 75.21 |
|
Bore (railroad north of Grapevine Creek) - Complete | 74.05 |
|
Bore (Roxford Street) - Complete | 75.42 |
|
Block Valve (Sylmar) - Complete | 76.00 |
|
Block Valve - Complete | 76.63 |
|
Bore (Hubbard Street) - Complete | 77.33 |
|
Los Feliz |
Pipeline Installation - Complete | 93.14 to 93.78 |
Valves (StorItAll) - Complete | 93.48 |
|
Bore (Glendale Blvd.) - Complete | 93.78 |
1. Construction progress from November 2 through November 29.