Table 7. Construction Activities for Segment 41
Segment |
Activity |
Milepost (approximate) |
Segment 4A (nights) |
Bore (College Street) - Complete | 98.75 |
Block Valve (7th Street) - Complete | 100.69 |
|
Bore (railroad crossing) - Complete | 102.08 |
|
Block Valve (25th Street) - Complete | 102.17 |
|
Bore (Slauson Avenue) - Complete | 103.89 |
|
Bore (Randolph Street) - Complete | 104.07 |
|
Block Valve (Southgate) - Complete | 105.85 |
|
Bore (92nd Street) - Complete | 106.45 |
|
Segment 4A (days) |
Bore (Alameda St. & Fernwood Ave.) - Complete | 107.86 |
Bore (E. Alameda & Martin Luther King Jr. Blvd) - Complete | 108.50 |
|
Segment 4B |
Backfill | 1.11, 1.16 |
Lynwood Station - In Progress | ESMP 0.00 |
|
Bore (108th Street) - Complete | ESMP 1.10 |
|
Bore (108th Street) - Complete | ESMP 1.15 |
|
Block Valve (Between 109th and 110th Street) - Complete | ESMP 1.22 |
|
Bore (109th Street) - Complete | ESMP 1.25 |
|
Bore (Compton Street) - Complete | ESMP 1.38 |
|
Bore (by LAFCD, east of Slater) - Complete | ESMP 1.56 |
|
Bore (Slater Avenue) - Complete | ESMP 1.68 |
|
Bore (Central Avenue) - Complete | ESMP 1.70 |
|
Check Valve (by Compton Creek) - Complete | ESMP 1.91 |
|
Bore (Avalon Street) - Complete | ESMP 2.52 |
|
Bore (San Pedro & Emperial Hwy #1) - Complete | ESMP 2.74 |
|
Bore (San Pedro & Emperial Hwy #2) - Complete | ESMP 2.79 |
|
Bore (San Pedro & Emperial Hwy #3) - Complete | ESMP 2.81 |
|
Directional Drill (Hoover to Main) - Complete | ESMP 3.04 to 3.84 |
|
Bore (Vermont Avenue) - Complete | ESMP 4.12 |
|
Bore (Budlong Avenue) - Complete | ESMP 4.34 |
|
Bore (Western Avenue) - Complete | ESMP 5.40 |
|
Bore (Van Ness Avenue) - Complete | ESMP 5.90 |
|
Bore (Wilkie Avenue) - Complete | ESMP 6.27 |
|
Block Valve (east of Dominguez Channel) - Complete | ESMP 6.36 |
|
Bore (by Dominguez Channel) - Complete | ESMP 6.41 |
|
Bore (Crenshaw Blvd.) - Complete | ESMP 6.46 |
|
Check Valve (east side of Crenshaw) - Complete | ESMP 6.48 |
|
Bore (Prairie Avenue) - Complete | ESMP 7.45 |
|
Bore (York Avenue) - Complete | ESMP 7.51 |
|
Bore (Oxford Avenue) - Complete | ESMP 7.57 |
|
Bore ( Menlo Avenue) - Complete | ESMP 7.64 |
|
Bore (Freeman Ave.) - Complete | ESMP 7.70 |
|
Bore (Cedar Avenue) - Complete | ESMP 7.76 |
|
Bore (Birch Avenue) - Complete | ESMP 7.82 |
|
Bore (Hawthorne Blvd.) - Complete | ESMP 7.99 |
|
Bore (Grevillea Avenue) - Complete | ESMP 8.09 |
|
Bore (Eucalyptus Avenue) - Complete | ESMP 8.34 |
|
Bore (Inglewood Avenue) - Complete | ESMP 8.50 |
|
Directional Drill (El Segundo & I-405) - Complete | ESMP 8.93 to 9.38 |
|
Bore (Aviation Blvd.) - Complete | ESMP 9.60 |
|
Bore (Douglas Blvd) - Complete | ESMP 9.87 |
|
Bore (between Sepulveda & Douglas) - Complete | ESMP 10.44 |
|
Bore (between Sepulveda & Douglas) - Complete | ESMP 10.55 |
|
Bores (Sepulveda & Allied Yard) - Complete | ESMP 10.78 |
|
El Segundo Station - In Progress | ESMP 10.78 |
1. Construction progress from November 2 through November 29.