CPUC/ANF Environmental Monitoring Activities Pacific Pipeline Construction Project |
Aspen Environmental Group | Saturday, January 09, 1999 |
The following is a brief summary of the environmental monitoring activities that were completed between January 09, 1999 1:00 and 1:00 on January 10, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.
Construction Highlights
01/09/99 (Saturday)Segment 1 (Emidio Pump Station to Copco Road): Report for 9 January 1999: Fiber optic crews worked pulling cable north of the Warbler Skip, as well as on Tejon Bench. Coating worked on five welds on the north end of Tejon Bench. Crews at Grapevine Creek continued to work on the tie in on the north side, and the ditch on the south side. Ditch was cleaned out and fiber optic conduit was strung by Grapevine Station. The ditch crew at the top of Grapevine Road, at the bore site, continued to have slow progress due to the cross lines.
Inspection Summar
In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.
Non-Compliance Reports (NCR's) Issued
No new non-compliance reports were issued during the last reporting period.
Non-Compliance Resolution Reports (NCRR's) Issued
No new non-compliance reports were issued during the last reporting period.
Summary of Follow-up Items for Today
No follow-up items were reported for today.