Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Friday, January 15, 1999
   

The following is a brief summary of the environmental monitoring activities that were completed between January 15, 1999 1:00 and 1:00 on January 16, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

01/15/99 (Friday)

Segment 1 (Emidio Pump Station to Copco Road): Report for 15 January 1999: Dewatering began at Stream Crossing #1 after the successful hydrotest of the final section of pipe between the Warbler Skip and Grapevine Station. Welding and x-ray of surplus pipe and pups continued along Highway 166. Backfill moved forward at the bore site for I-5/Tejon, on the west side. General clean up was done segment wide, as well as fence repair on Tejon Bench. Cleaning pigs were run through the section of pipe between Copco Road and Cuddy Creek, after the water that stood in the pipe for an extended period of time was discharged into Cuddy Creek Tributary.

Segment 5 (Lynwood to Long Beach): Report for 1-15-99. Crews completed insertion of pipe through the Edison bore near EMP 113.5. South of the Tosco refinery crews continued welding 40' sections of pipe together and staging pipe for the Huntway project. Meanwhile, crews backfilled drain lines, collected debris and pulled wire for the valves. In addition, crews walked the station to create a punch list. Segment 4B (Lynwod to El Segundo): Crews continued clean up, pressure washing of the brick face and removal of scaffolding at the Lynwood station site.

Inspection Summar

In the past 24 hours, 2 inspection event(s) were reported for 2 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.