CPUC/ANF Environmental Monitoring Activities Pacific Pipeline Construction Project |
Aspen Environmental Group | Friday, February 05, 1999 |
The following is a brief summary of the environmental monitoring activities that were completed between February 05, 1999 1:00 and 1:00 on February 06, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.
Construction Highlights
02/05/99 (Friday)Segment 5 (Lynwood to Long Beach): Report for 2-5-99. Crews exposed the end of the bore casing on Lomita Blvd and completed a short section of trench. In addition, one segment of pipe was lowered into the ditch on the southern end of the Huntway section while crews worked to coat several tube turns on the 16'' pipe. No work was conducted at the Edison site although crews removed scaffolding and placed rock around the Lynwood station.
Inspection Summar
In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.
Non-Compliance Reports (NCR's) Issued
No new non-compliance reports were issued during the last reporting period.
Non-Compliance Resolution Reports (NCRR's) Issued
No new non-compliance reports were issued during the last reporting period.
Summary of Follow-up Items for Today
No follow-up items were reported for today.