Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Monday, February 08, 1999
   

The following is a brief summary of the environmental monitoring activities that were completed between February 08, 1999 1:00 and 1:00 on February 09, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

02/08/99 (Monday)

Segment 5 (Lynwood to Long Beach): Report for 2-8-99. Crews completed 140' of trench, set 80' of pipe in the ditch and one weld at the southern end of the Huntway section. In addition, crews completed the bore from the Wilmington refinery to Lomita St then removed the sled and machine from the right of way. Meanwhile, crews cored several lifting holes into the vault top at the Edison tie-in site near EMP 113.5. At Lynwood station crews completed removal of the scaffolding while coating crews prepared to spray an anti-graffiti coat on the exterior walls.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.